1/33
Looks like no tags are added yet.
If EPA regulations change after a technician has been certified
it is the technician's responsibility to comply with future changes
Why is it easier to have air enter gaskets and fittings on a low-pressure system than a high-pressure system?
because a low-pressure system operates in a vacuum
At what pressure does a rupture disc open on a low-pressure system?
at 15 psig
What is the easiest way to leak test a low-pressure system?
add warm water over the coil to raise the pressure to 10 psig
Why is it important not to exceed 10 psig when leak testing a low-pressure system?
because the rupture disc, located on the evaporator, may fail
When using an electronic leak detector, where is a water box leak tested after the water has beenremoved?
at the drain valve
What is used when leak testing a water tube on a low-pressure chiller?
a hydrostatic tube kit
The EPA requires that all comfort cooling systems with more than 50 lb of refrigerant be repaired whenthe annual leak rate exceeds
10%
The EPA requires that all commercial and industrial process refrigeration systems with morethan 50 lbs of refrigerant be repaired when the annual leak rate exceeds
20 and 30%
What pressure is a high-pressure cut-out set for on a recovery system that is used onlow-pressure refrigeration systems?
10 psig
When recovering R-11 or R-123 from a low-pressure system, always recover
liquid first
What is commonly done to prevent a low-pressure system from freezing during evacuation?
run the water through the chiller tubes
What does the ASHRAE guideline 3-1990 state about a vacuum test?
If a 1 mm Hg vacuum level rises to 2.5 mm Hg, the system should be leak tested
How is refrigerant added to a low-pressure chiller system after an evacuation?
by the use of the evaporator charging valve
After a chiller system has had a deep system evacuation, what is commonly done to decrease thepossibility of system freeze-up prior to a liquid charge?
pressurize the system with vapor up to the saturation temperature
When using recovery or recycling equipment manufactured or imported before November 15,1993, the required level of evacuation for low-pressure equipment is
25 Hg
When using recovery or recycling equipment manufactured or imported on or afterNovember 15, 1993, the required level of evacuation for low-pressure equipment is
25 mm Hg absolute
What is used on low-pressure chillers to remove non-condensables from the system?
a purge unit
From where does the purge unit remove trapped air in a low-pressure system?
the top of the condenser
The equipment room that contains a chiller using R-123 group B-1 refrigerant requires a(n)
refrigerant sensor
It is important to recover the vapor refrigerant in a chiller after the liquid has been removed, since there is approximately ______ lbs of vapor in a common 350 ton R-11 chiller.
100
When leak testing a low pressure centrifugal chiller with nitrogen, what is the maximum test pressure?
10 psig
Charged low pressure refrigeration machines may be most efficiently leak checked by:
raising system pressure by heating with circulated hot water or heating blankets
With a low pressure chiller what must you do after recovering the liquid refrigerant?
recover the vapor refrigerant
When removing oil from a low pressure system, the temperature should be 130 F because,
less refrigerant will be contained in the oil at the higher temperature
After a system servicing, why is refrigerant vapor re-introduced to the refrigeration systembefore refrigerant liquid?
Liquid charged into a deep vacuum will boil and may lower temperatures enough to freezewater in the tubes
Appliances need not be evacuated all the way to the prescribed level when;
leaks in the appliance make evacuation to the prescribed level unattainable
After reaching the required recovery vacuum on an appliance, you should
wait for at least a few minutes to see if the system pressure rises, indicating that there is stillrefrigerant in liquid form or in the oil
Under EPA's regulations, which of the following methods can be used to pressurize an R-11 or R-123 system for thepurpose of opening the system for a non-major repair?
Adding nitrogen
During vapor removal from a low pressure refrigeration system
the system water pumps, the recovery compressor, and the recovery condenser water should all be on
Which of the follow safety precautions should be adhered to for low pressure systems?
-Do not siphon refrigerant by mouth
-Avoid spilling liquid refrigerant on the skin
-Use gloves and safety goggles when working liquid refrigerant
When recharging a refrigeration system with R-11, what vapor pressure is necessary in the shells before chargingwith liquid
16.9" Hg vacuum
A centrifugal chiller's rupture disk isconnected to the chiller's
Evaporator
What is the primary water source for arecovery unit condensing coil?
Local municipal water supply