1) The City of Spainville approved the construction of a city hall complex for a total cost of $120,000,000. A few days later, a contract with a 5% Retainage clause was signed with Paltrow Construction for the complex. The buildings will be financed by a federal grant of $25,000,000 and a general obligation bond issue of $100,000,000. During the current year, investment revenue of $4,000,000 is budgeted.
Part 1: Budgeting
Estimated Revenue - Investment Income 4,000,000
Estimated Revenue - Federal Grant 25,000,000
Estimated Revenue - Other Financing Source - Bond 100,000,000
—Appropriation - building 120,000,000
—Budgetary Fund Balance 9,000,000
Part 2: Signing the Contract. Contracts are journal entried like ENCUMBRANCES.
Encumbrance 120,000,000
—Budgetary Fund Balance Reserved for Encumbrances 120,000,000
2) The bonds were issued for $100,000,000 face value.
Cash 100,000,000
—Other Financing Source - Bond 100,000,000
3) The city collected the grant money from the government.
In 1) this was the sentence that goes along with this “ The buildings will be financed by a federal grant of $25,000,000 …”
CASH 25,000,000
—Advance - Federal Grant 25,000,000
4) The city invested $90,000,000
Investment 90,000,000
—CASH 90,000,000
5) The contract signed with Paltrow stipulated that the contract price included architect fees. the architects were paid their fee of $45,000 by Spainville (assume a voucher system).
Step 1: Reverse the encumbrance
Budgetary Fund Balance Reserved for Encumbrances 45,000
—Encumbrance 45,000
Step 2: Set Expenditure with a voucher payable
Expenditure - bldg. 45,000
—Voucher Payable 45,000
Step 3: Pay Voucher
Voucher payable 45,000
—Cash 45,000
6) Paltrow submitted a progress billing for $25,000,000. The billing was approved.
Reverse encumbrance:
BFBRFE 25,000,000
—encumbrance 25,000,000
Actually pay expenditure:
Expenditure - bldg. 25,000,000
—construction contract payable 23,750,000
—Retainage payable 1,250,000
Record revenue from grant (defined in question 1, collected in question 3, recorded in this question.)
Advance from Federal Grant 25,000,000
—revenue - federal grant 25,000,000
7) investments that cost $5,000,000 were redeemed for $5,020,000
Cash 5,020,000
—investment 5,000,000
—revenue - investment income 20,000
8) investments income totaling $3,500,000 were received in cash.
Cash 3,500,000
—revenue - investment income 3,500,000
9) The contractor was paid the amount billed in #6. (Paltrow submitted a progress billing for $25,000,000. The billing was approved. 5% Retainage)
Construction contract payable 23,750,000
—cash 23,750,000
10) The contractor submitted another progress billing for $25,000,000. The billing was approved. (5% Retainage)
Reverse encumbrance:
BFBRFE 25,000,000
—encumbrance 25,000,000
Actually pay expenditure:
Expenditure - bldg. 25,000,000
—construction contract payable 23,750,000
—Retainage payable 1,250,000
11) Investments totaling $14,600,000 were redeemed, together with $1,400,000 investment income
Cash 16,000,000
—investment 14,600,000
—revenue - investment income 1,400,000
12) The contractor was paid the amount billed from #10 above (The contractor submitted another progress billing for $25,000,000. The billing was approved. (5% Retainage))
Construction contract payable 23,750,000
—cash 23,750,000
13) Investment income of $250,000 was accrued.
Investment income receivable 250,000
—revenue - investment income 250,000
14) Bond interest totaling $10,000,000 was paid.
TRICK QUESTION!
This is no longer for the Capital Project Fund, this is for the Debt Service Fund.
NO Journal Entry!