Comprehensive practice flashcards covering foundational concepts, initiating, planning, executing, monitoring, controlling, and closing processes from FBLA Project Management Practice Tests 1 and 2.

43 Terms

1
New cards

What is the definition of a project?

A temporary endeavor undertaken to create a unique product, service, or result.

2
New cards

What characteristic most clearly distinguishes a project from ongoing operations?

A project has a definite beginning and end.

3
New cards

What three factors traditionally make up the "triple constraint" of project management?

Scope, time, and cost.

4
New cards

What is the correct sequence of the project management process groups?

Initiating, planning, executing, monitoring and controlling, and closing.

5
New cards

What constitutes a conflict of interest in project management?

A situation where personal interests could improperly influence professional decisions.

6
New cards

What are the four core values of the PMI Code of Ethics and Professional Conduct?

Responsibility, respect, fairness, and honesty.

7
New cards

How does the primary role of a project sponsor differ from that of a project manager?

The sponsor provides funding and authority, while the project manager manages day-to-day work and leads the team to achieve objectives within scope, time, and budget.

8
New cards

In which organizational structure does the project manager typically have the most authority?

A projectized organizational structure.

9
New cards

What is a project program?

A group of related projects managed in a coordinated way to obtain benefits not available by managing them separately.

10
New cards

What is the primary purpose of a project charter?

To formally authorize a project and give the project manager the authority to use organizational resources.

11
New cards

How does a feasibility study differ from a business case during project initiation?

A feasibility study determines whether a proposed project is practical and viable, whereas a business case justifies why the project is worth the investment.

12
New cards

On a stakeholder power/interest grid, how should a stakeholder with high power and high interest be engaged?

They should be managed closely.

13
New cards

On a stakeholder power/interest grid, how should a stakeholder with low power but high interest be engaged?

They should be kept informed.

14
New cards

What is scope creep?

The uncontrolled expansion of project scope without adjusting time, cost, or resources.

15
New cards

What do the letters stand for in the MoSCoW prioritization method?

Must have, Should have, Could have, and Won't have.

16
New cards

What roles are designated by the acronym in a RACI chart?

Responsible, Accountable, Consulted, and Informed.

17
New cards

What is a Work Breakdown Structure (WBS), and what is its lowest level called?

A hierarchical decomposition of the total project scope into smaller deliverables, where the lowest level is called a work package.

18
New cards

What does the "100% rule" of a Work Breakdown Structure state?

The WBS must include all of the work in the project and nothing more.

19
New cards

According to the 8/80 rule, how much effort should be assigned to a work package?

Between 88 and 80 hours80\,\text{hours} of effort.

20
New cards

What is a milestone in a project schedule?

A significant point or event in the project schedule with zero duration.

21
New cards

What is the critical path in project scheduling?

The longest sequence of dependent tasks, which determines the shortest possible project duration.

22
New cards

What is float (slack) in project scheduling?

The amount of time a task can be delayed without delaying the project finish date.

23
New cards

Using the PERT formula O+4M+P6\frac{O + 4M + P}{6}, what is the estimated duration for a task with an optimistic time of 4 days4\,\text{days}, most likely time of 6 days6\,\text{days}, and pessimistic time of 14 days14\,\text{days}?

7 days7\,\text{days}, calculated as 4+4(6)+146=426=7\frac{4 + 4(6) + 14}{6} = \frac{42}{6} = 7.

24
New cards

Using the formula n(n−1)2\frac{n(n-1)}{2}, how many communication channels exist in a team of 66 members?

1515 communication channels, calculated as 6(6−1)2=302=15\frac{6(6-1)}{2} = \frac{30}{2} = 15.

25
New cards

What is an example of "pull" communication?

Posting project documents on a shared site that stakeholders access when needed.

26
New cards

How does quality control differ from quality assurance?

Quality control inspects deliverables for defects, whereas quality assurance focuses on processes that prevent defects.

27
New cards

What principle governs the use of a Pareto chart in quality management?

About 80%80\% of problems come from about 20%20\% of causes.

28
New cards

What is the primary difference between a project risk and an issue?

An issue has already occurred and requires resolution, whereas a risk is an uncertain future event that might occur.

29
New cards

What risk response strategy involves purchasing insurance to cover potential equipment damage?

Risk transfer.

30
New cards

What risk response strategy involves moving an outdoor event indoors to eliminate the threat of rain?

Risk avoidance.

31
New cards

What is a contingency reserve?

Time or money set aside to address identified risks if they occur.

32
New cards

If a project's planned value (PVPV) is $10,000\$10{,}000 and its earned value (EVEV) is $8,000\$8{,}000, what is the schedule variance (SVSV) and what does it mean?

SV=EV−PV=$8,000−$10,000=−$2,000SV = EV - PV = \$8{,}000 - \$10{,}000 = -\$2{,}000, which means the project is behind schedule.

33
New cards

If a project has an earned value (EVEV) of $9,000\$9{,}000 and an actual cost (ACAC) of $10,000\$10{,}000, yielding a Cost Performance Index (CPICPI) of 0.90.9, what does this indicate?

The project is over budget because the Cost Performance Index (CPICPI) is less than 1.01.0.

34
New cards

How does schedule "crashing" differ from "fast tracking"?

Crashing adds resources to critical path tasks to shorten duration (usually at added cost), while fast tracking performs activities in parallel that were originally scheduled sequentially.

35
New cards

According to Herzberg's two-factor theory, which factor is a motivator rather than a hygiene factor?

Recognition for achievement.

36
New cards

In Tuckman's stages of team development, which stage involves conflict as members compete for position?

Storming.

37
New cards

In Tuckman's stages of team development, which stage is characterized by developing cohesion and agreed-upon ways of working?

Norming.

38
New cards

What is the purpose of resource leveling and how does it commonly affect the project schedule?

It adjusts task dates to balance resource demand, which may extend the project schedule.

39
New cards

What does a burndown chart track over time?

The amount of work remaining over time.

40
New cards

What must be obtained from the customer or sponsor before a project can be officially closed?

Formal acceptance, or sign-off, of the deliverables.

41
New cards

What should a project manager do if a project is canceled prior to completion?

Still perform closing procedures and document the reasons for cancellation.

42
New cards

Why should project financial accounts be closed at the end of a project?

To prevent additional charges from being made to the project.

43
New cards

If a project costs $10,000\$10{,}000 and generates a financial gain of $15,000\$15{,}000, what is the return on investment (ROIROI)?

50%50\%, calculated as \frac{\$15{,}000 - \$10{,}000}{\10{,}000} \times 100\% = \frac{\5{,}000}{\$10{,}000} \times 100\% = 50\%.