47 Terms

1
New cards

How does the predictive approach define requirements?

Requirements and scope are defined up front before significant development begins.

2
New cards

What is a key characteristic of the predictive approach?

Detailed planning occurs before execution.

3
New cards

What does the business analyst (BA) do in a predictive environment?

The BA performs substantial analysis before implementation, including eliciting, analyzing, and documenting requirements.

4
New cards

What is the purpose of formal change control in a predictive approach?

To evaluate the impact of significant changes on scope, schedule, cost, and other project constraints.

5
New cards

What is the main focus of the adaptive approach (Agile)?

Requirements are defined, refined, prioritized, reassessed, developed iteratively, and delivered incrementally.

6
New cards

What does 'iterative' mean in the context of Agile methodologies?

The team repeatedly revisits and improves the product based on feedback and learning.

7
New cards

What is Scrum?

An agile framework used to develop and deliver products incrementally and iteratively.

8
New cards

What is the Product Backlog in Scrum?

An ordered list of work/items that may be needed for the product.

9
New cards

What is a Sprint in Scrum?

A fixed-length period during which the team creates a usable increment.

10
New cards

Who is accountable for maximizing product value in Scrum?

The Product Owner.

11
New cards

What is the main goal of Lean methodology?

To maximize value while minimizing waste.

12
New cards

What types of activities are considered waste in Lean?

Unnecessary work, waiting, rework, excessive handoffs, unnecessary inventory, defects, and overproduction.

13
New cards

What is Kanban?

An approach for managing and improving the flow of work by visualizing tasks.

14
New cards

What does a Kanban board visualize?

What work needs to be done, what is currently in progress, and what has been completed.

15
New cards

What are key concepts of Kanban?

Visualizing workflow, managing the flow of work, identifying bottlenecks, and limiting Work in Progress (WIP).

16
New cards

What is a Product Backlog Item (PBI)?

An individual item of work in the Product Backlog.

17
New cards

What are the two major project management approaches?

Predictive (Waterfall) and Adaptive (Agile)

18
New cards

What does the term 'Product Increment' refer to in Scrum?

A usable, valuable version of the product produced during the work.

19
New cards

What is the role of the Scrum Master?

To help establish Scrum and support the team's effectiveness.

20
New cards

What is a key takeaway about Scrum methodology?

Scrum uses iterative and incremental development, frequent inspection, feedback, and adaptation.

21
New cards

What is the significance of acceptance criteria in business analysis?

Acceptance criteria define the conditions under which a solution is accepted as meeting requirements.

22
New cards

What is the importance of stakeholder identification in business analysis?

To understand and address the needs and expectations of those affected by the project.

23
New cards

How does the adaptive approach differ from the predictive approach in terms of requirements?

In the adaptive approach, requirements are not fully defined at the beginning and evolve over time.

24
New cards

What is the purpose of developing requirements traceability?

To ensure that all requirements are accounted for and linked to their source throughout the project lifecycle.

25
New cards

What is the primary role of a Business Analyst (BA) in an adaptive environment?

To work closely with stakeholders, product team, and delivery team to continuously understand and refine what provides value.

26
New cards

What activities does a BA perform to identify and analyze project/product work?

Elicit stakeholder needs, identify and analyze requirements, break larger requirements into smaller pieces, clarify acceptance criteria, and refine requirements as more information becomes available.

27
New cards

How does a BA prioritize value in an adaptive environment?

By considering business value, customer value, risk, urgency, dependencies, cost/effort, and strategic objectives.

28
New cards

What does a BA help the team understand in terms of delivery?

What needs to be delivered, why it is needed, how requirements relate to stakeholder needs, what acceptance criteria must be met, and what dependencies exist.

29
New cards

What types of risks and issues can a BA help identify?

Requirement-related risks, ambiguous requirements, conflicting stakeholder needs, dependencies, assumptions, constraints, and potential issues affecting value delivery.

30
New cards

In a predictive environment, what is the BA's approach to requirements?

Performing more up-front requirements analysis and documentation.

31
New cards

What responsibilities does a BA have in a predictive environment?

Identify stakeholders, elicit and analyze requirements, document requirements, define and validate scope, develop requirements models, establish acceptance criteria, and support requirements traceability.

32
New cards

What is a key concept the BA ensures the project team understands?

What needs to be delivered, why it is needed, and how to determine whether the delivered solution meets the requirements.

33
New cards

What is the difference between predictive and adaptive environments regarding requirements?

Predictive environments have requirements defined largely up front, while adaptive environments have requirements that evolve and are progressively elaborated.

34
New cards

How does planning differ between predictive and adaptive environments?

Predictive environments involve detailed planning up front, while adaptive environments have planning that occurs progressively.

35
New cards

What is the focus of a BA in a predictive environment?

To elicit, analyze, document, and validate requirements largely up front.

36
New cards

What does iterative mean in the context of business analysis?

Iterative refers to repeatedly improving or refining the solution.

37
New cards

What does incremental mean in business analysis?

Incremental refers to delivering the solution in separate pieces.

38
New cards

What is the relationship between iterative and incremental approaches in agile teams?

An agile team may build incrementally and improve iteratively.

39
New cards

What is a major concept in business analysis regarding stakeholder needs?

Business analysis is not simply about writing down requirements; it involves moving from stakeholder need to requirement to solution to validation to value.

40
New cards

What should a BA investigate when a stakeholder expresses a need?

The problem stakeholders are experiencing, who needs the information, what information is needed, when it is needed, what 'better access' means, constraints, solution options, and how success will be measured.

41
New cards

What are the key ideas associated with the predictive/waterfall approach?

Requirements largely defined up front, detailed planning, more formal documentation, scope established early, and changes generally go through formal change control.

42
New cards

What are the key ideas associated with the agile/adaptive approach?

Requirements evolve, progressive elaboration, iterative and incremental delivery, frequent stakeholder feedback, continuous prioritization, and adaptation to change.

43
New cards

What does Scrum emphasize in its framework?

Iterations/Sprints, Product Backlog, Increment, Feedback, and Adaptation.

44
New cards

What does Lean focus on in business analysis?

Maximizing value and minimizing/eliminating waste.

45
New cards

What is the focus of Kanban in project management?

Visualizing work, managing flow, limiting work in progress (WIP), and continuous improvement.

46
New cards

What is the most important distinction for the CAPM exam regarding requirements?

If requirements are expected to change as the team learns, an adaptive approach is appropriate; if requirements can be defined and planned in detail before execution, a predictive approach is more suitable.

47
New cards