Chapter 17 Notes
Why are leaders at all levels forced to determine the best way to use available resources?
increased demand for effectiveness and efficiency in healthcare delivery
project management
a temporary endeavor undertaken to create a unique product, service, or result/a systematic approach to planning and guiding project processes from start to finish
a proven way to improve outcomes that can directly and positively impact costs through the efficient and effective use of limited resources for HIT
indispensable in health IT, as it is a structured approach to help ensure effective implementations of healthcare initiatives
can improve the quality of health IT project outcomes, provide accountability of expenses, and reduce inefficiencies through structured change control processes
best practices can help create transparency and visibility within the organization and helps eliminate many of these issues
helps ensure delivery of initiatives and projects on time and within budget and provide well-defined value requirements that positively affect the organization’s financial performance, productivity, and delivery of patient services
enhances patient satisfaction either directly or indirectly
fundamental project management practices
allow organizations to reach strategic goals within a planned timeline within cost parameters
What does a strong project management discipline include?
high degrees of communication, organization, interpersonal leadership, cross-functional team coordination and negotiations, problem solving, attentiveness to detail, technical and business domain knowledge, and the ability to methodically guide the project processes through organizational governance parameters
What does a strong project management process include?
initiation or preplanning
formal planning with the creation of a project plan
implementation and execution of that project plan with measurement of progress and performance
project closure through delivery of value through project objectives
What does the temporary nature of projects indicate?
a definite beginning and end
When is the end of a project reached?
when the project’s objectives have been achieved
when the project is terminated because its objectives will not or cannot be met
when the need for the project no longer exists
program management
involves larger implementations, like a large-scale hospital document management application or an organization-wide EHR system
there are multiple, aligned projects affecting many teams or departments that are coordinated and managed in concert
ensures goals, project steps, and resource needs are in sync
portfolio management
even more complex
involves the creation of common programs and projects that are not necessarily related but are important to combine and view as a whole
essential for a healthcare organization to adequately prioritize and approve new project requests and to work strategically on projects throughout the years
provides an essential foundation for decisions and discussions in governance committees as projects are prioritized and funded
centralizes the management of processes, methodologies, and technologies used by PMs, pro- gram managers, and project management offices (PMOs); allows collective management of the entire suite of current and proposed projects
allows for better prioritization and optimization of projects as well as creating the opportunity for efficiencies
Project Management Institute (PMI)
association created to improve organizational success and mature the profession of project management
has conducted a number of studies related to the impact of project management; studies reveal that nearly 80% of all projects fail to meet their objectives if they do not have some type of structured project methodology
What impact does applying appropriate processes, methodologies, and tools within a hospital setting have?
multidimensional benefits by reducing variability across processes, providing standardization across projects, and increasing the overall project success rate
Why do many healthcare projects across departments overlap or even clash?
departments are frequently regarded as separate entities or “silos” where clinical projects and initiatives are often carried out independently at the discretion of a leader and at times without aligning project goals with the larger organizational objectives
standardized and consistent project management
needed throughout the organization at all levels to optimize process and project outcomes across all entities
effective organizations have formal strategic plans showing what they can and will do, so there is a clear understanding of what is expected across organizational departments and levels
List the 3 levels of focus in formal project management
project management
program management
portfolio management
project
refers to an undertaking that is time bound and delivers a particular product or service/a temporary undertaking ending after a set of goals are achieved, involving the application of knowledge, ideas, and skills to execute a plan of action
consists of goals, activities, a timeline, projected risks, and mitigation plans
has an appointed manager who leads the effort
List the project phases
initiation
planning
execution
closure
monitoring & control
formally takes place during the planning and executing phases when most activities are moving at a fast pace
not necessary during initiating and closing because the work has not been defined (initiating) or it is completed (closing)
initiating activities
generally the most important activities and yet often the most rushed or undervalued
requires a PM to gather initial information and resource estimates so that project viability can be assessed
initial project scope and timeline are established so leaders can balance the impact on resources and existing workloads
projects have organization visibility so larger risks and impacts on architecture and existing initiatives can be mitigated across efforts
planning activities
begins once projects are approved, funded, and resourced
lay the foundation for the project life cycle and are used to track future project performance
formally defines projects by project teams and subject matter experts who decompose project deliverables into workable tasks as part of the overall project plan
helps team members achieve defined goals and objectives and serves as a basis for good communication and evaluation for managing project staff and external vendors about timelines and budget
skipping this step or even inadequately completing this step typically hinders progress throughout the life of a project and affects the long-term results stakeholders seek
executing activities
begins once a formal project plan has been completed, resourced, and scheduled
often take the most time and resources to complete
ultimately defines the success of a project; this is where the build of project deliverables and customer testing and approval occurs
use of solid management processes, including effective monitoring and control of all elements of a project—time, cost, quality, change, management of risk, issues, procurement, customer acceptance, and communications—can help ensure success
closing activities
include release management, project delivery, documentation of lessons learned, and formal handoffs to operational and maintenance teams
critical to define and complete in a healthcare setting because some of the same people (resources) who worked on a project are often the ones who maintain that project’s outcomes
project plan
assists project leaders with time management, cost estimation, quality, change, risk, and issues throughout the life of a project
risk management
includes both project threats and opportunities (plausible scenarios that may or may not impact the scope, timeline, or resources of a project, given a set of circumstances)
must be managed to avoid delays or project failure
focus is on planned risk management, identification of risks, performance of qualitative and quantitative risk analysis, and monitoring and control of risk
should include requisite changes to project scope
any issues should be well controlled to keep the project on schedule and avoid project derailment
Why is a clear delineation of the end of every project needed?
