Communications matrix
Answers who needs what information, when, in what format, from whom, and by which method
Interactive communication
Two-way, real time (meetings, calls); best for complex issues and decisions
Push communication
Sent to specific recipients (email, memos, reports); best for status updates
Pull communication
Recipients retrieve it when needed (portals, wikis, shared drives); best for large audiences
Communication channels formula
n(n − 1) ÷ 2; 10 people = 45, 20 people = 190
Status report
Where the project stands right now
Progress report
What was completed this period
Forecast report
Where the project is heading (EAC, ETC)
Variance report
Deviation from baseline plus root cause
Dashboard
Displays KPIs with red/yellow/green status
Information radiator
Large visible display (Kanban board, burndown chart); common in Agile
Make (vs. buy)
Choose when work is core, sensitive/proprietary, or you have idle capacity
Buy (vs. make)
Choose when you need special expertise, lack capacity, need speed, or the work is one-time
Procurement process
Plan (needs, SOW, selection criteria) → Conduct (solicit, evaluate, award) → Control (performance, changes, payments) → Close (acceptance, final payment, lessons learned)
Statement of Work (SOW)
Defines scope, location, period of performance, and acceptance criteria; vagueness here is the root cause of most disputes
Source selection criteria
Price, technical capability, past performance, management approach; set before bidding
RFI
Learn about the market; no commitment
RFP
For complex needs; asks vendors for both a technical and a cost proposal
RFQ
For a well-defined item; price is the main factor
IFB
Government sealed bidding; lowest responsive, responsible bidder wins
Fixed-price contract
Seller bears cost risk; best for well-defined scope; highest buyer cost certainty. Variants: FFP, FPIF (target + ceiling), FP-EPA (inflation adjustment)
Cost-reimbursable contract
Buyer bears cost risk; best for uncertain scope; lowest buyer cost certainty. Variants: CPFF (fixed fee), CPIF (fee tied to cost vs. target), CPAF (subjective award fee)
Time & materials contract
Hourly rate plus materials; cost risk mostly on buyer; limited certainty; best for low-to-medium scope clarity; capped by a not-to-exceed (NTE) limit
Buyer vs. seller roles
Buyer: defines need, solicits/selects, monitors, closes/archives. Seller: responds to solicitation, executes, reports, supports closure. All changes go through formal change control; no verbal agreements
Why communication matters
Leading cause of project failure; PMs spend up to 90% of their time on it; sending a message isn't the same as getting it understood