373 original concept-focused flashcards organized in exam-domain order: 1. Project Management Concepts (191), 2. Project Life Cycle Phases (65), 3. Tools and Documentation (48), 4. Basics of IT and Governance (69). Includes methodology distinctions, roles, change control, risks, scheduling, testing, procurement, lifecycle artifacts, charts, security, cloud models, operational releases, and supporting calculations. Coverage checked against CompTIA PK0-005 objectives v6.0. Supplemental formulas extend core coverage. Study aid, not official exam questions; combine with scenario practice.

373 Terms

1
New cards

1 | Concepts — Project

A temporary effort that creates a unique result, with a defined purpose and start and finish.

2
New cards

1 | Concepts — Operations

Ongoing, repeatable work that sustains the business; a project may deliver a capability to operations.

3
New cards

1 | Concepts — Program

Related projects coordinated together to obtain benefits unavailable from managing each separately.

4
New cards

1 | Concepts — Portfolio

Projects, programs, and other work selected and managed to advance organizational strategy.

5
New cards

1 | Concepts — Waterfall

A predictive approach that plans work upfront and progresses through ordered phases; useful when requirements are stable.

6
New cards

1 | Concepts — Agile

An adaptive approach that delivers value in small increments and uses frequent feedback to adjust plans.

7
New cards

1 | Concepts — Hybrid approach

Combines predictive planning with adaptive delivery where different parts of the work need different controls.

8
New cards

1 | Concepts — Method selection

Consider requirement uncertainty, change tolerance, budget, deadlines, culture, industry constraints, and team availability.

9
New cards

1 | Concepts — Scrum

An Agile framework using Sprints, clear accountabilities, inspection, and adaptation to deliver usable increments.

10
New cards

1 | Concepts — Kanban

A flow-based method that visualizes work and limits work in progress to expose bottlenecks and improve throughput.

11
New cards

1 | Concepts — Work in progress (WIP) limit

A cap on simultaneous work in a workflow stage; helps finish work before starting more.

12
New cards

1 | Concepts — PRINCE2

A project management method emphasizing continued business justification, defined roles, stages, and management by exception.

13
New cards

1 | Concepts — SAFe (Scaled Agile Framework)

A framework for coordinating Agile delivery across multiple teams and broader enterprise planning.

14
New cards

1 | Concepts — XP (Extreme Programming)

An Agile development approach emphasizing technical practices such as pair programming, test-first development, and frequent integration.

15
New cards

1 | Concepts — DevOps

Collaboration and automation connecting development and operations to improve software delivery and reliability.

16
New cards

1 | Concepts — DevSecOps

Integrates security practices into development and operations throughout delivery rather than waiting until the end.

17
New cards

1 | Concepts — SDLC (Software Development Life Cycle)

The activities used to create and maintain software, including requirements, design, building, testing, deployment, and maintenance.

18
New cards

1 | Concepts — Sprint

A fixed-length Scrum event of one month or less in which the team works toward a Sprint Goal.

19
New cards

1 | Concepts — Sprint Goal

The single objective that gives a Sprint coherence and guides tradeoffs during the Sprint.

20
New cards

1 | Concepts — Sprint planning

The team determines why the Sprint is valuable, what can be delivered, and how the work will be done.

21
New cards

1 | Concepts — Daily Scrum

A short daily event for Developers to inspect progress toward the Sprint Goal and adapt their work plan.

22
New cards

1 | Concepts — Sprint review

The team and stakeholders inspect the increment and discuss what to do next based on feedback.

23
New cards

1 | Concepts — Sprint retrospective

The Scrum team examines how it worked and chooses improvements to quality and effectiveness.

24
New cards

1 | Concepts — Product backlog

An evolving, ordered list of work needed to improve the product; owned and ordered by the Product Owner.

25
New cards

1 | Concepts — Sprint backlog

The Sprint Goal, selected backlog items, and Developers' plan for delivering them.

26
New cards

1 | Concepts — Backlog refinement

Ongoing clarification, splitting, and estimation of backlog items so they are ready for future selection.

27
New cards

1 | Concepts — User story

A brief description of a user need and its value, commonly phrased as who wants what and why.

28
New cards

1 | Concepts — Epic

A large body of related work that is broken into smaller stories or tasks.

29
New cards

1 | Concepts — Story points

A relative estimate of effort, complexity, and uncertainty; points are not a universal conversion to hours.