helps in understanding when maintenance and operational phases begin
postimplementation review
conducted to gather and share lessons learned and define next steps
typical deliverables in this phase include documentation for support and specific communications to inform stakeholders the project has ended
Why is monitoring project progress and controlling changes to scope critical?
it ensures accurate patient data is captured on the new electronic forms and issues and risks are resolved to keep the project within budget and timeline constraints
List key PMI knowledge components
project integration
scope management
time and cost management
quality management
human resource management
communication management
risk management
procurement management
project integration
includes the development of a project charter
focuses on how project issues will be managed, tracks changes to the original plan, and coordinates replanning, if necessary
project charter/management plan
outlines the direction and management of overall project execution, monitoring and control processes for scope, schedule and resource management, performance of change control procedures, and project closure and release management steps
scope management
focuses on work of the project and clarifies boundaries and areas to include or exclude
involves collecting project requirements (desired functions) and defines the scope in more detail
includes creating a work breakdown structure, scope verification, and validation process with stakeholders and key project sponsors and outlines scope change control
without a well-defined scope document, there is no way to know if a project is in or out of scope at any particular phase
time management
includes estimations of task effort (by complexity), determines the project schedule, and records actual completion dates
includes monitoring and control of schedule and resources, ensuring project teams are empowered to be productive, and reporting accurate time spent on activities (effort) throughout the project
closely aligned with cost management, especially for estimating resources required for tasks and task durations, as these directly align with project costs
cost management
involves the cost of resources such as materials, equipment, facilities, labor, and other related services
determining cost estimates, budget, and financial controls all fall into this category
quality management
includes creating deliverables that meet an acceptable quality level and the quality of the project management process itself, focusing on quality assurance and quality control
quality assurance
consists of auditing and comparing initial quality requirements against quality control measurements
quality control
involves monitoring results of quality activities, which include project deliverables and project management results
human resource management
the management of people and includes aspects like team acquisition, team development, and processes for project resource issue resolution
PMs and RMs closely work together to ensure they are in sync throughout a project
communication management
includes meeting management, risk actions and assessments, project plans, project reviews, stakeholder identification, and project information distribution
stakeholder communication should be frequent and include project status, issues, risks, and successes to adequately manage expectations
risk identification
most effective if done during the planning phase and should include outcomes and possible solutions to threats if the given scenario materializes
procurement management
includes acquiring products or services from outside the project team
includes working with vendors, contractors, and service groups.
List benefits of improved project performance
increased efficiency in service delivery
enhanced customer satisfaction when following formal project management process areas and using key knowledge components
allow organizations to reach strategic goals within a planned timeline within cost parameters
program
refers to a group of related projects managed together
What is the logic behind program management?
it is less complicated, less costly, and more operation- ally efficient to control similar projects together than separately
resource sharing can then occur, as projects might be able to be managed by the same person or with shared resources, leading to significant efficiencies, financial savings, and coordination across projects
What is the purpose of portfolio management?
to determine an optimal resource mix for project implementation and scheduling that is most effective in achieving an organization’s operational and financial goals
portfolio
includes projects that are combined together as a logical group, but are not necessarily linked directly together as in program management
might include aligning projects, programs, and operations with strategic objectives and investing resources in the right work to deliver the expected value
List benefits of portfolio management
helps mitigate individual departments expending monies and labor on single department initiatives
assists in collaborative decision making for organization priorities
removes a portion of organizational politics and deliver clarity across project goals and processes
results in greater organizational stability and realization of projected benefits
Why is initiating a portfolio management process difficult?
