1. Introduction to Government Procurement System and RA 12009

0.0(0)
Studied by 0 people
call kaiCall Kai
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
GameKnowt Play
Card Sorting

1/34

encourage image

There's no tags or description

Looks like no tags are added yet.

35 Terms

1
New cards

Government procurement

Process by which public entities acquire goods, infrastructure projects, and consulting services needed to deliver public services.

2
New cards

Goods (in procurement)

Materials, equipment, supplies, and other items acquired by public entities.

3
New cards

Infrastructure projects (in procurement)

Roads, bridges, drainage, buildings, water systems, seawalls, slope protection, ports, airports, railways, and similar works.

4
New cards

Consulting services (in procurement)

Planning, design, engineering, supervision, and other professional services.

5
New cards

Why government procurement matters

Ensures responsible use of public funds, addresses community needs, promotes fair competition for value for money, and supports timely, quality delivery while avoiding delays, cost overruns, disputes, and defects.

6
New cards

Republic Act No. 12009, the New Government Procurement Act (NGPA),

revises the legal framework previously established under RA 9184.

7
New cards

20 July 2024

RA 12009 signed into law date

8
New cards

13 August 2024

RA 12009 effectivity date

9
New cards

25 February 2025

RA 12009 IRR effectivity date

10
New cards

RA 9184 Government Procurement Reform Act

enacted in 2003, which served as the principal procurement law for more than two decades before RA 12009.

11
New cards

Transparency (governing principle)

Information and decisions should be open to scrutiny.

12
New cards

Competitiveness (governing principle)

Qualified participants should have fair opportunities.

13
New cards

Efficiency (governing principle)

Procurement should achieve results without unnecessary delay or waste.

14
New cards

Proportionality (governing principle)

Requirements should fit the project's nature, size, and complexity.

15
New cards

Accountability & public monitoring (governing principle)

Decision-makers and project participants must be answerable.

16
New cards

Sustainability & value for money (governing principle)

Consider long-term outcomes, not price alone.

17
New cards

Civil engineering-relevant public projects

Roads, highways, bridges, drainage, flood control, river protection, public buildings, schools, hospitals, water supply, wastewater facilities, ports, airports, railways, seawalls, slope protection, and resilient infrastructure.

18
New cards

Procurement-to-project delivery cycle (6 stages)

  1. Identify need -> 2. Plan & design -> 3. Budget & prepare -> 4. Procure & evaluate -> 5. Award & implement -> 6. Inspect & close


19
New cards

Stage 1: Identify need

Determine what public problem must be addressed.

20
New cards

Stage 2: Plan & design

Conduct investigations and define scope, plans, specifications, and cost.

21
New cards

Stage 3: Budget & prepare

Arrange funding, procurement plan, and bidding documents.

22
New cards

Stage 4: Procure & evaluate

Invite offers, then receive and evaluate bids.

23
New cards

Stage 5: Award & implement

Execute contract, carry out construction, and monitor progress.

24
New cards

Stage 6: Inspect & close

Verify quality, quantities, completion, and acceptance.

25
New cards

Municipal concrete road example

An LGU plans a 2-km concrete road linking two barangays: identify need and scope, run surveys/investigations, prepare plans/specs/quantities/cost estimate, prepare procurement docs and select contractor, then monitor construction, test quality, and verify completion.

26
New cards

Civil engineer role: Planning

Define the need, scope, feasibility, and project risks.

27
New cards

Civil engineer role: Design & estimating

Prepare engineering plans, specifications, Bill of Quantities (BOQ), and cost estimates.

28
New cards

Civil engineer role: Technical support

Help review technical requirements and submissions within assigned roles.

29
New cards

Civil engineer role: Implementation

Monitor schedule, quantities, workmanship, and materials.

30
New cards

Civil engineer role: Quality & acceptance

Verify tests, inspect completed work, and document deficiencies.

31
New cards

Impact of incomplete site data

Can lead to design changes.

32
New cards

Impact of incorrect quantities

Can distort the project cost estimate.

33
New cards

Impact of unclear specifications

Can create inconsistent bids and disputes.

34
New cards

Impact of unrealistic schedules

Can affect competition and implementation.

35
New cards

Impact of poor quality control

Can compromise durability and public safety.