This set of vocabulary flashcards covers essential software project management terminology for planning, estimation, network diagrams, and schedule compression techniques based on the SOFT2301 course materials.
Activity Float (or Slack Time)
The amount of time an activity can be delayed without delaying the project.
Free float
The amount of time a task can be delayed without delaying a successor task.
Total float
The amount of time a task can be delayed without delaying project completion.
Positive float
The most common type of activity float time.
Negative float
Activity float time that occurs when lead time is required.
Zero float
Activity float time associated with activities on the critical path.
Critical Path Method (CPM)
A methodology where activities are represented as nodes and relationships are shown as arrows; it defines the earliest time a project can be completed.
Forward pass
The process used in a network diagram to identify the early start (ES) and early finish (EF) times for every activity.
Backward pass
The process used in a network diagram to identify the late start (LS) and late finish (LF) times for every activity.
Critical Path
The path through a network diagram that has no slack or float; any delay to an activity on this path will delay project completion.
Critical Chain Method
A technique that improves reliability by focusing on resource constraints and protecting the schedule with shared buffers instead of padding individual tasks.
Project buffers
In the Critical Chain Method, durations of extra time added to the end of the project to manage uncertainty.
Feeding buffers
In the Critical Chain Method, durations of extra time added to the end of an individual activity.
Resource Leveling
The process of adjusting a project schedule so resource demand does not exceed resource availability, which may extend project duration or change the critical path.
Schedule Compression
The act of shortening the project schedule without changing the project scope.
Crashing
Shortening activity duration for the least incremental cost by adding resources or paying for overtime.
Fast tracking
Shortening activity duration by performing activities in parallel that were originally planned sequentially, which increases risk.
Schedule Baseline
An accepted and approved version of the project schedule used to compare planned start and finish dates against actual dates.
Gantt Chart
A project schedule representation in bar chart form, such as the example for 'Building a House' spanning from 09/17/2010 to 03/25/2011.
Calculation for Finish Date (Exercise 17)
The formula used to determine when a task ends: FINISH=START+TIME−1.
Float Calculation Formula
Found by subtracting early finish from late finish (LF−EF) or early start from late start (LS−ES).