What two essential characteristics define a project
A project has a definite beginning and end and produces a unique product
Project management
A discipline compromising methods, theories, and techniques that serves as both an art and a science to guide project activities
Why is project management considered a strategic strength for an organization
It aligns project execution with executive goals and enables smoother cross-functional team performance
How do projects differ from operations in terms of their duration
Projects have a defined completion date, whereas operations are ongoing with no defined end
How do projects differ from operations regarding their outputs
Projects produce, whereas operations continuously produce standardized or identical outputs
What three primary constraints make up the ‘iron triangle’ of project management
The three constraints are scope, time (schedule), and cost, with quality at the center
How is success traditionally defined for a project
Success is defined as delivering the agreed scope on a time and within budget
What are the three fundamental functions of project management
The three functions are project definition, project planning, and project control
What is the primary objective of the project definition function
It lays out the baseline foundation, boundaries, and governing rules for the project
What is the primary objective of the project planning function
It formulates detailed operational steps to achieve project goals within identified constraints
What is the primary objective of the project control function
It tracks progress, facilitates communication, and applies corrective actions to keep the project on target
What three core skill sets are required for an effective project manager
The required skill set are project management discipline, business management software skills, and field specific technical competence
How does the applicability of project management discipline compare to technical skills across industries
The project management discipline is industry independent, whereas technical skills are industry specific
How does a product life cycle differ from a project life cycle
A product life cycle is industry specific and encompasses creating the product, whereas a project life cycle is industry independent and focuses on managing the work
In a function-driven organization, how much authority does the project manager typically possess
The project manager possesses minimal formal authority and must seek cooperation from functional managers
In a project-oriented organization, who holds primary authority over resources
The project manager holds primary authority over resources and project execution
What defines authority in a matrix organizational structure
Project managers share equal authority, and staff report to both
Who qualifies as a project stakeholder
Anyone who actively contributes to the project or is impacted by its outcomes
In stakeholder management, how does a role differ from a position
A role reflects a persons specific involvement and influence in a project, whereas a position is their formal organizational job title
What primary responsibility does a project sponsor hold
The sponsor provides executive support, secures funding, and confers legitimate authority on the project
What primary roles do the project customers fulfill
Customers establish project requirements and provide project funding
What is the primary purpose of a stakeholder register
It documents key information, contact details, organizational positions, and specific project roles for all stakeholders
Managing upward
The practice of guiding and influencing project stakeholders who hold higher formal organizational authority than the project manager
What is the most effective way for a project manager to handle unreasonable stakeholder schedule demands
Present a factual, data-driven work breakdown and realistic timeline to reset expectations
Why is it necessary to formalize project rules through key documents
Project rules secure agreement on goals, establish scope control, and foster clear stakeholder communication
What is the main objective of a project charter
To formally authorize the existence of a project and grant the project manager legitimate authority
How does legitimate authority differ from expert authority
Legitimate authority is conferred formally by the organization, whereas expert authority is earned through job performance
What standard process must be followed when changes occur to a project charter
The charter must be updated to reflect changes, and all key stakeholders must agree to those updates
What minimal elements must be included in a project charter
It must include a purpose statement, scope description, deliverables list, cost and schedule estimates, measures of success, stakeholders, and chain of command
What should be states in ten purpose statement of a project charter
It should clearly outline what the project will be accomplished, why it is being undertaken, and its measurable result goals
Where should detailed financial ROI and justification metrics be placed if not in the project charter
They should be contained in a separate business case, proposal, or cost-benefit analysis document
How does the scope description section of a project charter help prevent scope creep
It defines major project activities and explicitly lists items that fall outside the project scope
What is the function of the deliverables section in a project charter
It details all intermediate outputs, final products, and project management artifacts produced by the project
What is the purpose of defining measures of success in a project charter
To set quantifiable exit standards that verify acceptable project completion
Responsibility matrix
A grid detailing the participation level and authority role of key stakeholders across major project activities
In a RACI responsibility matrix, what does the letter ‘R’ represent
‘R’ stands for responsible, indicating the party executing the actual work
In a RACI responsibility matrix, what does the letter ‘A’ represent
‘A’ stands for approval (or accountable), indicating the party with final decision-making authority
In a RACI responsibility matrix, what does the letter ‘C’ represent
‘C’ stands for Consulted, indicating subject matter experts whose input is required prior to execution
In a RACI responsibility matrix, what does the letter ‘I’ represent
‘I’ stands for informed, indicating stakeholders whose must be updated on progress and outcomes
Project risk
An uncertain event or condition that, if it occurs, has a positive or negative impact on project objectives
