Comprehensive vocabulary flashcards for the LANL Project Engineer Oral Checkout examination, covering institutional governance, roles and responsibilities, safety basis concepts, change control, engineering documentation, and technical baseline management.

49 Terms

1
New cards

Conduct of Engineering (CoE) Program

A governing framework and flow-down structure established to define concise engineering requirements, efficient engineering processes, and training and qualification requirements to ensure personnel perform safe, compliant, and high-quality facility engineering work.

2
New cards

LANL Design Authority

The authority formally designated through PD340 to the Engineering Services Division Leader (ES-DL), who also holds the title Site Chief Engineer and is responsible for facility engineering design authority.

3
New cards

Facility Design Authority Representative (FDAR)

The single, accountable individual qualified and designated for a specific facility, program, or project who is responsible for approving design inputs, design outputs, design requirements, design configuration, and design changes throughout the project lifecycle.

4
New cards

LANL Building Official (LBO)

The designated Authority Having Jurisdiction (AHJ) and technical authority for the application and interpretation of LANL's building codes, specifically the International Building Code (IBC) and International Existing Building Code (IEBC).

5
New cards

Facility Operations Director (FOD)

The senior line manager and facility owner steward who provides organizational leadership and overall accountability for ensuring that all facility and programmatic activities are performed safely and in compliance with Laboratory, DOE, and governmental requirements.

6
New cards

Cognizant System Engineer (CSE)

A specialized, DOE-mandated engineer responsible for maintaining configuration management, overall engineering cognizance, continued operability, and performance of assigned Vital Safety Systems (Safety Class and Safety Significant systems) in Hazard Category 1, 2, and 3 nuclear facilities.

7
New cards

System Engineer

An engineer responsible for general engineering oversight of facility systems broadly, distinct from a DOE-mandated Cognizant System Engineer (CSE) who specifically oversees Vital Safety Systems.

8
New cards

Safety Function

A function of a System, Structure, or Component (SSC) credited in a facility's Documented Safety Analysis (DSA), hazard analysis, or other safety basis document with preventing, mitigating, or detecting a hazard.

9
New cards

Design Feature

Passive characteristics of a facility specified in the Technical Safety Requirements (TSRs) that are important to safety, not subject to routine modification by operations personnel, and do not require (or infrequently require) maintenance or surveillance, but would have a significant effect on safe operation if altered.

10
New cards

Safety Analysis

A documented process providing systematic identification of hazards within a given DOE operation, describing and analyzing the adequacy of controls to eliminate or mitigate those hazards, and evaluating potential accidents and their associated risks.

11
New cards

Defense in Depth

A safety approach (illustrated by the 'Swiss Cheese Model') that provides multiple independent layers of defense against a specific hazard or accident scenario so that no single layer is solely relied upon.

12
New cards

Administrative Control

Provisions relating to organizational and management procedures, record keeping, assessments, and reporting necessary to ensure the safe operation of a facility by modifying how work is performed without altering equipment design.

13
New cards

Technical Safety Requirements (TSRs)

The limits, controls, and related actions (such as safety limits, operating limits, surveillance requirements, and administrative controls) establishing the specific parameters and requisite actions for safe operation of a nuclear facility under 10 CFR 830.

14
New cards

Limiting Conditions of Operation (LCO)

The limits that represent the lowest functional capability or performance level of safety-related structures, systems, and components required for safe operations.

15
New cards

Authorization Basis

Those aspects of facility design and safety documentation (including DSA, TSRs, hazard classifications, permits, and DOE commitments) relied upon by the DOE to authorize facility operation.

16
New cards

Unreviewed Safety Question (USQ)

A situation defined under 10 CFR 830.203 where a proposed change, test, experiment, or discovery could increase the probability or consequences of a previously evaluated accident, create a new type of accident/malfunction, or indicate that the documented safety analysis may be inadequate.

17
New cards

Potential Inadequacy of the Documented Safety Analysis (PISA)

A condition discovered in a nuclear facility where the existing safety analysis potentially may not be bounding or is otherwise inadequate, requiring actions to place the facility in a safe condition, DOE notification, and a USQ determination.

18
New cards

Priority Document

A technical document required to respond to events causing loss of life, serious injury, or environmental damage; support facility operation within its approved safety envelope; or perform TSRs, OSRs, or Accelerator Safety Envelope conditions (e.g., evacuation routes, specific P&IDs, electrical single-lines).

19
New cards

Support Document

A technical document needed to safely maintain and operate a facility, such as lockout/tagout procedures, venting procedures, and system operating instructions.

20
New cards

General Document

A technical document providing engineering details necessary for procurement of replacement parts, modifications, maintenance, and operation of SSCs that is not classified as a priority or support document.

21
New cards

Graded Approach (Administrative Control)

An approach governed primarily by SD330 that scales the rigor of administrative controls—analysis, documentation, and oversight—based on risk, hazard level, and safety/security significance rather than applying a uniform level of control.

22
New cards

Preliminary Project Determination (PPD)

A document prepared using ESM Chapter 16 Form 1 by the Responsible Engineer and approved by the FDAR to provide early and timely design input relative to International Building Code (IBC) and other institutional requirements for non-repair jobs.

