What is the source of cash for funding initial CFs vs “financing” projects. What is the common mistake about cost of capital if someone is confused about the two? What is the correct way to estimate capital k?

If After Tax WACC is used to take on +NPV project, what must a firm do w/ debt as a result?

What is the formula for levered firm APV method. Explain each term.

Define expected financial distress. What does it include & not include?

What are the 3 different valuation methods for a project with a constant D/E ratio? What are the discount rates used for each CF & why?

What value does the flow of equity “match” for a constant D/E project?
FCFE = NPV using WACC & APV
*FCFE = gain from shareholders from project
For a project with a constant D/E, why is WACC & APV give the same value as NPV? Is that always true?
WACC & APV = NPV bc D/E constant (D & Divs increase @ same rate). → not true if D/E ≠ constant
What is the main contrast between a project w constant vs not constant D/E? Why?

What are 2 aspects of valuing uncertainty?
Add firm specific risk into probability weighted CFs/ NPV calc
Account for ability to abandon/ ∆ course when new info is available → ALWAYS CHOOSE option w higher NPV
What are the E(NPV) assumptions? Why is that problematic?

What is the effect of decreasing the left tail or increasing the right tail effect on NPV?

FCF =
EBIT(1 - T)
+ Depr
- CAPEX
- ∆NWC
rE =
rE = Pretax WACC + (D/E)(Pretax WACC - rD)
PV (Interest Tax Shield) =
PV(ITS) = (∑ ITS_t)/ (1 + PRE-tax WACC)^t
Interest Tax Shield =
ITS = Interest * Tax
Interest =
Interest = rD * D_t-1
Net borrowing =
Net Borrowing = Dt - D_t-1
FCFE =
FCFE = FCF - (1 - T)( interest expense) + Net Borrowing
NPV (FCFE) =
(∑ FCFE_t)/ (1 + rE)^t
V L =
V L = (∑ FCF_t)/ (1 + AFTER-tax WACC)^t
V_t_L (terminal levered value)=
V_t_L = (FCF_t+1 + V_t+1) / ( 1 + AFTER tax WACC)
Term Value =
FCF (1 + g) / (AFTER tax WACC - g)
Enterprise Value (with horizon value) =
EV = ∑FCF / (1 + AFTER tax WACC)^t
+ Terminal Value/ (1 + AFTER tax WACC)^n
Value Unlevered Vu =
Value Unlevered Vu = ∑FCF_t / ( 1 + PRE tax WACC)^t
APV method Levered Value VL =
APV VL = Unlevered Value Vu + PV (ITS) - PV (Financial Distress)
Du pont EV/ EBITDA
EV = (FCF/ WACC - g)
/ EBITDA
= (FCF/EBITDA) / (WACC - g)
EV/ EBITDA_industry * _____firm = EV firm
EBITDA_firm
SHARE PRICE =
Market Cap / Shares Outstanding
Market Cap =
Share price * Shares Outstanding
Enterprise Value =
Market Equity + Debt - Excess Cash
→
Mkt Equity + net debt
Net Debt =
Debt - excess cash
Market Equity =
Mkt Equity = (Mkt V/ Book V) * (Total Assets - Total Liabilities)
DuPont P/E =
(Div Payout Ratio/ rE - g)/ EPS
→
(DPO/ EPS) / rE - g
Price of firm given industry =
P_firm = P/E_industry * EPS_firm
E(NPV w Option) =
∑p * MAX( NPV continue, NPV abandon)
Option Payoff =
Call = MAX( SPOT price - EXERCISE price, 0)
Default Option Payoff =
Break Even = (Extraction cost + Debt)/ units that create the CF
Delayed Option NPV_wait =
[ ∑p * MAX(NPV state, 0) ]/ (1 + r)
Timing Option rules for holding vs selling when given
Fair values
Present Values
Hold given FV if g > discount rate k.
g = FV_t / FV_t -1
Sell @ max PV(CF)
Public Co acquiring Private Co
Control Premium =
(V_control - V_no control) / (V_no control)
Private Acquisition Value =
Public Value * (1 - illiquidity discount)
who has a higher acquisition price, a private or public investor?
PUBLIC
Bc they have less risk (more liquid = easy to sell asset)= less return compensation = higher price (inverse relationship) = pay CONTROL PREMIUM
Public co pays a…
Control premium
Private investor gets an…
Illiquidity discount on acquisition price bc they r more risky = expect more return compensation = lower price differential
Share price given dividend amt=
D0 = D1/ rE - g
CF0
Or
D0 =
CF0 = CF_t+1/ (rE - g)
APV Method
Enterprise Value =
What is each value discounted at?
APV EV = ( PV Planning Period Unlevered FCF + PV Planning Period Interest Tax Shield ) + (PV (Horizon Period Terminal Value)
PP Unlev FCF disct @ (1 + rE)
PP ITS disct @ (1 + PREtax WACC) if D/E constant
PP ITS disct @ (1 + rD) if D/E ≠ constant
HP TV disct @ (AFTER tax WACC - g)
PP Unlev FCF disct @ (1 + __)
rE
PP ITS disct @ (1 + ___) if D/E constant
PREtax WACC
PP ITS disct @ (1 + ___) if D/E ≠ constant
rD
HP TV disct @ (_____- g)
HP TV disct @ (AFTER tax WACC - g)
Pretax WACC
rU =
rU = rD(D/V) + rE(E/V)
Vu =
CF/ 1 + rU
We can NOT use WACC method if…
D/E ≠ constant
What does NPV (FCFE) assume?
CONSTANT D/E
Same NPV from WACC & APV
What is spot price
Sell @ t= 0
What is forward price?
Sell @ t = n = expected price = risk neutral
Risk neutral forward price is discounted @…
Risk free rate
You will NEVER have a negative terminal value. Why?
You would just abandon once it was negative.
Dont extend it into infinity just make it 0.
Equity holders have a call option on….
ASSETS
Debt holders have an exercise price on…
ASSETS
Max(A sets - Debt, 0)
Option Price to discount =
Acquisition price s - Extraction cost x
Acquisition price s < Extraction cost x =
0
Dont exercise or extract
Acquisition price s > Extraction cost x =
S - x