Vocabulary flashcards covering construction fieldworks, observation reports, contract and control documents, heavy equipment operations and maintenance, and construction planning, scheduling, WBS, PERT, and CPM network diagramming techniques.

66 Terms

1
New cards

Construction Fieldworks

Any work operations conducted on the job site in construction apart from paperwork, such as surveying, earthworks, concrete works, and masonry.

2
New cards

Light Construction

A category of construction that mostly refers to residential buildings, small commercial buildings, remodeling, renovations, and landscaping that do not require heavy machinery or extensive engineering.

3
New cards

Heavy Construction

Large-scale, complex construction projects that require substantial resources, heavy machinery, and a large workforce, such as highways, bridges, tunnels, dams, and airports.

4
New cards

Construction Observation

The process of monitoring and inspecting a construction project to verify that work complies with design plans, technical specifications, and building codes.

5
New cards

Punch List

A construction form that lists incomplete, defective, or non-critical tasks (such as paint touch-ups, clearing debris, or replacing fixtures) that must be finished before the construction phase is considered complete.

6
New cards

Construction Plan

A comprehensive document detailing all planning components of a project, including scope of work, budget, schedule, and work breakdown structure.

7
New cards

Construction Budget

A document that outlines all projected costs of a project to help project managers control spending, prevent overruns, and ensure profitability.

8
New cards

Construction Schedule

A document that coordinates execution-phase activities and establishes deliverable due dates so that contractors and subcontractors complete the project on time.

9
New cards

Construction Estimate

A preliminary forecast of direct, indirect, and overhead expenses (such as labor, materials, and equipment rental) that serves as the basis for the construction budget.

10
New cards

Scope of Work (SOW)

A document describing the work to be performed in a project, detailing the estimated timeline, deliverables, costs, milestones, and payment terms.

11
New cards

Construction Proposal (Bid)

A contractor's official application document submitted to a project owner—typically in response to an RFP—outlining project execution, timeline, scope, costs, and specifications.

12
New cards

Request for Proposal (RFP)

A document issued by project owners to solicit bids and detailed proposals from interested contractors, establishing the required scope, timeline, and cost criteria.

13
New cards

Request for Information (RFI)

A formal inquiry submitted to the owner, architect, engineer, or project manager to clarify ambiguities, omissions, or errors in contract drawings or specifications.

14
New cards

Construction Lien Waiver

A legal form in which a contractor or subcontractor gives up their right to place a mechanic's lien against a property, confirming receipt of payment for services rendered.

15
New cards

Request for Quotation (RFQ)

A document sent to material suppliers or subcontractors to obtain pricing estimates for goods and services before issuing a formal purchase order.

16
New cards

Construction Submittals

Shop drawings, material samples, product data, and certifications created by subcontractors for review and approval by the general contractor, architect, or engineer prior to installation.

17
New cards

Construction Change Order

A formal document used to modify the initial contract scope, timeline, or price due to additions, deletions, or unforeseen field conditions.

18
New cards

Bill of Quantities (BOQ)

A pre-construction document that itemizes the quantities and specifications of materials, parts, and labor required for a build, aiding contractors in pricing their bids.

19
New cards

Schematic Design

An early architectural drawing that illustrates building layout, general dimensions, site integration with surroundings, and spatial relationships relative to building codes.

20
New cards

Construction Specifications

Written guidelines accompanying drawings that define the scope, quality of workmanship, performance standards, and material properties required for project activities.

21
New cards

Construction Daily Report

A daily site record detailing performed work, on-site personnel and trade crews, equipment status, material deliveries, weather conditions, and incidents.

22
New cards

Material Takeoff (MTO)

A form listing the itemized materials and quantified requirements extracted directly from drawings and engineering documents to determine procurement costs.

23
New cards

Schedule of Values (SOV)

A project management billing schedule where contractors allocate the contract sum across work items, reporting work completed and materials stored for progress payments.

24
New cards

Construction Timesheet

A tracking log of daily work hours, regular hours, and overtime spent by labor on-site used to compute payroll and monitor field productivity.

25
New cards

Contractor Payment Schedule

A ledger tracking payment milestones, amounts due, retainage withheld, and disbursement dates across multiple subcontractors on a project.

26
New cards
<p>Motor Grader</p>

Motor Grader

An earthmoving machine equipped with a long, adjustable blade used to create a flat, smooth base surface during grading and site preparation.

27
New cards
<p>Asphalt Paver</p>

Asphalt Paver

A piece of road construction machinery used to lay asphalt flat on roads, bridges, and parking lots while providing preliminary compaction before rolling.

28
New cards
<p>Concrete Pump</p>

Concrete Pump

A machine equipped with a hydraulic articulating boom used for transferring liquid concrete precisely to elevated or distant locations on a construction site.

29
New cards
<p>Tunnel Boring Machine (TBM)</p>

Tunnel Boring Machine (TBM)

A specialized heavy excavation machine used to excavate circular cross-section tunnels through soil and hard rock strata.

30
New cards
<p>Rotary Drilling Rig</p>

Rotary Drilling Rig

Specialized heavy equipment used to bore deep vertical holes into rock or soil for cast-in-place foundation piles, caissons, or deep foundation shafts.

31
New cards
<p>Curb Machine</p>

Curb Machine

A specialized slipform paving machine used to extrude continuous concrete curbs, gutters, and highway barriers accurately along grade stakes.

32
New cards

Preventive Maintenance (PM)

Scheduled, routine servicing and inspection—including lubrication, fluid changes, and replacing worn components—performed to prevent unexpected equipment failure.

