Republic Act No. 1378
Plumbing Law signed by Pres. Magsaysay.
Republic Act No. 1364
Sanitary Engineering Law signed by Pres. Magsaysay.
Republic Act No. 6541
Building Code of the Philippines
City Ordinance 2411
Plumbing Code for the City of Manila
Governor General Harrison
issued a letter of proposal for proper waste disposal.
John F. Hass
first Chief of the Division of Plumbing Construction and Inspection.
Jaime M. Cabase
spearheaded the updating of the Revised Plumbing Code
Feati University
Plumbing Engineering was first introduced.
NAMPAP
National Master Plumbers Association of the Philippines
NAWASA
National Waterworks and Sewerage Authority
1902
Year the plumbing trade was duly recognized by the government.
July 1956
First licensure examination for master plumbers
January 28, 1959
Plumbing Code was promulgated and approved by Malacanang.
1935
Year NAMPAP has been registered with the Securities and Exchange Commission
1966-1969
Examiners and NAMPAP prepared a curriculum for Plumbing Engineering.
November 28, 1967
First Amendment to the Plumbing Code was approved (inclusion of Asbestos Cement Pipe as approved plumbing material)
February 23, 1994
First fully computerized examination for master plumbers
December 21, 1999
Section 4 of R.A. 1378 was approved by Pres. Estrada.
6 sets
Set/s of plumbing plans, drawings, diagrams, and other documents to be submitted for the application of permit.
1 set
Set of approved plans, specifications, and data to be retained by the Administrative Authority.
2 sets
Sets of entire plans and specifications to be returned to the applicant.
2 sets
Sets of entire plans and specifications to be returned to the Owner.
1 set
Set of entire plans and specifications to be kept at the job site
1 year
Expiration of plumbing permit if work is not commenced from the date of issuance.
120 days
Expiration of plumbing permit if work has been suspended or abandoned.
50%
Percentage of the original fee to be paid for the renewal of permit.
72 hours
Request for inspection for the replacement of an existing equipment shall be filed not more than after such replacement work is completed.
3 working days
Request for inspection shall be filed with the Administrative Authority at least ______ before such inspection is intended.
Partial Permit
The Administrative Authority may issue ______ for the construction of a part of a large and/or complicated plumbing system before the entire plans & specifications for the whole system submitted or approved: