What is scheduling

the process of listing a number of tasks or events in the sequence they will occur. A schedule is a timetable.

2
New cards

Why plan?

cannot schedule without planning first

project can be built on paper first

is a powerful resource management tool

3
New cards

Task/activities

Production

Procurement

Administrative

4
New cards
5
New cards

how is project planning accomplished?

review historical data for similar project

review contract for milestones

6
New cards

production

related to the actual on-site construction of the project

7
New cards

procurement

related to the purchasing and tracking of materials from the supplier to the jobsite

8
New cards

administrative

related to permits, inspections, final approvals, or other government requirement

9
New cards

construction phase

schedules are essential to the succesful coordination of a projects day-to-day operations

10
New cards

preconstruction phase

schedule used to coordinate and control when the owner begins to occupy the facility

11
New cards

schedule types

bar chart

matrix

network

12
New cards

bar charts represent

planned overall length of project

planned duration of each project component

calendar start and finish dates for each project

13
New cards

pros of bar charts

simple and quick to produce

easy to read and understand

good for executive reviews and public meetings

14
New cards

cons of bar charts

does not communicate the interrelationships among project activities

15
New cards

milestones show in?

black diamonds

16
New cards

activity duration defined

amount of time assigned to complete a task

17
New cards

matrix schedule

typically used for repetitive work

18
New cards

network schedule

workhorse of the construction schedule-AKA critical path method (CPM) schedule

19
New cards

pros of network schedule

communicates the interrelationships among the project activities

forces a detailed discussion at the projects outset

20
New cards

cons of network schedule

consumes a lot of resources

requires technical training and experience to develop and maintain

21
New cards

CPM schedule

a completed network schedule means that all work performed on the project has been defined and organized

22
New cards

activities with zero float are defined as

critical activities

23
New cards

float or slack is also calculated by?

the software

24
New cards

activity logic defined

determines the sequence that activities can or will be carried out during construction

25
New cards

schedule logic should consider

safety of personnel

resources of the project

relationships between activities

26
New cards

types of logic

sequential and concurrent

27
New cards

what is project control (PC)?

an effective system allowing the project team to monitor

process of documenting the projects ongoing cost, time, and quality

28
New cards

Why PC?

provides team members with a measure of success of past actions/decisions

provides an opportunity to make course corrections early if needed

29
New cards

Pareto’s law (80/20) rule

80% of the outcome of any project is determined by 20% of it’s included elements

30
New cards

crashing

process of accelerating an activity or multiple activities in the schedule to shorten the overall duration of the project

31
New cards

standard/target VS actuals

PC must have a timely and effective way to measure and report actual progress

32
New cards

key to any reporting process is?

any inconsistency is identified quickly, good reports show variance (deltas or differences)

33
New cards

basic control theory

best be illustrated as a repeating control loop

34
New cards

bottom line

the construction professional must determine the proper level of control that prvides feedback

35
New cards

minimum cost scheduling

establishes the most effective project duration

36
New cards

bottom line in planning

determining the optimum duration for a project is an important step in proper planning

37
New cards

managing project finances

contractors receive income from the owner in the form of invoices

managing cash flow can be difficult bc payments are made in different increments

38
New cards

measuring progress

units completed- floor tiles ex( 1,500 SF or 2,000 SF installed = 75% complete)

39
New cards

trending

looking back at how the project has failed or succeeded, trends are helpful when developing a forecast

40
New cards

forecasting

provides info on the ultimate cost and completion date of project

41
New cards

reporting

process of gathering, recording, and analyzing

42
New cards

documentation

companies establish a formal system of documenting project events

43
New cards

notice to proceed

1st formal communication under a construction contract

44
New cards

contains two basic provisions (notice to proceed)

accepts the bid submitted by the contractor

establishes a start date and completion date

45
New cards

meeting minutes

minutes should be action oriented and kept for all meetings, especially ones involving job progress

46
New cards

meeting minutes should include-

project name

project #

date of the meeting

47
New cards

submittals

certain info is required to be submitted to the design professionals for review and approval

48
New cards

example of submittals

shop drawings

product samples

product literature/data

49
New cards

shop drawings

translate the intent of the design documents into a buildable system, they are detailed and precise so review can be time consuming

50
New cards

tracking shop drawings

person assigned is responsible for making sure they are received from respective trade partner on time

51
New cards

Who was the guest speaker

Sarah Earl from Chevron Phillips Chemical Company

52
New cards

productivity =

earned hrs/burned hrs

53
New cards

daily reports

a record of the day-to-day activities and conditions on the job site

54
New cards

change orders

a change on the project-money, scope, or time

55
New cards

Process of change order

submit a change order

reviewing the form for scope and pricing

if approved, the change becomes apart of the original contract

56
New cards

what can be a major source of disputes

change orders

57
New cards

reasons for a change order

owner-directed change of scope

owner-directed change of material

unforseen site conditions

58
New cards

construction change directive (CCD)

a CDD may be issued by the owner that authorizes a change in the project scope, schedule, or other contract terms

serves as temporary instructions

59
New cards

Application for payment

each owner has specific progress payment requirements

the GC should carefully review the request

request for payments must be signed by the contractor and notarized

60
New cards

what is a schedule of values

written list (usually in tabular form) of the value and amounts of the work

61
New cards

why schedule of values?

provides order/structure

helps expedite payments

62
New cards

consequences of accidents

injury or death

decreased productivity

lower morale

63
New cards

direct cost

medical transportation

healthcare providers

hospital

medications

medical equipment

64
New cards

indirect cost

lost productivity

lower morale

insurance rates

training replacements

lost contracts

65
New cards

experience modification rate (EMR)

used to price workers comp insurance premiums

the average EMR is less than a 1.0 is considered safer than most

66
New cards

OSHA reporting requirements

a death must be reported within 8 hrs

and in patient hospitalization, amputation, or eye loss, 24 hrs

67
New cards

OSHA inspection process

opening conference

walkthrough

closing conference