When should a pressure relief valve be added to the connections for a pressure test?
For all pressure tests
When performing an initial service test, the test pressure should be applied
gradually
Steam cleaning is a common cleaning method because
it will remove oils and grease
Leak repairs should never be made
as long as the system is still pressurized
After installing and cleaning instrumentation piping, tubing, and hoses, the system should be
purged
Brittle fracture occurs when
the test medium is significantly different in temperature than the tested system
When testing piping or tubing, the test pressure should not be applied
until the test medium is at a specified temperature
Before attempting to disassemble or further tighten a grip-type compression fitting, always
place a mark across the tube nut and fitting body
The process of passivating is designed to
form a protective layer to inhibit corrosion
Why is acid cleaning not used as a standard cleaning method?
The danger to untrained personnel when handling acid is excessive