A ______________ is any part of an organization that takes inputs and transforms them into outputs that are of greater value to the organization
process
The ____________ of a repetitive process is the average time between completions of successive units.
cycle time
_____________ is the ratio of the time a resource is actually activated relative to the time available for use.
Utilization
A _____________ process has multiple groups of activities that are linked through flows.
multi-stage
The term ____________ is used to indicate that multiple activities have been pulled together for analysis purposes.
stage
A _____________ refers to a storage area between stages where the output of a stage is placed prior to being used in a downstream stage.
buffer
Buffering allows stages to operate _____________.
independently
_____________ occurs when the activities in the stage must stop because there is no place to deposit the item just completed.
Blocking
____________ occurs when the activities in a stage must stop because there is no work.
Starving
The ____________ process is activated only in response to an actual order.
make-to-order
In a ____________ process, inventory (both work in progress and finished goods) is kept to a minimum.
make-to-order
The _____________ process produces standard-level products that can be delivered quickly to the customer.
make-to-stock
_____________ refers to the fixed timing of the movement of items through the process.
Pacing
____________ is the ratio of output to input.
Productivity
What unit is total factor productivity usually measured in?
Monetary dollars.
______________ is measured based on individual input, labor being the most common.
Partial factor productivity
____________ is the ratio of the actual output of a process relative to some standard.
Efficiency
_____________ is the time required to produce a batch of parts.
Run time
___________ is calculated by multiplying the time required to produce each unit by the batch size.
Run time
____________ is the time required to prepare a machine to make a particular item.
Setup time
The ______________ is the sum of the setup time and the runtime for a batch of parts that are run on a machine.
operation time
_____________ includes the time the unit spends actually being worked on, together with the time spent waiting in the queue.
Flow time
The ___________ is the output rate that the process is expected to produce over a period of time,
throughput rate
____________ is the ratio of the value-added time to the flow time.
Process velocity
______________ is the time in which useful work is actually being done on the unit.
Value-added time
Assuming that all of the activities included in the process are value-added activities, value-added time should be the sum of the ______________ times in the process.
activity operation
The _______________ is the sum of the value (at cost) of the raw material, work-in-process, and finished goods inventory.
total average value of inventory
_____________ is the cost of goods sold divided by the average inventory value.
Inventory turn
_____________ is the inverse of inventory turned scaled to days.
Days of supply
_____________ can be analyzed quickly using a principle known as little's law.
Simple systems
inventory=
throughput rate x flow time
_______________ says there is a long-term relationship between the inventory, throughput, and inflow time of production in a steady state.
Little's law
What is the little's law relationship?
inventory=throughput rate x flow time
______________ is defined as the function of specifying the work activities of an individual or group in an organizational setting.
Job design
_______________ is the double-edged sword of job design. On one hand, specialization has made it possible to achieve high-speed, low-cost production
Specialization of labor
T/F: extreme specialization often has serious adverse effects on workers, which in turn are passed on to management.
True
______________ generally entails adjusting a specialized job to make it more interesting for the job holder.
Job enrichment
A job is said to be enlarged _______________ if the worker performs a greater number or variety of tasks.
horizontally
A job is said to be enlarged ______________ if the worker is involved in planning, organizing, and inspecting the worker's own work.
vertically
_____________ is intended to counteract oversimplification and to permit the worker to perform a "whole unit of work".
Vertical enrichment
The organizational benefits of job enrichment occur in both quality and _______________.
productivity
The fundamental purpose of ________________ is to set time standards for a job.
work measurement
Comparing the metrics of one company to another is often referred to as _____________.
benchmarking
____________ productivity answers the question of how much output we can get from a given level of input
Partial factor
For two similar product manufacturers, an inventory turn of _________ times per year is certainly much better than a firm turning over its inventory of two times per year.
six
___________ involves creating new products, exploring materials, validating market fit, monitoring and enforcing contract terms, managing inventories...
planning
____________ involves creating SOPs and training materials, assessing working conditions, monitoring quality issues and the root causes of nonconformity, implementing
production
_____________ involves route design and tracking, document management, augmented driving, yard management, warehouse design (digital twins), materials management
warehousing and logistics
A ________________ can control whether you accept or reject jobs into a flow.
work-in-process (WIP)
In a factory, a _____________ limit means they would continue receiving new jobs even when the shop floor was crowded, potentially allowing longer queues and higher inventories to form.
high WIP
In a factory, a _____________ limit means they would turn away more new jobs but keep the shop floor less crowded, potentially letting some workstations sit idle waiting for new jobs to come along.
low WIP
T/F: It is always good to maximize the utilization of a process
False
As long as μ ≥ λ, with no waiting and no variability, adding capacity at the bottleneck increases system capacity and cycle time but has ____________________.
no impact on flow time
________________ means you process job arrivals in fixed sets. Instead of arrivals (items) flowing through one at a time, you bundle them into batches. The batch becomes the job that the system must process, and it remains together from start to finish, still processed one item at a time.
Batching
When there is a setup time for processing (e.g., you must configure the processor before each batch and/or clean it after each batch before doing the next one), larger batch sizes ________________ of items processed per hour.
increase the throughput
_____________ batches are beneficial if there is high setup times and high utilization.
larger
With ______________ batch sizes, you produce finished work more quickly, which is helpful if flow time is essential or if you have downstream processes that can immediately begin work on the finished jobs.
smaller
Do you produce work faster with smaller or larger batch sizes?
smaller
____________ batches are beneficial if you have downstream processing steps with capacity and flow time is important.
smaller
____________ is the required rate at which you must complete jobs to meet customer demand
Takt time
Takt Time=
Available Production Time/Customer Demand
Your auto manufacturing plant runs two 8-hour shifts per day, for a total of 960 working minutes for the production line. Forecasts indicate that customers will demand 1000 finished cars per day from your plant. What is your takt time?
0.96 minutes or 57.6 seconds per care