Change Management Procedures

0.0(0)
Studied by 0 people
call kaiCall Kai
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
GameKnowt Play
Card Sorting

1/18

flashcard set

Earn XP

Description and Tags

Last updated 11:14 PM on 10/7/26
Name
Mastery
Learn
Test
Matching
Spaced
Call with Kai
Chat

No analytics yet

Send a link to your students to track their progress

19 Terms

1
New cards

What is a documented procedure that reverses a change and restores the system to its previous known-good configuration if the change fails

Rollback plan

2
New cards

What is a documented process for creating and storing copies of data so that the data can be restored if it becomes lost, corrupted, or damaged

Backup plan

3
New cards

What is the practice of implementing and verifying a change in an isolated, non-production environment specifically designed to prevent any impact on live systems

Sandbox testing

4
New cards

What is the reason for documenting staff members responsible for each stage of a business process

To ensure accountability

5
New cards

What documnet must be submitted first to initiate a formal change to management process and update firmware on all backbone switches in a data center

Change request form

6
New cards

What part of the change management process is justifying the replacement by noting why the change will help

Purpouse of the change

7
New cards

What part of the change management process details how a change will impact a business or company

Scope of the change

8
New cards

How should a monthly update of antivirus be classified if it is low-risk and has a pre-approved procedure

Standard change

9
New cards

What type of change is an organization planning on moving its entire on-premises email system to a cloud based one that requires a formal approval and risk assesment

Normal change

10
New cards

What classification of change is a critical security vulnerability being discovered and an immediate patch must be applied outside the regular maintenance window

Emergency change

11
New cards

What change management concept is a non-urgent change being denied due to more important reasons

Change freeze

12
New cards

What is an authorized timeframe that a policy enforces where all non-emergency software patches must be deployed in

Maintenance window

13
New cards

What part of a change request should include a list of all VLANs and servers that will lose connectivity during the reboot

Affected systems/impact

14
New cards

What is a section of a change request that lists the assesed likelehood of potential negative outcomes

Risk level

15
New cards

What element of the change management process ensures that a change is formally authorized

Change board approvals

16
New cards

What is a representation of the implementation phase of the change management process

Applying a configuration update to a server according to a documented procedure

17
New cards

When does formal peer review of a proposed change typically occur in the change management lifecycle

Before the implementation phase

18
New cards

When does end-user acceptance typically take place in a standard change management workflow

In a test environment before full production deployment

19
New cards

What are the steps in the change management process

  1. Complete request forms

  2. Determine the purpouse

  3. Identify the scope

  4. Schedule a date and time

  5. Determine impact

  6. Analyze risk

  7. Get change board approval

  8. Obtain end-user acceptance