1/6
CE 5575 - Lecture 14
define free float
max amount of days an activity can be delayed without delaying successor
define total float
max amount of days an activity can be delayed without delaying the whole project
define network sensitivity
likelihood original critical paths will change
define insensitive network
only 1 critical path with lots of slack
define resource loading
assign labor/equipment to activities to see when demand > availability
define resource leveling
adjusting activity timing to resolve overallocations
define resource smoothing
adjust activities with float to lower demand spikes