According to the APM, what is the definition of a project?
A unique and transient endeavour undertaken to bring about change and achieve planned objectives.
How does the APM define project management?
The application of process, methods, knowledge, skills and experience to achieve specific objectives for change.
What are the six core objectives of a project?
Scope, Quality, Cost, Time, Risk, and Benefits.
What is considered the 7th project objective, and why is it not linked to the other objectives?
Safety is the 7th objective; it is not linked to any other objective because it should not be compromised to achieve any of the other objectives.
Who is responsible for ensuring that project benefits are realised?
The Project Sponsor.
What is the APM definition of a programme?
A unique and transient strategic endeavour undertaken to achieve beneficial change and incorporating a group of related projects and business as usual, or steady-state activities.
What is the key difference between project and programme management regarding business as usual (BAU)?
In programme management, BAU relates to change management and benefits realisation, whereas in project management, benefits are achieved by the business using outputs outside the scope of the project.
What is the APM definition of a portfolio?
A collection of projects and/or programmes used to structure and manage investments at an organisational or functional level to optimise strategic benefits or operational efficiency.
How does the meaning of business as usual (BAU) differ between a programme and a portfolio?
In a programme, BAU means management of change and benefits, whereas in a portfolio, BAU means day-to-day activities.
In which lifecycle phase is the business case developed, and who owns it?
The business case is developed at the concept phase and is owned by the Project Sponsor.
What are the cases included in the 5 case business case model?
Strategic, Economic, Financial, Commercial, and Management.
What is the APM definition of success criteria?
The satisfaction of stakeholder needs for the deployment of a project.
How does the APM define a benefit?
A positive and measurable impact of change.
What are the four components of the DOAM test used in benefits management?
Describe (clearly described), Observe (what will be seen as different), Attribute (which operational area it arises in), and Measurement (how it will be measured).
What are the four steps of Steve Jenner's benefits realisation management approach?
What are the four sequential steps of the Benefits Management Process?
Step 1: Identify; Step 2: Define; Step 3: Plan benefits realisation; Step 4: Track & realise benefits.
What three key documents are produced as outputs of benefit definition?
Benefit Profiles, Benefits Register, and Benefits Map.
What is the purpose of a Benefits Map?
It is a diagram showing the inter-dependencies of all benefits (initial, mid, and final), allowing the team to understand which benefits to measure first and enabling early intervention if early benefits are not being achieved.
In an iterative lifecycle deployment baseline, what occurs when work is not achieved within a timebox?
The unachieved work is added to the product backlog.
What is the definition of a critical chain?
The longest sequence of dependent tasks in a project that factors in both logical task dependencies and the availability of constrained resources.
The Project Management Plan (PMP) is the primary output of which project lifecycle phase?
The definition phase.
Who writes the Project Management Plan (PMP), and who approves it?
It is written by the project team under the guidance of the Project Manager, and agreed by the Project Sponsor on behalf of the organisation and the Project Manager on behalf of the team.
Do project logs for Issues, Quality, Change, and Risk form part of the Project Management Plan (PMP)?
No, they do not form part of the PMP; they are separate documents that are updated separately.
What is the purpose of the Risk Management Plan component of the Project Management Plan (PMP)?
It outlines the process for identifying, analysing, and responding to project risks, including methodology, roles and responsibilities, budget, schedule, risk categories, risk appetite, risk thresholds, and the format for the risk register.
Why is a Quality Management Plan included in the Project Management Plan (PMP)?
To ensure project deliverables meet specified requirements and standards, prevent defects, reduce rework, ensure stakeholder satisfaction, and foster continuous improvement and high-quality standards.