LANDSCAPE MATERIALS AND CONSTRUCTION

0.0(0)
Studied by 0 people
call kaiCall Kai
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
GameKnowt Play
Card Sorting

1/65

encourage image

There's no tags or description

Looks like no tags are added yet.

Last updated 9:17 AM on 10/1/26
Name
Mastery
Learn
Test
Matching
Spaced
Call with Kai
Chat

No analytics yet

Send a link to your students to track their progress

66 Terms

1
New cards

Schematic Design (SD)

  • 30% completion

  • General design concepts in plan

  • Color rendered presentation is done for client review

  • No written specifications


2
New cards

Design Development (DD)

  • ~50-65% complete

  • Coordination among the design team

  • Approximate cost estimate

  • Written specifications


3
New cards

Construction Drawings (CD)

  • 100% complete

  • Also known as Final or Bid set

  • Final drawings for bidding and construction

  • Some projects will have a Pre-Final (90%) submittal before


4
New cards

As Built Plans

  • Markup of the construction set drawings by the contractor after final landscape installation to record any changes or adjustments of the design drawings as typically relating to site conditions and approved changes


5
New cards

TMK

  • Tax Map Key

  • A legal number designation that identifies a property to the government

  • Required to indicate on a construction drawing for permitting

  • Zoning, height limits, and other information when searched


6
New cards

Arial

  • Most common font for construction drawings

  • AutoCAD standard

  • Font size of 1/8” for a full-size drawing (half size printed drawing is still legible)


7
New cards

Romans

  • Font commonly used on construction drawings

  • Font size of 1/8” for a full-size drawing (half size printed drawing is still legible)


8
New cards

Maintenance Period

  • Begins at the time of substantial completion of the project

  • Meant to ensure successful establishment of the plantings

  • 90 days


9
New cards

Title Block Info

  • Architecture/landscape architecture firm name and address

  • Project name and location

  • TMK

  • Sheet name

  • Date

  • Scale

  • Sheet number


10
New cards

Basis of Design (BOD)

  • Written description of the existing conditions and proposed design

  • For client or owner


11
New cards

Post Contract Document (PCD)

  • Changes to drawings and specifications after the contractor is selected


12
New cards

Change Order Procedure (COP)

  • Contractor submits a cost estimate for a change order to do the work issued in a PCD


13
New cards

Contour Interval

  • Vertical distance or difference in elevation between contour lines

  • Bolder or thicker contour lines appear for “major” contours such as 5’, 10’, 15’, 20’


14
New cards

Slope (on grading plans)

  • Horizontal distance first, then vertical distance (run over rise)

  • Different than slopes for hardscape/ramps (rise over run)


15
New cards

Americans with Disabilities Act (ADA)

  • Ramp: needed if slope is equal to or greater than 5% (1:20)

  • Ramp: slope maximum 1:12 or 8.33%. 36” width min

  • Handrails: if ramp is longer than 6ft, extend 12” beyond end of ramp or steps

  • Railing: 34” min to 38”

  • Ramp Top/Bottom Landings: 60” min. diameter. 30 ft maximum distance between landings (at 1:12 slope), 30” max. rise between landings

  • Cross Slopes: 1:50 (2%) cross slope

  • ¼” max vertical change

  • ½” max gaps in paving


16
New cards

Straw Wattle

  • Netting filled with straw

  • Filters water and prevent soil migration


17
New cards

Compost Sock

  • Filled with compost

  • Filters water and prevent soil migration


18
New cards

Riprap

  • Loose or mortared rocks

  • Slows, divert or dissipate energy from water/waves


19
New cards

Erosion Control Blanket

  • Short term or permanent erosion control blankets secured to the slope

  • Short term blankets are made with straw, coconut fiber and/or jute


20
New cards

Air Spade

  • Special tool that uses compressed air to excavate around tree roots

  • For transplanting trees or for arborist inspection and mediation


21
New cards

Container Sizes

  • A size designation of nursery plants

  • Typically 4” pots, 1-gal, 5-gal, 15-gal, 25-gal sizes

  • Larger Sizes (boxed or bagged): 60-gal, 80 gal, and 100 gal sizes

  • Groundcovers: small pots, “Flats”, sprigs, or rooted cuttings


22
New cards

Hydromulch

  • A process of applying a wet slurry mix of fine organic mulch, organic fibers, and seed or stolons

  • Often dyed green

  • Applied using special spray equipment


23
New cards

Plugs

  • Individually grown grass portions that have roots and soil

  • Planted in holes in the ground and spaced apart


24
New cards

Root Barrier

  • A metal, plastic, or fabric sheet installed between a tree and paving or buildings

  • Reduces or delay damage of expanding roots


25
New cards

Sod

  • Grass that is fully grown

  • Laid down in sheets or rolls

  • Instant lawn


26
New cards

Springs

  • Grass cut from rhizomes or stolons that include roots but no soil

  • Planted in holes in the soil and spaced apart


27
New cards

Stolons

  • Grass that is grown using shredded root material

  • Applied with hydromulch


28
New cards

Tree Trunk Guard

  • Expandable plastic or metal band placed at the base of tree trunks

  • Prevents damage from weed whackers and lawn mowers


29
New cards

Tree Spade

  • Special equipment that uses tall blades that hydraulically sink into soil around a tree to lift a tree for transplanting


30
New cards

Finish Grade (FS)

  • The final set level of soil

  • Important for establishing against paving, retaining walls, and other landscape elements