33
New cards

Predictive Maintenance

Condition-based maintenance that evaluates equipment health in real time using sensor data, such as vibration analysis, infrared thermography, and oil condition monitoring.

34
New cards

Corrective Maintenance

Maintenance tasks involving repair or replacement of broken parts carried out only after equipment has failed or malfunctioned.

35
New cards

Emergency Maintenance

Unscheduled, urgent repairs performed immediately on equipment to address sudden breakdowns that halt critical job site operations.

36
New cards

Rollover Protective Structures (ROPS)

Operator cabin framework, roll bars, and structures designed to protect equipment operators from injury in the event of machine overturns or rollovers.

37
New cards

Computerized Maintenance Management System (CMMS)

A software platform that centralizes maintenance data, automates work orders, tracks spare parts inventories, and monitors equipment upkeep schedules.

38
New cards

Construction Planning

The foundational project management process of deciding what to do, how to do it, when to do it, and who will do it by organizing resources including labor, materials, equipment, money, and time.

39
New cards

Project Scheduling

The process of sequencing, timing, and assigning start and finish dates to project tasks to execute a construction plan efficiently within set budget and quality parameters.

40
New cards

Strategic Plan

A high-level construction planning document focusing on broad, long-term project-wide goals and objectives.

41
New cards

Operational Plan

A tactical construction plan focusing on day-to-day work methods, task execution, and short-term schedules.

42
New cards

Work Breakdown Structure (WBS)

A hierarchical project management tool that decomposes total project scope into smaller, deliverable-oriented tasks, subtasks, and work packages.

43
New cards

Work Package

The lowest or most granular level in a Work Breakdown Structure (Level 3 or 4) containing manageable, assignable tasks that can be accurately estimated for time and cost.

44
New cards

Deliverable-Based WBS

A Work Breakdown Structure organized around tangible end products or project outputs (e.g., Foundation, Walls, Roof, Finishes) rather than execution phases.

45
New cards

Phase-Based WBS

A Work Breakdown Structure organized according to chronological project life cycle steps (e.g., Pre-Construction, Site Works, Superstructure, Handover).

46
New cards

Gantt Chart

A project scheduling bar chart that displays activities along a vertical axis and time intervals on a horizontal axis, showing task durations and calendar progress.

47
New cards

Milestone

A significant point or event in a project schedule that marks key achievements or stage completions without having a duration or consuming resources directly.

48
New cards
<p>Finish-to-Start (FS)</p>

Finish-to-Start (FS)

The most common PDM dependency where a successor activity cannot start until its predecessor activity has finished.

49
New cards
<p>Start-to-Start (SS)</p>

Start-to-Start (SS)

A PDM logical dependency where a successor activity cannot start until its predecessor activity has started.

50
New cards
<p>Finish-to-Finish (FF)</p>

Finish-to-Finish (FF)

A PDM logical dependency where a successor activity cannot finish until its predecessor activity has finished.

51
New cards
<p>Start-to-Finish (SF)</p>

Start-to-Finish (SF)

A rare PDM logical relationship where a successor activity cannot finish until its predecessor activity has started.

52
New cards

Arrow Diagramming Method (ADM)

An activity-on-arrow (AOA) scheduling technique where arrows represent activities, nodes represent milestone events, and dashed arrows represent dummy activities.

53
New cards

Precedence Diagramming Method (PDM)

An activity-on-node (AON) network scheduling technique where boxes (nodes) represent activities and connecting arrows depict logical dependencies without needing dummies.

54
New cards

Dummy Activity

A zero-duration, zero-resource dashed arrow used in AOA diagrams to maintain unique activity identification between common nodes or preserve logic.

55
New cards

Merge Event

An event node in a network diagram where two or more distinct incoming activities terminate simultaneously.

56
New cards

Burst Event

An event node in a network diagram from which two or more outgoing activities originate simultaneously.

57
New cards

Fulkerson's Rule

A systematic method for numbering nodes in an AOA network diagram from left to right such that every activity arrow goes from an event with a smaller number ii to a head event with a larger number jj (i<ji < j).

58
New cards

Critical Path

The longest continuous sequence of dependent activities through a project network diagram, determining the shortest allowable completion time for the project.

59
New cards

Float (Slack Time)

The amount of time an activity can be delayed without extending the overall project completion date, calculated as S=LS−ESS = LS - ES or S=LF−EFS = LF - EF.

60
New cards

Forward Pass

A calculation process moving from project start to finish that determines the earliest start (ESES) and earliest finish (EFEF) times for each activity.

61
New cards

Backward Pass

A calculation process moving from project completion back to project start that calculates the latest finish (LFLF) and latest start (LSLS) times for each activity.

62
New cards

Program Evaluation and Review Technique (PERT)

A probabilistic project management tool developed in the 1950s by the U.S. Navy for the Polaris missile project to schedule complex projects with uncertain activity durations.

63
New cards

Optimistic Time (OO)

In PERT analysis, the minimum possible time required to complete an activity assuming everything proceeds better than expected.

64
New cards

Most Likely Time (MM)

In PERT analysis, the best estimate of the time required to complete an activity under normal working conditions.

65
New cards

Pessimistic Time (PP)

In PERT analysis, the maximum possible duration required to complete an activity assuming significant setbacks and unfavorable conditions occur.

66
New cards

Expected Time (TETE)

The weighted average activity duration computed in PERT using the formula TE=O+4M+P6TE = \frac{O + 4M + P}{6}.