30
New cards

1 | Concepts — Acceptance criteria

Specific conditions that a deliverable or backlog item must satisfy to be accepted.

31
New cards

1 | Concepts — Definition of Done

A shared quality standard that determines when an increment is complete and usable.

32
New cards

1 | Concepts — Change request

A documented proposal to alter an approved project element; assess its effects before implementing it.

33
New cards

1 | Concepts — Change control sequence

Record the request, review it, assess impacts, obtain the authorized decision, communicate it, update plans, implement, and validate.

34
New cards

1 | Concepts — CCB (Change Control Board)

The authorized group that evaluates and approves, rejects, or defers changes within its decision authority.

35
New cards

1 | Concepts — Change impact assessment

Evaluate effects on scope, schedule, cost, resources, quality, risks, and stakeholders before a change decision.

36
New cards

1 | Concepts — Scope creep

Uncontrolled expansion of work without corresponding approval and adjustments to the project plan.

37
New cards

1 | Concepts — Product change versus project change

A product change alters features or behavior; a project change alters delivery arrangements such as scope, budget, or schedule.

38
New cards

1 | Concepts — New feature during a Sprint

Have the Product Owner evaluate and order it; Developers and Product Owner may negotiate scope while preserving the Sprint Goal.

39
New cards

1 | Concepts — Risk

An uncertain event or condition that could help or harm project objectives if it occurs.

40
New cards

1 | Concepts — Issue

A current problem requiring action; a risk that occurs may become an issue.

41
New cards

1 | Concepts — Known versus unknown risk

Known risks are identified and can have planned responses; unknown risks were not identified in advance.

42
New cards

1 | Concepts — Risk owner

The person accountable for monitoring a risk and ensuring the planned response is carried out.

43
New cards

1 | Concepts — Risk trigger

A warning sign or event that indicates a risk response should begin.

44
New cards

1 | Concepts — Qualitative risk analysis

Prioritizes risks using judgments such as likelihood, impact, urgency, detectability, and connections to other risks.

45
New cards

1 | Concepts — Quantitative risk analysis

Uses numerical data and models to estimate uncertainty's effect on project outcomes.

46
New cards

1 | Concepts — Probability versus impact

Probability is how likely an event is; impact is the size of its effect if it happens.

47
New cards

1 | Concepts — Risk interconnectivity

The way one risk can cause, amplify, or depend on another risk.

48
New cards

1 | Concepts — Risk detectability

How readily warning signs can be recognized before a risk causes its full effect.

49
New cards

1 | Concepts — Monte Carlo simulation

Repeatedly samples uncertain inputs to estimate a range of possible cost or completion outcomes.

50
New cards

1 | Concepts — Scenario analysis

Examines plausible situations and their consequences to prepare decisions and responses.

51
New cards

1 | Concepts — Avoid a threat

Change the plan to remove the threat or protect the objective from its impact.

52
New cards

1 | Concepts — Mitigate a threat

Reduce a threat's probability or impact, such as testing early to reduce failures.

53
New cards

1 | Concepts — Transfer a threat

Shift financial or contractual consequences to a third party, such as insurance; the threat may still occur.

54
New cards

1 | Concepts — Accept a risk

Acknowledge it without proactively changing its likelihood; active acceptance may include a contingency reserve.

55
New cards

1 | Concepts — Exploit an opportunity

Act to make a beneficial uncertain event happen, such as assigning the strongest team to secure a benefit.

56
New cards

1 | Concepts — Enhance an opportunity

Increase the probability or size of a potential benefit.

57
New cards

1 | Concepts — Share an opportunity

Partner with a party best able to help realize the benefit.

58
New cards

1 | Concepts — Contingency plan

A prepared response activated when a specified risk event or trigger occurs.

59
New cards

1 | Concepts — Fallback plan

An alternative response used if the primary risk response does not work.

60
New cards

1 | Concepts — Contingency reserve

Time or money allocated for identified risks and planned uncertainty.

61
New cards

1 | Concepts — Management reserve

Additional provision for unforeseen work within overall scope, controlled through management authorization.

62
New cards

1 | Concepts — Residual risk

Risk that remains after a response is implemented.

63
New cards

1 | Concepts — Secondary risk

A new risk created by implementing a response to another risk.

64
New cards

1 | Concepts — Issue prioritization

Consider severity, urgency, project impact, and organizational reach when deciding what to resolve first.