23
New cards

Requirements and Criteria Document (RCD)

The primary design input document governing project design work, included in the Statement of Work to the Design Agency, which documents the complete basis of design at the end of the Conceptual Design Phase.

24
New cards

Functions and Requirements Document (FRD)

A document that captures the systematically decomposed functions and requirements to be performed by facility SSCs, serving as a primary source for creating the Requirements and Criteria Document (RCD).

25
New cards

Permits and Requirements Identification (PRID)

A project planning tool that facilitates interactive communication among project team personnel and institutional SMEs early in planning to identify LANL, State, and Federal requirements and document compliance.

26
New cards

Change Control Objective

The process objective to maintain consistency among design requirements, physical configuration, and related facility documentation during and after the implementation of a change.

27
New cards

Equivalent Change

A hardware change that continues to meet all original design requirements and interface requirements for the equipment without impacting the facility safety basis.

28
New cards

Like-for-Like Replacement Item

The replacement of an item with one that is identical, purchased from the same vendor with identical design, materials, and processes, or manufactured in the same timeframe/lot.

29
New cards

Equivalent Replacement Item

A replacement item that is not physically identical to the original, requiring a formal engineering equivalency evaluation to confirm that its intended design and safety functions are fully maintained.

30
New cards

Temporary Modification (TM)

A modification installed for six months or less to facility SSCs (such as lifted leads, jumpers, pulled breakers, or bypass lines) where the configuration is fully restorable to its original baseline.

31
New cards

Design Revision Notice (DRN)

A change control mechanism used to process complex design changes that introduce new functions or requirements exceeding project definition documents, or that require substantial reanalysis or new analysis.

32
New cards

Field Change Request (FCR)

A change control mechanism used to process field design changes within existing project scope that do not rise to the level of a DRN and do not introduce new functions or requirements.

33
New cards

Interim Work Release Request (IWR)

A request issued as part of an FCR to allow construction implementation to proceed while the FCR is being processed, restricted to items that do not affect the safety basis, ALARA, or fire protection, and will not be embedded in concrete.

34
New cards

Technical Baseline

All documents, including safety basis documentation, used to identify, justify, and demonstrate the physical, functional, and operational requirements of configuration-controlled SSCs.

35
New cards

Work Control Process

An administrative process used to identify, initiate, plan, schedule, coordinate, perform, approve, validate, and review work activities to maintain consistency between documentation, procedures, and physical configuration.

36
New cards

Master Equipment List (MEL)

A subset of Computerized Maintenance Management System (CMMS) data used for configuration management and maintenance tracking, containing unique identifiers and key attributes (such as Management Level) for facility SSCs.

37
New cards

Design Information Reconstitution

The process governed by AP-341-511 to identify, retrieve, regenerate, and document missing design basis and design requirements for existing SSCs in operating facilities to establish a valid technical baseline.

38
New cards

Field Walk Down

An engineering activity conducted under AP-341-510 to capture as-found technical baseline information, inspect material conditions, verify physical versus document consistency, and check for equipment interactions.

39
New cards

As-Built Drawing

Engineering documentation verified by physical inspection as depicting the actual physical configuration and confirmed to be consistent with design requirements.

40
New cards

As-Found Drawing

Drawings or marked-up documents reflecting the actual physical configuration of a system as discovered in the field, identifying any discrepancies with currently approved documentation.

41
New cards

Baseline Drawing Change Notice (BDCN)

A form used under AP-341-608 to document unincorporated changes to a single approved baseline drawing without immediately requiring a full redraw and re-issue.

42
New cards

Engineering Specification

A written technical document that describes materials, equipment, systems, standards, and workmanship requirements to complement graphical descriptions provided in engineering drawings.

43
New cards

Management Level (ML)

A classification system that grades SSCs based on an estimation of failure consequences to establish the appropriate level of technical oversight, quality assurance, and administrative control.

44
New cards

Management Level 1 (ML-1)

The classification assigned to SSCs and activities in Hazard Category 2 or 3 nuclear facilities that perform Documented Safety Analysis (DSA) credited Safety Class (SC) functions, or public protection functions in accelerator and high-hazard facilities.

45
New cards

Management Level 2 (ML-2)

The classification assigned to SSCs and activities in Hazard Category 2 or 3 nuclear facilities that perform DSA credited Safety Significant (SS) functions, or worker protection functions in accelerator and high-hazard facilities.

46
New cards

Critical Characteristics

The essential design, material, and performance properties or attributes of an item or service that, once verified, provide reasonable assurance that the item will perform its intended safety function.

47
New cards

Post-Modification Testing (PMT)

Testing performed following an SSC modification to confirm installation complies with design, verify functional and performance requirements are met, ensure no new deficiencies were created, and validate return-to-service readiness.

48
New cards

Post-Maintenance Testing (PMT)

Testing performed following maintenance activities to verify that the original deficiency has been corrected, no new deficiencies were introduced, and the SSC performs its intended function prior to returning to service.

49
New cards

Configuration Management (CM)

A disciplined process involving technical and management direction to establish consistency between design requirements, physical configuration, and facility documentation throughout the facility lifecycle.