1/12
For a mound system, what is the minimum depth for the high water table?
10 inches
What is the recommended sand for mound systems?
coarse sand with few fines
What is the purpose of the observation tubes for a mound system?
To look for signs of ponding
Where should observation tubes be placed in a mound system?
1/6, 1/2, 5/6, along the length of the absorption area
A mound system is designed around what type of network?
pressure distribution network
Where are the 2 areas where a mound system might fail?
clogging of sand/aggregate interface
soil ponding or saturation
What is the shoulder slope measurement for a mound system?
3’:1’
What is the shoulder slope measurement for an area fill?
5’:1’
How is a mound system layered from bottom to top?
tilled original soil
approved sand
aggregate
pressure distribution system
1” of aggregate
geotextile synthetic fabric
6” of suitable soil
seed/mulch
What is the shoulder setback for an area fill?
5’
What is the maximum perc rate for use of an area fill?
30
What is the minimum depth to the water table for an area fill?
12 inches
Area fills should not be placed on sites that exceed what slope?
12%