31
New cards

Sub-grade

  • Soil elevation prior to landscape soil

  • By general contractor


32
New cards

Typical Concrete Finishes

  • Broom Finish

  • Trowel Finish

  • Rock Salt Finish

  • Exposed Aggregate Finish

  • Stamped Concrete


33
New cards

Broom Finish

  • Uses an actual broom to sweep a pattern

  • Straight lines or swirled

  • Skid resistance


34
New cards

Trowel Finish

  • Uses a large metal trowel (like a flat triangle) to rotate over wet concrete and draw water to the surface

  • Smooth finish or “troweled” finish with swirled surface texture


35
New cards

Rock Salt Finish

  • Uses actual salt crystals that are scattered over concrete while wet

  • Creates a pocketed texture

  • Salt washed away


36
New cards

Exposed Aggregate

  • Surface of concrete is lightly washed with water before hardening

  • Exposes the stone in the concrete mix


37
New cards

Stamped Concrete

  • Template pattern pressed into freshly poured cement

  • Typically, ±¼” depth


38
New cards

Concrete Color

  • Stained: acid stain applied after concrete has hardened

  • Dry Shake: topically applied to freshy poured and leveled cementations concrete surface

  • Integral Color Dyes: a powder color mixed into concrete cement before pouring


39
New cards

Curing / Setting

  • Time it takes for concrete to harden


40
New cards

Floating

  • Process of spreading freshly poured cementitious concrete with long poles with steel plates attached to level it


41
New cards

Aggregate

  • Sand and gravel mixed with cement and water to make concrete


42
New cards

Rebar

  • Metal rods, usually steel

  • Used to reinforce concrete construction


43
New cards

Pre-cast Concrete

  • Concrete which is cast and cured in a different location than its final designated position


44
New cards

Construction Joint

  • A joint in concrete paving formed by different placements of concrete

  • Planned stopping point where two separate concrete pours mix


45
New cards

Control (Score) Joint

  • Joint formed by a special metal trowel or by saw cutting

  • Helps control cracking

  • Provides an aesthetic design pattern

  • Typically, ¼” depth (most effective, should go down ¼ the thickness of the pavement)


46
New cards

Edges

  • Filet: rounded

  • Chamfer or Bevel: angled

  • Created by a tool before concrete hardens

  • Takes away sharp edges

  • Makes the edge less likely to break and chip, and edges of concrete benches less sharp


47
New cards

Expansion Joint

  • Separation between concrete areas

  • Allow for expansion and contraction of concrete

  • Filled with rubber or fiber compound to maintain a level surface


48
New cards

Spalling

  • Result of water entering concrete

  • Causes breaking, flaking, or cracking

  • Can result from rebar rusting and expanding. In cold climates can result from freeze and thaw cycles


49
New cards

Efflorescence

  • White powdered deposits due to the evaporation of water from the concrete surface from moisture within the concrete

  • Waterproofing the back side of retaining walls helps to reduce efflorescence


50
New cards

GFRC

  • Glass Fiber Reinforced Concrete

  • Used to make lightweight concrete forms, or for naturalistic forms

  • Textured with latex molds and tools then color stained for a desired appearance


51
New cards

Cement

  • A powdered lime ingredient used to make concrete

  • Concrete is the hardened form of cement


52
New cards

Mortar

  • A paste which is used to bind building blocks such as brick, stones, to fill gaps between them

  • Often made with cement


53
New cards

Base Course

  • Compacted base below paving, usually gravel or sand


54
New cards

Header / Edging

  • Made of plastic, metal, stone, or brick

  • Separates lawn areas from shrub and groundcover areas


55
New cards

Permeable Paving

  • Paving that is designed to allow water percolation

  • Grass block, permeable brick, permeable concrete are examples of permeable paving


56
New cards

Brick Paving Patterns

  • Most Common: Herringbone, running bond, basket weave patterns


57
New cards

Walls

  • Mechanically Stabilized Earth (MSE)/ Keystone walls: interlocking blocks

  • Gabion wall: metal wire wrapped around boulders or large gravel

  • Weep Holes: holes through retaining walls to allow drainage

  • Battered wall: face of wall leans back so wall is wider at the base

  • Cantilever: face of the wall leans forward so the wall is wider at the top

  • Shotcrete: reinforcing frame put against the slope and high-strength concrete mix is sprayed on

  • Footing: base structure of wall, usually concrete reinforced with rebar


58
New cards

Model Space

  • Default working space where you draw

  • 1:1 scale


59
New cards

Layout (Paper) Space

  • Used for creating a finished layout for printing and plotting

  • Viewports in paper space bring in your design in model space

  • At a specified scale.


60
New cards

EJ

  • Common abbreviation used for calling out an expansion joint on a hardscape plan


61
New cards

TYP

  • Abbreviation for typical


62
New cards

EQ

  • Abbreviation for equal

  • Used to call out equal spacing for score joints for example


63
New cards

Dimension

  • Numerical value representing the distance or size of what is being dimensioned


64
New cards

Dimension Line

  • Line that is related to the dimension

  • Ends with a symbol such as arrowheads or tick marks


65
New cards

Extension Line

  • Lines perpendicular to the dimension line that almost touch the object

  • Thinner than dimension lines

  • Extension lines can cross other extension lines but should not cross another dimension line


66
New cards

Hardscape (Paving) Plans

  • Shows the types of hardscape (paving), color, joints, finishes, references to related details, walls, and main features

  • Directions to the contractor for what to construct and how

  • Key or legend is helpful

  • Curves can be called out with a radius (complex can be shown with a grid system)