Value-adding (VA) step
A step the customer is willing to pay for and that directly gives them the outcome they want (e.g., deliver product, examine patient)
Business value-adding (BVA) step
A step the business needs but the customer doesn't value: reduces risk, earns revenue or meets regulations (e.g., credit check, inspection)
Non-value-adding (NVA) step
A step that adds no value: handoffs, waiting, rework (e.g., repairing a defect, re-entering data)
Repairing a defective product
NVA (defect / rework)
Reducing risk of business losses
BVA
Step essential to the quality the customer enjoys
VA
VA goal / BVA goal / NVA goal
Maximize VA, minimize BVA, eliminate NVA
7 wastes (Move, Hold, Over-do)
Move: transportation, motion. Hold: inventory, waiting. Over-do: defects, over-processing, over-production
Over-processing
Doing more work or using more resources than the case needs (e.g., non-urgent patient using the ER)
Immediate goal of waste analysis
To IDENTIFY waste (removing it happens later in redesign)
Issue register
Maintains, organizes and prioritizes weaknesses; focuses on HIGH-LEVEL issues and their tangible/intangible impact
Issue register used with
Why-why diagrams and cause-effect diagrams (they document the factors behind top-level issues)
Why-why diagram
Explores root causes of an issue by repeatedly asking "why?"
Cause-effect (fishbone) diagram
Groups root causes into 6 categories (6Ms); a QUALITATIVE technique
6Ms
Machine, Method, Material, Man, Measurement, Milieu (Mother Nature/environment)
Technique that identifies non-value steps
Value classification
Qualitative analysis happens in which lifecycle phase
Process analysis (NOT process identification)
Cycle time
Processing time + waiting time
Processing time
Time a case is actually being worked on; also called theoretical cycle time
Waiting time
Time a case spends idle
Sequence cycle time
CT = T1 + T2 + … + Tn
XOR block cycle time
CT = p1 × T1 + p2 × T2 (weighted by probability)
AND block cycle time
CT = max(T1, T2) (longest branch)
Rework loop cycle time
CT = T / (1 − r), where r = probability of going back
Example: A=5, B=10 with 20% rework, C=5
5 + 10/(1 − 20%) + 5
Example: A=5, AND(B=10, C=20), D=5
5 + 20 + 5
Cycle time efficiency
Processing time (theoretical CT) ÷ cycle time; close to 0 = lots of waiting
Can flow analysis calculate cost?
Yes, the same equations work for cost
Little's Law
WIP = λ × CT
WIP
Average number of items inside the process at a given time
λ (lambda)
Arrival rate = arrivals ÷ time period (e.g., 300 customers ÷ 6 h = 50/h)
Little's Law assumptions
Stable average arrival/departure rates; jobs leave as soon as they are completed
Utilization ρ (M/M/c)
ρ = λ ÷ (c × μ) (e.g., 5 claims/day ÷ (2 clerks × 2/day))
Run-time flexibility
Adapting while the process is running, without redesign (e.g., adding staff in a rush)
Build-time flexibility
Changing the process design itself (e.g., adding self-service)
Devil's Quadrangle
Time, cost, quality, flexibility; improving one often hurts another
Main performance measures
Time, cost, quality, flexibility (NOT waste or value added)
Triage
Split a general task into specialized ones (e.g., credit-limit requests go to a specialist unit)
Integration
Link with the customer's or supplier's process (e.g., patient vitals sent from home to the clinic)
Parallelism
Run tasks at the same time (e.g., process order and update inventory together)
Resequencing
Move tasks to better places; knock-out checks first
Control relocation
Move checks to the customer
Contact reduction
Fewer contacts with customers and third parties
Activity elimination
Remove NVA steps
Activity composition
Merge small tasks into one
Does redesign use process analysis insights?
Yes, it builds on qualitative and quantitative analysis
Does redesign always lead to changes?
No, it may end up with no feasible solutions
Does redesign produce one solution?
No, it is iterative and proposes several alternatives