65
New cards

1 | Concepts — Escalation path

The agreed route for raising a matter when the owner lacks authority or cannot resolve it within thresholds.

66
New cards

1 | Concepts — Workaround

An immediate response to a problem without a previously planned response; document its impact and follow-up.

67
New cards

1 | Concepts — Root cause analysis

Investigates the underlying cause of a problem so action prevents recurrence rather than only treating symptoms.

68
New cards

1 | Concepts — Milestone

A significant checkpoint or achievement, usually represented as zero duration in a schedule.

69
New cards

1 | Concepts — Mandatory dependency

A sequence required by physical reality, law, or the work itself; also called hard logic.

70
New cards

1 | Concepts — Discretionary dependency

A preferred sequence chosen by the team or practice; also called soft logic and may be changed.

71
New cards

1 | Concepts — External dependency

A relationship involving work or events outside the project team's control.

72
New cards

1 | Concepts — Internal dependency

A relationship between activities within the project's control.

73
New cards

1 | Concepts — Finish-to-start (FS)

The successor cannot start until the predecessor finishes; testing follows completion of the build.

74
New cards

1 | Concepts — Start-to-start (SS)

The successor cannot start until the predecessor starts; two activities can then overlap.

75
New cards

1 | Concepts — Finish-to-finish (FF)

The successor cannot finish until the predecessor finishes.

76
New cards

1 | Concepts — Start-to-finish (SF)

The successor cannot finish until the predecessor starts; a replacement service starts before the old service ends.

77
New cards

1 | Concepts — Lead

Allows a successor activity to begin earlier than the normal dependency relationship would permit.

78
New cards

1 | Concepts — Lag

A required delay between linked activities, such as waiting for concrete to cure.

79
New cards

1 | Concepts — Critical path

The longest-duration dependency path through the schedule; it determines the earliest possible project finish.

80
New cards

1 | Concepts — Total float

How long an activity can slip without delaying the project finish; critical activities commonly have zero float.

81
New cards

1 | Concepts — Resource loading

Shows how much work is assigned to each resource over time and helps reveal overallocation.

82
New cards

1 | Concepts — Resource leveling

Adjusts activity dates to resolve resource conflicts; it may extend the finish date or change the critical path.

83
New cards

1 | Concepts — Resource smoothing

Adjusts activities within available float to reduce resource peaks while preserving the finish date.

84
New cards

1 | Concepts — Crashing

Adds resources or cost to shorten duration, usually focusing on critical-path activities.

85
New cards

1 | Concepts — Fast tracking

Overlaps activities originally planned in sequence; can shorten the schedule while increasing rework risk.

86
New cards

1 | Concepts — Analogous estimating

Uses a similar past project's data for a quick estimate; accuracy depends on comparability.

87
New cards

1 | Concepts — Parametric estimating

Uses a measurable rate times quantity, such as cost per device multiplied by device count.

88
New cards

1 | Concepts — Bottom-up estimating

Estimates detailed work packages or tasks and sums them into the overall estimate.

89
New cards

1 | Concepts — Three-point estimate

Uses optimistic, most likely, and pessimistic estimates to represent uncertainty.

90
New cards

1 | Concepts — PERT weighted duration

Expected duration = (optimistic + 4 × most likely + pessimistic) / 6.

91
New cards

1 | Concepts — Forecast

An updated prediction of future results based on current performance and remaining work.

92
New cards

1 | Concepts — Rebaseline

Formally replace an approved comparison baseline after an authorized significant change; do not use it merely to hide poor performance.

93
New cards

1 | Concepts — Quality assurance (QA)

Process-focused prevention: ensure the methods used to produce work are suitable and followed.

94
New cards

1 | Concepts — Quality control (QC)

Deliverable-focused checking: inspect or test actual results to find defects.

95
New cards

1 | Concepts — Verification

Checks whether a result meets specified requirements: was it built correctly?

96
New cards

1 | Concepts — Validation

Checks whether a result meets the intended user need: was the right result built?

97
New cards

1 | Concepts — Quality audit

An independent examination of processes and compliance with agreed standards.

98
New cards

1 | Concepts — Inspection

Examination of a deliverable to determine whether it meets requirements.

99
New cards

1 | Concepts — Unit testing

Tests an individual component or small piece of code in isolation.

100
New cards

1 | Concepts — Smoke testing

A quick check of essential functions to determine whether a build is stable enough for deeper testing.