Net present value (NPV)

  • is?

  • NPV discounts?

  • Positive NPV means? Accept or Decline?


The difference between an investment's market value (the PV of its future cash flows) and its cost.

NPV discounts an investment's FUTURE CASH FLOWS (not profits).

Positive NPV = the project is expected to create value for its owners → accept.

| Clue: cost vs. market value

2
New cards

is NPV the best single method? why?

  • If you can only pick ONE method to analyze a variety of projects, use NPV.

  • It's also the best method for mutually exclusive projects, and a positive NPV is the best assurance a project will create value.

| Clue: when in doubt, NPV

3
New cards

Internal rate of return (IRR) - expected cash inflow/outflows on project

  • is?

  • accept if?

  • when is NPV = 0


  • The discount rate (YTM: market return) that makes a project's NPV equal ZERO.

  • Accept if : IRR is > the required return.

  • If IRR= the required return, its NPV is zero.

| Clue: "NPV = 0"

4
New cards

NPV profile is

A graph showing how a project's NPV changes as the DISCOUNT RATE changes.

Where the line crosses zero is the IRR, so the NPV profile is most closely related to IRR.

| Clue: NPV vs. discount rate

5
New cards

Multiple rates of return

When MORE than one discount rate makes NPV equal zero (happens with non-normal cash flows). A weakness of IRR. | Clue: "more than one" IRR

6
New cards

Mutually exclusive projects

Choosing one project eliminates the option to choose the other, even if both are acceptable on their own.

Use NPV to choose between them (IRR can give the wrong ranking).

| Clue: pick A OR B, not both

7
New cards

Profitability index (PI)

A benefit-cost ratio: the PV of future cash flows compared to the initial cost.

Shows the value created per dollar INVESTED (the dollar return per dollar spent).

  • PI above 1.0 = accept;

  • PI below 1.0 = reject.

| Clue: "per dollar invested"

8
New cards

Payback period

The length of time it takes an investment to generate enough cash flows to RECOUP its initial cost.

A shorter payback is preferred.

Accept if payback is shorter than the required cutoff.

| Clue: "recoup its initial cost"

9
New cards

Payback: pros and cons

PROS - EASE OF USE.

CONS - it IGNORES the time value of money, uses an arbitrary cutoff, ignores cash flows after the cutoff, and is biased toward SHORT-TERM projects.

Best for low-cost, short-term projects.

| Clue: payback = only method that ignores time value

10
New cards

Average accounting return (AAR)

A project's average net income DIVIDED by its average book value.

Uses accounting numbers, not cash flows.


| Clue: "average net income ÷ average book value"

11
New cards

Accept/reject signals

ACCEPT: positive NPV, PI above 1.0, IRR above the required return, payback shorter than the cutoff. REJECT: PI below 1.0, negative NPV, IRR below the required return.

| Clue: PI below 1 = reject

12
New cards

What CFOs use most

Surveys show CFOs most frequently use IRR and NPV. | Clue: IRR + NPV

13
New cards

Incremental cash flows

Any changes to a firm's future cash flows that are caused by taking on a new project. Only these matter when evaluating a project. | Clue: "caused by adding a new project"

14
New cards

Stand-alone principle

The assumption that a project is evaluated based only on its own incremental cash flows, like a mini-firm on its own. | Clue: evaluate the project by itself

15
New cards

Sunk cost

A cost already incurred that can't be recouped. IGNORE it when evaluating a project. | Example: a $2.2M furnace that can't be used or sold

16
New cards

Opportunity cost

The value of the best alternative given up when you choose an investment. INCLUDE it in the analysis. | Example: using land or a building you own → its CURRENT MARKET VALUE is the cost (not what you paid)

17
New cards

Pro forma financial statements

Statements that project FUTURE years' operating results. | Clue: "projected"

18
New cards

Depreciation tax shield and accelerated depreciation

Depreciation tax shield: the amount a firm's tax bill is reduced because of depreciation expense. Accelerated cost recovery system (ACRS/MACRS): a method that INCREASES the rate at which an asset is depreciated. | Clue: depreciation lowers taxes

19
New cards

Forecasting risk

The risk that bad estimates lead to bad decisions; also called estimation risk. | Clue: "estimation risk"

20
New cards

Scenario analysis vs. sensitivity analysis

Scenario analysis: changes SEVERAL variables at once (sales quantity, price, and costs) to see the NPV under different conditions. Sensitivity analysis: changes ONE variable (e.g., only sales quantity) to see its effect on NPV. | Clue: one variable = sensitivity; several = scenario

21
New cards

Managerial options, contingency planning, strategic options

Managerial options: chances to modify a project after it starts. Contingency planning: focuses on the managerial options built into a project. Strategic option: the option to expand into related businesses in the future. | Clue: expand into related businesses = strategic

22
New cards

Capital rationing

A firm has positive-NPV projects but can't get (or won't allocate) enough financing for all of them. | Clue: good projects, no money