Relevant Cash Flows: What are relevant cash flows?
Cash flows that occur ONLY if a project is accepted.
Trigger: Project changes future cash flow → Relevant.
Incremental Cash Flows: What are incremental cash flows?
Changes in a firm's future cash flows directly caused by accepting a project.
Stand-Alone Principle: What does the stand-alone principle mean?
Evaluate each project independently by focusing only on its incremental cash flows.
Opportunity Costs: What are opportunity costs?
Cash flows given up by choosing a project instead of the best alternative.
Example: Using a warehouse you could rent out.
Trigger: Forgone alternative income → Include.
Sunk Costs: What are sunk costs?
Costs already incurred that cannot be recovered.
Example: Money previously spent on research.
Trigger: Already spent → Exclude.
Financial Costs: Should interest and dividends be included in project cash flows?
No. Financing costs are reflected in the discount rate (WACC), not project operating cash flows.
Side Effects: What are positive and negative side effects?
Positive: A project increases sales of another product.
Negative: A project reduces sales of an existing product (cannibalization).
Both should be included when incremental.
Net Working Capital: What is NWC?
NWC = Current Assets − Current Liabilities.
Represents funds tied up in short-term operations.
Change in NWC: How do you calculate ΔNWC?
ΔNWC = New NWC − Old NWC.
An increase in NWC generally represents a cash outflow.
ΔNWC = New NWC − Old NWC.
An increase in NWC generally represents a cash outflow.
The invested NWC is generally recovered as a cash inflow.
Trigger: Beginning → Outflow; Ending → Recovery.
OCF: What is operating cash flow?
Cash generated by a project's normal business operations.
Common Approach: What is the common OCF formula?
OCF = EBIT + Depreciation − Taxes.
Bottom-Up Approach: What is the bottom-up OCF formula?
OCF = Net Income + Depreciation.
Note: Works when there are no interest expenses.
Top-Down Approach: What is the top-down OCF formula?
OCF = Sales − Cash Costs − Taxes.
Do not subtract depreciation as a cash cost.
Tax-Shield Approach: What is the tax-shield OCF formula?
OCF = (Sales − Cash Costs)(1 − T) + Depreciation × T.
T = Tax rate.
OCF Calculation: EBIT = $400, depreciation = $3,600, taxes = $60. Find OCF.
OCF = $400 + $3,600 − $60
= $3,940
OCF Methods: Should all four OCF approaches produce the same answer?
Yes, when applied correctly using consistent assumptions.
Pro Forma Statements: What are pro forma financial statements?
Financial statements that forecast a company's future financial performance.
Trigger: Projected future income → Pro forma.
Depreciation: What is depreciation?
Allocation of an asset's cost over its useful life.
It is a non-cash expense.
Depreciation Tax Shield: Why is depreciation relevant to cash flow?
Because depreciation reduces taxable income, lowering taxes paid.
Depreciation Tax Shield: What is the formula?
Depreciation Tax Shield = D × T.
D = Depreciation expense.
T = Tax rate.
Straight-Line Depreciation: What is the formula?
D = (Initial Cost − Ending Book Value) / Number of Years.
Straight-Line Example: An asset costs $110,000 and has a $17,000 ending book value after 6 years. Find annual depreciation.
($110,000 − $17,000) / 6
= $15,500 per year
MACRS: What does MACRS stand for?
Modified Accelerated Cost Recovery System.
Used to calculate depreciation for tax purposes.
MACRS Calculation: How do you calculate annual depreciation?
Depreciation = Depreciable Basis × MACRS Rate.
MACRS Mid-Year Convention: Why does a 3-year MACRS asset depreciate over 4 years?
Because the half-year convention spreads depreciation across an additional tax year.
MACRS 3-Year Rates: What are the approximate rates from your example?
Year 1: 33%
Year 2: 45%
Year 3: 15%
Year 4: 7%
MACRS vs. Straight-Line: What is the difference?
Straight-line: Equal depreciation each year.
MACRS: Accelerated depreciation, generally larger deductions in earlier years.
Book Value: What is the formula?
Book Value = Initial Cost − Accumulated Depreciation.
Salvage Value: What is salvage value?
The estimated amount received from selling an asset at the end of its useful life.
After-Tax Salvage: What is the formula?
After-Tax Salvage = MV − T(MV − BV).
MV = Market Value.
BV = Book Value.
T = Tax Rate.
Salvage Tax: What happens if MV is greater than BV?
The company pays taxes on the gain.
Trigger: MV > BV → Tax payment.
Salvage Tax: What happens if MV is less than BV?
The company may receive a tax benefit from the loss.
Trigger: MV < BV → Tax savings.
Salvage Tax: What happens if MV equals BV?
No gain or loss, so no tax adjustment.
After-Tax Salvage = MV.
Salvage Example: MV = $17,000, BV = $0, tax rate = 40%. Find after-tax salvage.
$17,000 − 0.40($17,000 − $0)
= $10,200
Initial Investment: What costs are included at Year 0?
Equipment cost + Shipping/Installation + Initial NWC investment.
These are generally cash outflows.
Initial CF Example: Equipment = $200,000, installation = $40,000, increase in NWC = $20,000. Find CF₀.
CF₀ = −$200,000 − $40,000 − $20,000
= −$260,000
Terminal Cash Flow: What is terminal cash flow?
Additional cash received at the end of a project.
Terminal CF = After-Tax Salvage + NWC Recovery.
Terminal CF Example: After-tax salvage = $15,000 and NWC recovery = $20,000. Find terminal CF.
$15,000 + $20,000
= $35,000
Final-Year Cash Flow: What must be included in the final year?
Final-Year CF = Final OCF + Terminal CF. Example: $54,720 + $35,000 = $89,720
NPV: What is net present value?
Present value of future project cash flows minus the initial investment.
NPV Decision Rule: When should you accept or reject a project?
NPV > 0 → Accept.
NPV < 0 → Reject.
NPV = 0 → Financially indifferent.
IRR: What is the internal rate of return?
The discount rate that makes a project's NPV equal zero.
The discount rate that makes a project's NPV equal zero.
IRR > Required Return → Accept.
IRR < Required Return → Reject.
NPV & IRR Example: NPV = −$4,029.72, IRR = 9.28%, required return = 10%. Accept or reject?
Reject the project.
NPV is negative, and IRR is below the required return.