Calculate payback period
find accumulated cash flows for each year
payback period = break even year + (acc cash flow that year / cash flow next year)
Accumulated cash flows equation
acc cash flow n-1 + cash flow n
Crossover rate
Find difference between cash flow of each project
IRR function of the answers
Operating cash flow equation
EBIT + depreciation - taxes
Annual deprecation formula
total depreciation / lifetime
Accumulated depreciation at year n
annual deprecation * n
taxes on salvage value
(sale price - book value)*tax rate
aftertax salvage value
sale price - taxes on salvage value
book valye at year n
cost - acc depreciation
MACRS Schedule find book value
cost - (cost*(sum of percentages for each year of project)
MARCS Schedule after tax salvage value
sale price - (sale price - book value)*tax rate

Steps from word problem
Find cash flows: year 0 is total depreciation, rest of years of project is OCF
Market value of debt
price of coupon bonds * par value * quote price(percentage)
Market value of common stock
shares of cs * price per share
market value of preferred stock
shares of ps * price per share
total market value
sum of MVd, MVcs, MVps
Cost of capital of debt
rate function * price per share
cost of capital of common stock
(CAPM + Gordon model)/2
cost of capital of preferred stock
(percent of ps * par value)/price per share
WACC
(MVd/V)*+ (MVcs/V)*rcs + (MVps/V)*rps

Steps for WACC using debt to equity etc.
WACC = (debt-equity ratio/1+d.e ratio)*aftertax cost + (1/(1+d.e ratio))*cost of equity
Project discount = WACC + adjustment factor