1
New cards

If EPA regulations change after a technician has been certified

it is the technician's responsibility to comply with future changes

2
New cards

Why is it easier to have air enter gaskets and fittings on a low-pressure system than a high-pressure system?

because a low-pressure system operates in a vacuum

3
New cards

At what pressure does a rupture disc open on a low-pressure system?

at 15 psig

4
New cards

What is the easiest way to leak test a low-pressure system?

add warm water over the coil to raise the pressure to 10 psig

5
New cards

Why is it important not to exceed 10 psig when leak testing a low-pressure system?

because the rupture disc, located on the evaporator, may fail

6
New cards

When using an electronic leak detector, where is a water box leak tested after the water has beenremoved?

at the drain valve

7
New cards

What is used when leak testing a water tube on a low-pressure chiller?

a hydrostatic tube kit

8
New cards

The EPA requires that all comfort cooling systems with more than 50 lb of refrigerant be repaired whenthe annual leak rate exceeds

10%

9
New cards

The EPA requires that all commercial and industrial process refrigeration systems with morethan 50 lbs of refrigerant be repaired when the annual leak rate exceeds

20 and 30%

10
New cards

What pressure is a high-pressure cut-out set for on a recovery system that is used onlow-pressure refrigeration systems?

10 psig

11
New cards

When recovering R-11 or R-123 from a low-pressure system, always recover

liquid first

12
New cards

What is commonly done to prevent a low-pressure system from freezing during evacuation?

run the water through the chiller tubes

13
New cards

What does the ASHRAE guideline 3-1990 state about a vacuum test?

If a 1 mm Hg vacuum level rises to 2.5 mm Hg, the system should be leak tested

14
New cards

How is refrigerant added to a low-pressure chiller system after an evacuation?

by the use of the evaporator charging valve

15
New cards

After a chiller system has had a deep system evacuation, what is commonly done to decrease thepossibility of system freeze-up prior to a liquid charge?

pressurize the system with vapor up to the saturation temperature

16
New cards

When using recovery or recycling equipment manufactured or imported before November 15,1993, the required level of evacuation for low-pressure equipment is

25 Hg

17
New cards

When using recovery or recycling equipment manufactured or imported on or afterNovember 15, 1993, the required level of evacuation for low-pressure equipment is

25 mm Hg absolute

18
New cards

What is used on low-pressure chillers to remove non-condensables from the system?

a purge unit

19
New cards

From where does the purge unit remove trapped air in a low-pressure system?

the top of the condenser

20
New cards

The equipment room that contains a chiller using R-123 group B-1 refrigerant requires a(n)

refrigerant sensor

21
New cards

It is important to recover the vapor refrigerant in a chiller after the liquid has been removed, since there is approximately ______ lbs of vapor in a common 350 ton R-11 chiller.

100

22
New cards

When leak testing a low pressure centrifugal chiller with nitrogen, what is the maximum test pressure?

10 psig

23
New cards

Charged low pressure refrigeration machines may be most efficiently leak checked by:

raising system pressure by heating with circulated hot water or heating blankets

24
New cards

With a low pressure chiller what must you do after recovering the liquid refrigerant?

recover the vapor refrigerant

25
New cards

When removing oil from a low pressure system, the temperature should be 130 F because,

less refrigerant will be contained in the oil at the higher temperature

26
New cards

After a system servicing, why is refrigerant vapor re-introduced to the refrigeration systembefore refrigerant liquid?

Liquid charged into a deep vacuum will boil and may lower temperatures enough to freezewater in the tubes

27
New cards

Appliances need not be evacuated all the way to the prescribed level when;

leaks in the appliance make evacuation to the prescribed level unattainable

28
New cards

After reaching the required recovery vacuum on an appliance, you should

wait for at least a few minutes to see if the system pressure rises, indicating that there is stillrefrigerant in liquid form or in the oil

29
New cards

Under EPA's regulations, which of the following methods can be used to pressurize an R-11 or R-123 system for thepurpose of opening the system for a non-major repair?

Adding nitrogen

30
New cards

During vapor removal from a low pressure refrigeration system

the system water pumps, the recovery compressor, and the recovery condenser water should all be on

31
New cards

Which of the follow safety precautions should be adhered to for low pressure systems?

-Do not siphon refrigerant by mouth

-Avoid spilling liquid refrigerant on the skin

-Use gloves and safety goggles when working liquid refrigerant

32
New cards

When recharging a refrigeration system with R-11, what vapor pressure is necessary in the shells before chargingwith liquid

16.9" Hg vacuum

33
New cards

A centrifugal chiller's rupture disk isconnected to the chiller's

Evaporator

34
New cards

What is the primary water source for arecovery unit condensing coil?