How do known risks differ from unknown risks
Known risks are identified uncertainties that can be partially planned for, whereas unknown risks are completely unpredictable
How does a business risk differ from a project risk
Business risk focuses on choosing the right project to undertake, whereas project risk focuses on managing uncertainties to meet project objectives
Who holds primary accountability for managing business risk
Executive management holds accountability for business risk, not the project manager
What is the main purpose of project risk management
To systematically manage uncertainty in order to increase the probability of achieving project success
What is the first step in the risk management framework
Step one - identify potential risks using stakeholder feedback, historical records, and risk profiles
Risk profile
A standard set of questions probing typical vulnerability areas across past projects to aid risk identification
What two elements are required to construct a formal risk definition statement
A formal risk definition requires a condition statement (the situation causing concern) and a consequence statement (the negative outcome)
What formula is used to calculate the expected value of a project risk
Expected value = probability x impact
What action characterizes the ‘Accept’ risk response strategy
Taking no proactive action and absorbing the consequences if the risk materializes
What action characterizes the ‘Avoid’ risk response strategy
Changing the project plan or approach to completely eliminate the risk exposure
What is the purpose of a contingency plan in risk management
To outline an alternate preplanned action that will be executed if a monitored risk event occurs
In risk management, what is a trigger event
A predetermined threshold or event that signals when to activate a contingency plan
What does detectability measure in project risk analysis
The ease and speed with wich a risk condition can be identified before it inflicts damage
What action characterizes the ‘Transfer’ risk response strategy
Reallocating the financial or operational responsibility of a risk to a third party
What action characterizes the ‘Mitigate’ risk response strategy
Proactively taking steps to lower the probability or impact of a risk before it occurs
What type of risks are contingency reserves allocated to cover
Contingency reserves cover identified known risks (known unknowns)
What type of risks are management reserves set aside to cover
Management reserves cover unpredictable unknown risks (unknown unknowns)
What is the primary function of a risk log during project execution
To continuously document, monitor, track ownership of, and update the status of identified risks
What common IT project risk categories should be evaluated during risk identification
The broad categories are market risk, financial risk, technology risk, people risk, and structure/process risk
Work breakdown structure
A deliverable-oriented hierarchical breakdown of all the work required to fulfill project objectives
How does a summary task differ from a work package in the WBS
A summary task represents a higher-level grouping, whereas a work package is the lowest-level unit that can be estimated and assigned
Who is a WBS insufficient on its own for building a project schedule
A WBS outlines project scope components but does not define the sequence constraints or execution order of tasks
Sequence constraints
Logical restrictions specifying the mandatory order on which tasks must be performed
In a Finish-to-Start (FS) dependency, when can task B begin
Task B can begin only after predecessor Task A has finsihed
In a Start-to-Start (SS) dependency, when can task B begin
Task B can begin only after predecessor Task A has started
In a Finish-to-Finish (FF) dependency, when can Task B finish
Task B can finish only after predecessor Task A has finished
In Start-to-Finish (SF) dependency, when can Task B finish
Task B can finish only after predecessor Task A has started
In task dependency logic, what is a predecessor
A task that controls the start or finish timing of a subsequent task
In task dependency logic, what is a successor
A task whose start or finish date is dictated by a preceding controlling task
What is the rule regarding establishing task relationships between hierarchy levels in a network diagram
Task relationships must only be linked between work packages, never between summary tasks
What constraint type must task relationaships reflect when constructing initial network diagrams
Relationships must reflect only logical sequence constraints, not resource constraints
Milestone
A significant event or marker in a project schedule that has a duration of zero
What are the four primary sources used to construct cost estimates for work packages
The four sources are labor estimates, equipment estimates, material estimates, and fixed price bids
Duration
The total span of calendar time necessary to complete a task from its initiation to its finish
How does increasing available daily labor impact task duration
Increasing labor hours applied per day reduces the overall calendar duration required to complete the effort
Early start (ES)
The arilest possible state a task can commence based on the completion of its predecessor tasks
Early finish (EF)
The earliest possible date a task can be completed based on its early start and estimated duration
Late start (LS)
The latest date a task can begin without delaying the project completion date
Late finish (LF)
The latest date a task can finish without delaying the project completion date
What is calculated during the forward pass calculation of a network schedule
The forward pass determines the early start (ES) and early finish (EF) dates for all tasks
What is calculated during the backward pass calculation calculation of a network schedule
The backward pass determines the late start (LS) and late finish (LF) dates for all tasks
What formula is used to calculate total float (slack) for a task
Float = LS - ES (or LF - EF)
What does a total float (slack) value of zero indicate for a task
IT indicates that any delay in completing a task will directly delay the final project completion date
Critical Path
The continuous path of activities through a network diagram that possesses zero total float and determines the minimum project duration
How is the overall duration length of a critical path calculated
By summing the durations of all the tasks positioned along the critical path
How does having multiple critical paths affect project management risk
It increases project schedule risk because more paths require zero-delay management to complete on time