1/42
Comprehensive practice flashcards covering foundational concepts, initiating, planning, executing, monitoring, controlling, and closing processes from FBLA Project Management Practice Tests 1 and 2.
What is the definition of a project?
A temporary endeavor undertaken to create a unique product, service, or result.
What characteristic most clearly distinguishes a project from ongoing operations?
A project has a definite beginning and end.
What three factors traditionally make up the "triple constraint" of project management?
Scope, time, and cost.
What is the correct sequence of the project management process groups?
Initiating, planning, executing, monitoring and controlling, and closing.
What constitutes a conflict of interest in project management?
A situation where personal interests could improperly influence professional decisions.
What are the four core values of the PMI Code of Ethics and Professional Conduct?
Responsibility, respect, fairness, and honesty.
How does the primary role of a project sponsor differ from that of a project manager?
The sponsor provides funding and authority, while the project manager manages day-to-day work and leads the team to achieve objectives within scope, time, and budget.
In which organizational structure does the project manager typically have the most authority?
A projectized organizational structure.
What is a project program?
A group of related projects managed in a coordinated way to obtain benefits not available by managing them separately.
What is the primary purpose of a project charter?
To formally authorize a project and give the project manager the authority to use organizational resources.
How does a feasibility study differ from a business case during project initiation?
A feasibility study determines whether a proposed project is practical and viable, whereas a business case justifies why the project is worth the investment.
On a stakeholder power/interest grid, how should a stakeholder with high power and high interest be engaged?
They should be managed closely.
On a stakeholder power/interest grid, how should a stakeholder with low power but high interest be engaged?
They should be kept informed.
What is scope creep?
The uncontrolled expansion of project scope without adjusting time, cost, or resources.
What do the letters stand for in the MoSCoW prioritization method?
Must have, Should have, Could have, and Won't have.
What roles are designated by the acronym in a RACI chart?
Responsible, Accountable, Consulted, and Informed.
What is a Work Breakdown Structure (WBS), and what is its lowest level called?
A hierarchical decomposition of the total project scope into smaller deliverables, where the lowest level is called a work package.
What does the "100% rule" of a Work Breakdown Structure state?
The WBS must include all of the work in the project and nothing more.
According to the 8/80 rule, how much effort should be assigned to a work package?
Between 8 and 80hours of effort.
What is a milestone in a project schedule?
A significant point or event in the project schedule with zero duration.
What is the critical path in project scheduling?
The longest sequence of dependent tasks, which determines the shortest possible project duration.
What is float (slack) in project scheduling?
The amount of time a task can be delayed without delaying the project finish date.
Using the PERT formula 6O+4M+P, what is the estimated duration for a task with an optimistic time of 4days, most likely time of 6days, and pessimistic time of 14days?
7days, calculated as 64+4(6)+14=642=7.
Using the formula 2n(n−1), how many communication channels exist in a team of 6 members?
15 communication channels, calculated as 26(6−1)=230=15.
What is an example of "pull" communication?
Posting project documents on a shared site that stakeholders access when needed.
How does quality control differ from quality assurance?
Quality control inspects deliverables for defects, whereas quality assurance focuses on processes that prevent defects.
What principle governs the use of a Pareto chart in quality management?
About 80% of problems come from about 20% of causes.
What is the primary difference between a project risk and an issue?
An issue has already occurred and requires resolution, whereas a risk is an uncertain future event that might occur.
What risk response strategy involves purchasing insurance to cover potential equipment damage?
Risk transfer.
What risk response strategy involves moving an outdoor event indoors to eliminate the threat of rain?
Risk avoidance.
What is a contingency reserve?
Time or money set aside to address identified risks if they occur.
If a project's planned value (PV) is $10,000 and its earned value (EV) is $8,000, what is the schedule variance (SV) and what does it mean?
SV=EV−PV=$8,000−$10,000=−$2,000, which means the project is behind schedule.
If a project has an earned value (EV) of $9,000 and an actual cost (AC) of $10,000, yielding a Cost Performance Index (CPI) of 0.9, what does this indicate?
The project is over budget because the Cost Performance Index (CPI) is less than 1.0.
How does schedule "crashing" differ from "fast tracking"?
Crashing adds resources to critical path tasks to shorten duration (usually at added cost), while fast tracking performs activities in parallel that were originally scheduled sequentially.
According to Herzberg's two-factor theory, which factor is a motivator rather than a hygiene factor?
Recognition for achievement.
In Tuckman's stages of team development, which stage involves conflict as members compete for position?
Storming.
In Tuckman's stages of team development, which stage is characterized by developing cohesion and agreed-upon ways of working?
Norming.
What is the purpose of resource leveling and how does it commonly affect the project schedule?
It adjusts task dates to balance resource demand, which may extend the project schedule.
What does a burndown chart track over time?
The amount of work remaining over time.
What must be obtained from the customer or sponsor before a project can be officially closed?
Formal acceptance, or sign-off, of the deliverables.
What should a project manager do if a project is canceled prior to completion?
Still perform closing procedures and document the reasons for cancellation.
Why should project financial accounts be closed at the end of a project?
To prevent additional charges from being made to the project.
If a project costs $10,000 and generates a financial gain of $15,000, what is the return on investment (ROI)?
50%, calculated as \frac{\$15{,}000 - \$10{,}000}{\10{,}000} \times 100\% = \frac{\5{,}000}{\$10{,}000} \times 100\% = 50\%.