Sam, the project engineer, has been scheduled to run the product system test at the same time he is to build a marketing prototype. This is an example of what type of resource constraint?


People

2
New cards

What is created when project costs are placed in a time schedule depicting when they are to occur?


Project Cost Baseline

3
New cards

What project management tool/method is suggested to determine the customer's opinion of a project being time or resource constrained?


Project Priority Matrix

4
New cards

What do resource allocation methods seek to improve for a time constrained project?


Utilization of resources

5
New cards

what tool allows project management software to handle a multiproject environment by prioritizing resource allocation to specific projects?


project priority number rankings

6
New cards

Which of the following is NOT a potential consequence of failing to identify limited resources before project implementation?


Scope creep

7
New cards

Splitting an activity can result in all of the following EXCEPT


More people working on the same activity.

8
New cards

Gene is trying to order the concrete needed to continue his project. However, the supplier will not be able to deliver it until next week. This is an example of what kind of resource constraint?

Materials

9
New cards

If resources are not adequate to meet peak demands, the resulting reschedule is termed


Resource-constrained scheduling.

10
New cards

All resource leveling techniques involve


Delaying noncritical activities.

11
New cards

Project budgets are developed by time-phasing which of the following?


Work packages

12
New cards

These are all guidelines a project manager should consider when assigning project work EXCEPT


Always assign the best people to the most difficult tasks.

13
New cards

Regina's boss has told her that her project is very important. If the critical path is delayed, she will be given whatever she needs to get it back on schedule. Her project is classified as ________ constrained.


Time

14
New cards

Resource leveling or smoothing can have all the following results on a project EXCEPT


A longer project duration.

15
New cards

When developing a new software package, logically, the software must be designed before the code is written, and the code must be written before it is tested. These activities are dependent on each other by _________ constraints.


Technical

16
New cards

Rachel is working on a project that technically allows three activities to be done at the same time. If they were to be implemented at the same time, she would need 5 contractors in order for the activities to be completed on time. There are only 3 available for her to use. This is an example of what type of constraint?


People

17
New cards

In a resource-constrained project, the second priority in assigning resources is usually given to activities with the


Smallest duration.

18
New cards

A project budget report is showing our project as spending $35,000 against a budgeted amount of $40,000. Which of the following is true?


We can’t be sure how the project is going

19
New cards

All of the following are types of resource constraints EXCEPT


Information.

20
New cards

Why is it necessary to have a time-phased budget baseline?


It shows how much work was accomplished for the money spent

21
New cards

Which of the following is NOT one of the more common problems associated with scheduling multiproject resources?


Decline in project quality

22
New cards

In a resource-constrained project the third priority in assigning resources is usually given to activities with the


Lowest identification number.

23
New cards

All of the following are benefits of scheduling resources before project implementation EXCEPT


It ensures low network sensitivity.

24
New cards

Most of the scheduling methods available today require the project manager to classify the project as either _______ constrained or ______ constrained.


Time, resource

25
New cards

Technical constraints have been carefully considered when developing a project network. Which of the following is true at this point?


Technical dependencies between activities are known

26
New cards

Susan is to conduct environmental testing but the chamber cannot hold all the equipment that she wants to test. This is an example of a constraint that could impact the sequence and timing of activities in a project network. What type of constraint is it?


Physical

27
New cards

When considering the sequence and timing of activities, which of the following is NOT one of the types of project network constraints?


Time

28
New cards

Jan is trying to reallocate resources in a time-constrained project to create smoother resource utilization. She should first identify activities with the


Most slack

29
New cards

Tony has realized that two activities in his project cannot be done at the same time because not enough resources are available. Activity 3 is critical and has a duration of 5 days. Activity 4 has 2 days of slack and a duration of 2 days. How will he decide which activity should be scheduled first?


The activity with the least slack

30
New cards

When a company will reduce the number of projects they have to manage internally to only core projects and send noncritical projects to contractors and consulting firms this is called


Outsourcing

31
New cards

A special truck that George needs on his project has been scheduled on another project. This is an example of what type of resource constraint?


Equipment

32
New cards

In a resource-constrained project, the first priority in assigning resources is usually given to activities with the


Least slack

33
New cards

In a resource-constrained project, which of the following is most likely to be changed?


The completion date

34
New cards

In reviewing the status of her project with top management, Shirley was told that there are only two programmers that she can use for her project. Her project is classified as __________ constrained.


Resource

35
New cards

Resources are adequate, but demand varies widely over the life of the project. Delaying noncritical activities to lower peak demand on resources is known as resource


Smoothing.