portfolio managers must sometimes convince leaders these processes are best for their business
List benefits of portfolio management in healthcare environments
mitigates uncoordinated, decentralized efforts
improve implementation of myriad organizational initiatives
allows for an efficient sharing of resources, where feasible, and a better appraisal of what needs to be accomplished
provides an avenue for measuring ROI at the highest organizational level
portfolio governance committees
determine priorities and funding
also decide if, when, and how any reprioritizations occur within the respective portfolios, based on resource availability
How can organizations accomplish a strong ROI from each project or program?
outcomes must be measurable, weighted, and reviewed by a governance committee
What does integrating cost, schedules, contingencies, and risk response plans in a group with portfolios allow committees to do?
review projects and programs holistically to mitigate issues before projects are funded or implemented; enables organizations to have more visibility and less uncertainty about upcoming efforts
project manager (PM)
responsible for controlling any project changes that occur, ensuring progress is monitored continuously and that performance is measured periodically
activities include a major focus on project planning, budget allocations, and resource allocations
bring structure to a healthcare environment to ensure projects and programs are delivered on time and on budget and within the set scope and requirements
key role is to bring people and processes together to keep a project moving at an optimal pace and to ensure project deliverables are completed accurately and efficiently within the project deadline
have a responsibility to help stakeholders and staff manage the pace of delivery
obliged to control the project scope so it does not diverge from what has been planned
must update the sponsor and other stakeholders and solicit their help when necessary
need to understand the depth of resource requirements throughout a project or program
scope creep
increase of original scope
should be avoided or managed to avoid delays to project schedules
Why do most IT projects and programs tend to grow in scale and complexity as they progress?
as more stakeholders see details of the project they think of additional ideas
What is the most important aspect of scope creep?
the creation of a scope document
What is essential to have so projects can be effectively managed?
a full understanding of what is in and out of scope
project scope document
used to manage a project’s potential scope creep
should include information about project time, cost, and resources
provides an overview of what the project team is expecting to achieve and how the work will be accomplished
can be used to clarify what stakeholders can expect and what the parameters are for any changes that may be requested (scope creep)
List basic questions PMs can ask RMs before activities begin in order to avoid conflicts with resource allocation
who is responsible for allocation of team members’ time for the project or program?
what role will the RM play on the project, if any?
how will the RM and PM coordinate the work? What is the frequency of this coordination?
Why is not recommended that managers serve a dual role of both RM and PM?
the conflicting needs and goals of each role; RMs must ensure their operational area continues to run in parallel with whatever projects or programs are in progress while PMs must fulfill their duties to make certain nothing gets off track
program manager
tasked with similar roles and responsibilities as PMs
guide organization leaders and multiple projects
responsible for planning, executing, and delivering a program or collection of related projects within the defined program scope and schedule
coordinate activities across the group of projects in their program, which adds a level of complexity, monitor progress of individual projects
skills are typically at a higher level of strategic leadership, cross-functional team coordination, organizational resource negotiation, and communication due to the increased complexity of their responsibilities
portfolio manager
responsible for centralized management of portfolio processes, methods, and structures to ensure successful flow of projects within a portfolio
provides information about projects, programs, and resources within a portfolio to governance committees who will evaluate new requests based on strategic alignment
can help committees determine which projects should be given priority in terms of resource allocation, availability, realistic completion timelines, and project overlap because they should be aware of stakeholder demand and have high-level insight to requirements and deadlines of the projects within the portfolio
play a key role in ensuring project and program risks are known to committees and controlled to avoid poor project selection or delays
What is the ultimate success of a portfolio dependent on?
the performance of individual projects
What should portfolio managers do?
perform a value assessment for each completed project to provide information to leadership about long-term value; requires comparing initial definitions of benefits against actual results
List aspects project management tools should track
project scope determination
timelines
budget
resource assignment
project documentation
PERT charts
used to schedule, organize, and coordinate tasks in a project
use the foundation of an “activity list”
provide a graphical view of a project as a network diagram consisting of numbered “nodes”
preferred by some PMS because they clearly show task dependencies
can be more difficult to interpret, particularly in a complex project
Gantt Charts
a graphical view of the duration of tasks and activities shown as a progression in a timeline