This set of vocabulary flashcards covers essential software project management terminology for planning, estimation, network diagrams, and schedule compression techniques based on the SOFT2301 course materials.

21 Terms

1
New cards

Activity Float (or Slack Time)

The amount of time an activity can be delayed without delaying the project.

2
New cards

Free float

The amount of time a task can be delayed without delaying a successor task.

3
New cards

Total float

The amount of time a task can be delayed without delaying project completion.

4
New cards

Positive float

The most common type of activity float time.

5
New cards

Negative float

Activity float time that occurs when lead time is required.

6
New cards

Zero float

Activity float time associated with activities on the critical path.

7
New cards

Critical Path Method (CPM)

A methodology where activities are represented as nodes and relationships are shown as arrows; it defines the earliest time a project can be completed.

8
New cards

Forward pass

The process used in a network diagram to identify the early start (ES) and early finish (EF) times for every activity.

9
New cards

Backward pass

The process used in a network diagram to identify the late start (LS) and late finish (LF) times for every activity.

10
New cards

Critical Path

The path through a network diagram that has no slack or float; any delay to an activity on this path will delay project completion.

11
New cards

Critical Chain Method

A technique that improves reliability by focusing on resource constraints and protecting the schedule with shared buffers instead of padding individual tasks.

12
New cards

Project buffers

In the Critical Chain Method, durations of extra time added to the end of the project to manage uncertainty.

13
New cards

Feeding buffers

In the Critical Chain Method, durations of extra time added to the end of an individual activity.

14
New cards

Resource Leveling

The process of adjusting a project schedule so resource demand does not exceed resource availability, which may extend project duration or change the critical path.

15
New cards

Schedule Compression

The act of shortening the project schedule without changing the project scope.

16
New cards

Crashing

Shortening activity duration for the least incremental cost by adding resources or paying for overtime.

17
New cards

Fast tracking

Shortening activity duration by performing activities in parallel that were originally planned sequentially, which increases risk.

18
New cards

Schedule Baseline

An accepted and approved version of the project schedule used to compare planned start and finish dates against actual dates.

19
New cards

Gantt Chart

A project schedule representation in bar chart form, such as the example for 'Building a House' spanning from 09/17/2010 to 03/25/2011.

20
New cards

Calculation for Finish Date (Exercise 17)

The formula used to determine when a task ends: FINISH=START+TIME−1\text{FINISH} = \text{START} + \text{TIME} - 1.

21
New cards

Float Calculation Formula

Found by subtracting early finish from late finish (LF−EF\text{LF} - \text{EF}) or early start from late start (LS−ES\text{LS} - \text{ES}).