[1 Life cycles] What are the distinctive features, strengths and limitations of a linear life cycle?
A linear life cycle is sequential, predictive and phase-based, with scope largely defined upfront.
Strengths include clear milestones, strong governance and more predictable cost and schedule.
Limitations include less flexibility, later feedback and benefits, and difficulty accommodating changing requirements.
[1 Life cycles] What are the distinctive features, strengths and limitations of an iterative life cycle?
An iterative life cycle develops the solution through repeated timeboxes using feedback and evolving requirements.
Strengths include early value, flexibility and frequent user input.
Limitations include less certainty over final scope, cost, duration and resource demand.
[1 Life cycles] What are the distinctive features, strengths and limitations of a hybrid life cycle?
A hybrid life cycle add iteration to a linear life cycle enabling a mix of approaches.
It facilitates amix of approaches, to best suit the context, complexity and uncertainty of a project.
It adds complexity and requires clear interfaces, governance and skills.
[1 Life cycles] When is a hybrid life cycle most appropriate?
Most appropriate where linear or iterative lifecycles don’t suit the context, complexity or uncertainty.
Whilst some project elements are stable and can be planned predictively, while others are uncertain and benefit from iterative development and feedback.
[2 Governance arrangements] How does a functional organisational structure affect project authority?
Authority remains mainly with functional line managers and people work within specialist departments. Projects may have limited direct authority over resources, so coordination across functions is important.
[2 Governance arrangements] What are the main responsibilities of the project manager?
Manage the proejct day-to-day
Ensuring successful delivery of outputs, identifying and managing risks, budget and schedule
Develops the PMP, monitoring and controlling project progress
Communicates with and updates all stakeholders
Organises and motivates the team
[2 Governance arrangements] What are the main responsibilities of the project sponsor?
Secures funding for the project
Owns and develops the business case
Provides ongoing support to the PM and overarching governance
Makes decisions on behalf of the business at reviews / decision gates.
[2 Governance arrangements] What factors should determine project governance arrangements?
Governance should be proportionate to project scale, complexity, risk, life cycle, organisational structure, stakeholder needs and delegated financial authority, with clear roles, controls, reporting and escalation routes.
[3 Sustainability] What environmental sustainability considerations or principles may affect a project?
Climate impacts, Biodiversity, Energy efficiency
[3 Sustainability] What social sustainability considerations may affect a project?
Effects on communities, users and workers, including equality, inclusion, health and safety, human rights.
[3 Sustainability] What economic and administrative sustainability considerations may affect a project?
Economic considerations include affordability, profitability and risk.
Administrative considerations include legislation, regulation, health and safety, resource efficiency.
[4 Business case] What are the five elements of a business case?
Strategic context
economic analysis
commercial approach
financial case
management approach.
[4 Business case] How does PESTLE analysis support a business case?
It tests the external context by considering political, economic, sociological, technological, legal and environmental influences that could affect need, options, risk or viability.
[4 Business case] How do SWOT and VUCA analyses support a business case?
SWOT considers internal (current) strengths and weaknesses and external (potential future) opportunities and threats.
VUCA helps evaluate the messy, complicated uncertainty projects often face through exploring volatility, uncertainty, complexity and ambiguity that may affect assumptions, decisions and delivery.
[5 Procurement] What are the three key contents of a procurement strategy?
Make-or-buy decision
Supplier selection, including selection proces, single or multiple sourcing, negotiation approach
Decision on contractual relationships, including contract conditions, payment terms.
[5 Procurement] What are the 7 main stages of supplier selection?
Research the market
Pre-qualify suppliers
Issue the ITT
Respond to queries from bidders
Receive and evaluate bids
Award a contract to a successful bidder
Enter into contract and manage the contract
[5 Procurement] What do BATNA, ZOPA and win-win mean in negotiation?
BATNA is the Best Alternative To a Negotiated Agreement (Plan B if negotiation fails).
ZOPA is the Zone Of Possible Agreement - the overlap between each party’s acceptable positions.
Win-win is a form of joint venture with long term strategic benefit for both parties.
[6 Reviews] What is the purpose of a decision gate?
