Bid bond

Protects owner if the low bidder backs out before signing the contract

2
New cards

Performance bond

Guarantees the work gets finished per the specs (surety pays to finish if contractor goes broke)

3
New cards

Payment bond

Guarantees owner's finished project is free of liens (subs and suppliers get paid)

4
New cards

3 factors affecting Bonding capacity

Status of costs, payments, and disputes on incomplete work

5
New cards

Where project duration is specified in a contract

Supplementary (special) conditions

6
New cards

Obligee

Owner — the party protected by the bond

7
New cards

Principal

Contractor — the party whose performance is bonded

8
New cards

Surety

Bonding company — pays if the principal defaults

9
New cards

Bond that pays to finish the job if contractor goes broke

Performance bond

10
New cards

General conditions

Rules for how the contract is administered and the relationships between parties

11
New cards

Special conditions

Items unique to this project

12
New cards

Addenda

Changes/corrections to the bid package issued before bid opening; part of the bidding basis

13
New cards

Technical specifications

Written description of the technical requirements of the work

14
New cards

Why a bid bond is required

Protects the owner from the contractor refusing to sign after winning the award

15
New cards

Notice to bidders

Owner's ad inviting contractors to bid; tells how to submit and where to get plans and specs

16
New cards

Liquidated damages

Owner's estimated daily loss for a late project; contractor pays per day late

17
New cards

Penalty (late completion)

Amount higher than actual loss, not tied to real damages; must be matched by an early-finish bonus

18
New cards

Purpose of retainage

Incentive for the contractor to properly complete the project

19
New cards

When a bid can be withdrawn without penalty

Any time before bid opening

20
New cards

Bid receiving/opening procedure

1 Notice to bidders, 2 Bid opening, 3 Award / notice to proceed, 4 Sign contract

21
New cards

How to claim a time extension

Written request to owner stating the basis (e.g., unusually bad weather)

22
New cards

Documentation for a weather time extension

Daily job logs, photos, video showing conditions that couldn't be anticipated

23
New cards

Lump sum contract

One total fixed price based on complete plans and specs; changes only via change orders

24
New cards

Lump sum — other name

Stipulated sum

25
New cards

Lump sum — owner advantage

Knows total cost before work starts

26
New cards

Lump sum — owner disadvantage

Plans and specs must be 100% complete before picking a contractor

27
New cards

Unit price contract

Contractor quotes a price per unit for each bid item; paid = actual quantities x unit price

28
New cards

Unit price — contractor advantage

Lower risk; paid at quoted price for every unit placed

29
New cards

Unit price — owner disadvantage

Final cost unknown until field quantities are measured

30
New cards

Best contract for bridge piers

Unit price — many unknowns (sub-surface conditions) make quantities vary

31
New cards

Best contract for excavation with limited boring data

Unit price — unknown conditions

32
New cards

Three ways to terminate a contract

Mutual agreement, successful completion, default by either side

33
New cards

Unbalanced bid

Inflating unit prices on early work items to get cash sooner (e.g., $200/cy excavation when real cost is $100/cy)

34
New cards

Contract type implied by unbalancing

Unit price

35
New cards

Why cost + % of cost is rarely used

Contractor is rewarded for running up costs ("gold plating"); no incentive to save

36
New cards

When cost-plus works for both sides

When it creates incentives to cut cost while keeping quality and function

37
New cards

Field staff needed — unit price

Most people; every quantity placed must be precisely measured

38
New cards

Field staff needed — lump sum

Less measuring, but must document contractor actions that could cause cost/time overruns

39
New cards

Field staff needed — cost reimbursable

Least measuring; must verify pay requests match work done and materials installed

40
New cards

Sole proprietorship liability

Owner liable to the extent of personal wealth

41
New cards

Partnership liability

Partners liable to personal wealth (limited partner liable only up to their investment)

42
New cards

Corporation liability

No personal liability; limited to company assets

43
New cards

Hardest legal structure to set up

Corporation — needs stock certificates and registration with the Secretary of State

44
New cards

Corporation advantages vs partnership

Limited liability; easier to raise capital

45
New cards

Corporation disadvantages vs partnership

Complicated/costly to set up (needs lawyers); harder to manage (stockholder approval for borrowing)

46
New cards

Marginal tax rate

Rate at which the last (or next) dollar earned is taxed

47
New cards

MACRS new vs used equipment

Same schedule — used equipment is depreciated the same way

48
New cards

Book value

Initial cost minus accumulated depreciation

49
New cards

Estimated service life (hours)

Total hours / hours per year (10,000 hrs / 2,000 hrs/yr = 5 years)

50
New cards

Who are the three basic parties involved in any construction bonding agreement?

Obligee, principal, surety

51
New cards

Cost + percent of cost

Contractor is paid actual costs plus a fixed % of those costs; higher costs = higher fee, so no incentive to save

52
New cards

Cost + fixed fee

Contractor is paid actual costs plus a set dollar fee that doesn't change with cost; fee is fixed, so contractor wants to finish fast

53
New cards

Cost + fixed fee + profit-sharing clause

Cost + fixed fee, plus contractor gets a share of any savings under the target cost; incentive to cut costs

54
New cards

Cost + sliding fee

Contractor is paid actual costs plus a fee that goes up when costs come in under target and down when costs go over; strongest incentive to control cost