31 Terms

1
New cards
What is duration?
Estimated time required to complete an activity — from start to finish.
2
New cards
What is activity duration directly related to?
Assigned resources and estimated work required.
3
New cards
What is the ideal length of an activity duration?
As short as possible, while balancing durations that are too short or too long.
4
New cards
When should long activities be broken into shorter activities?
When logical breaks can be identified.
5
New cards
How long should near-term activity durations be?
No longer than the reporting period.
6
New cards
What is the ideal activity duration for weekly reporting?
One working week or less.
7
New cards
Why should very short activity durations be avoided?
They require more frequent schedule updates.
8
New cards
What is a resource?
Anything required to perform work.
9
New cards
What are the two types of resources?
Labor and nonlabor.
10
New cards
What are examples of nonlabor resources?
Subcontracts, materials, machines, and equipment.
11
New cards
Why are resources assigned to activities?
To ensure activity durations are realistic and rational.
12
New cards
What are two important factors in accurate cost estimates?
Quantity takeoff accuracy and proper unit costs/production rates.
13
New cards
What information is important when using historical data?
Productivity rates.
14
New cards
How are activity durations generally recorded?
Whole days; always round up.
15
New cards
What is the formula for activity duration?
Duration = Total worker-hours / (Number of workers × Hours per day).
16
New cards
Excavation: $950 budget, $33.20/hr, 1 worker. Duration?
950 / (33.20 × 1 × 8) = 3.58 → 4 days.
17
New cards
Excavation: $950 budget, $33.20/hr, 2 workers. Duration?
950 / (33.20 × 2 × 8) = 1.79 → 2 days.
18
New cards
Formwork: 47 m² at 1.8 hr/m², 2 workers. Duration?
(47 × 1.8) / (2 × 8) = 5.29 → 6 days.
19
New cards
Formwork: 47 m² at 1.8 hr/m², 4 workers. Duration?
(47 × 1.8) / (4 × 8) = 2.64 → 3 days.
20
New cards
What information is needed for probability-based duration estimates?
Mean and standard deviation.
21
New cards
What is the formula for the Z-score?
Z = (X − Mean) / Standard Deviation.
22
New cards
What is the formula for duration at a given confidence level?
X = Mean + (Z × Standard Deviation).
23
New cards
What is the Z-score for 95% confidence (not exceeded)?
1.645.
24
New cards
What is the Z-score for 98% confidence (not exceeded)?
2.054.
25
New cards
Mean = 20 days, SD = 5 days. Duration for 95% confidence?
20 + (1.645 × 5) = 28.23 → 29 days.
26
New cards
Mean = 20 days, SD = 5 days. Duration for 98% confidence?
20 + (2.054 × 5) = 30.27 → 31 days.
27
New cards
Mean = 8 days, SD = 2.4 days. Duration for 95% confidence?
8 + (1.645 × 2.4) = 11.95 → 12 days.
28
New cards
Mean = 8 days, SD = 2.4 days. Probability of exceeding 10 days?
Z = (10 − 8) / 2.4 = 0.833. Probability ≈ 20.2%.
29
New cards
How do you calculate the probability a duration will be exceeded?
100% − Probability of not exceeding that duration.
30
New cards
What does "duration will not be exceeded" mean?
Find the probability to the left of the duration on the normal curve.
31
New cards
What does "duration will actually exceed" mean?
Find the probability to the right of the duration on the normal curve.