A decision gate at a phase or iteration boundary. It reviews:
achievement
viability
readiness
risks
plans
and then authorises continuation, change, pause or closure.
[6 Reviews] What is the purpose of a benefits review?
To compare realised benefits and disbenefits with the approved benefits plan, confirm ownership and sustainability, identify corrective action and inform future investment decisions. Held by the Sponsor during adoption and Benefits Realisation phases.
[6 Reviews] What is the purpose of a project audit?
To provide an independent assessment of compliance, increase stakeholder confidence and ensure the project is follwing agreed governance and processes. Findings may lead to corrective actions.
[6 Reviews] What information should project reviews report?
Schedule progress
Project spend - actual against planned
Earned value
Audit findings and any non-conformance
Risks and issues
[6 Reviews] What are the key elements of information and data that are vital to enable effective project decision mkaing?
Status Reporting - current status
Estimating the project - Accuray is key - schedule & cost
Risk Identification
Problem Solving and option appraisals - current performance trends used to consider future options.
Availability of information -right info at the right time
Knowledge and information management - learning from experience
[6 Reviews] What findings may cause re-planning or re-baselining?
Material variance or change affecting performance, scope, schedule, cost, resources, suppliers, quality, risk, benefits, readiness or stakeholder needs may require an approved revised plan or baseline.
[7 Assurance] What is project assurance? What does it provide
An objective, independent and proportionate assessment of the project.
It gives:
Confidence to the governance board confidence that the project is on track
Support to the decision making and change control processes
Improved accuracy of risk assessment
Increased probability of projects meeting primary objectives.
[7 Assurance] What 3 activities can project assurance include?
Controls - Applying the agreed policies, procedures and processes
Compliance - monitoring and auditing that controls are being followed
Independent Review - carried out by external staff to ensure the assurance acitvities are operating effectively
[7 Assurance] What 5 criteria help ensure that an assurance plan is effective?
It must:
Be independent, objective and proportionate
Target the greatest risks
Show clear accountability for all assurance arrangements, activities and subsequent outputs.
Show timings of assurance activity cycles
Show a clear governance route for reporting outcomes and resolving issues
[8 Transition management] What are the 5 basic actions that should be taken to ensure a successful transition into business-as-usual?
• Manage stakeholder expectations from the outset - to increase the likelihood of the project outputs being accepted
• Identifying and engage with end users and project sponsors throughout the project
• Aligning needs with outputs
• Set the path for handover and acceptance by familairising key stakeholders with the deliverables
• Clear communication to reduce the risk of misunderstanding the requirements.
[8 Transition management] What is knowledge transfer? How does Progressive Implementation help achieve it?
Knowldge Tranfer transfers information, skills and expertise from the Project to the operational users.
Progressive Implementation is a graduated approach to Knowledge Transfer that ensures:
Good communication between the project and end users to enable business readiness, which is championed by the Sponsor
An extended lifecycle is applied to keep the rpoejectteam accountable for change management
Sufficeint capability is held by operational users to enable continuous improvement
[8 Transition management] What should be done as part of engaging stakeholders for transition planning?
Early engagememnt and Stakeholder mapping - who is high power, high interest , for / against
Strategic alignment of goals and understanding of the future state
Communicate the benefits, ideally by designating benefits champion
[9 Benefits management] What happens during benefits identification and definition?
Identification determines expected benefits and disbenefits, showing a ROI
Definition outlines how the benefits will be managed through transition into operational use. Records each benefit’s measure, baseline, target, value, timing, dependencies and accountable owner.
[9 Benefits management] What happens during benefits planning and tracking?
Planning sets the activities, milestones, resources, measures and organisational change needed.
Tracking compares actual and forecast performance with targets and triggers corrective action.
[9 Benefits management] What is benefits realisation?
Embedding outputs into operations so intended outcomes occur and measurable benefits are achieved, evidenced and sustained.Change manager is usually responsible for tracking realisation of benefits.
[9 Benefits management] Why must benefits align with strategic objectives? What three activities support this?
Benefits justify investment only when they contribute to organisational strategy. Alignment supports prioritisation, ownership, measurement and decisions on continued investment.
Business Case
Benefits Mapping
Benefits Identification and Measurement