Schedule definiton
timetable showing the forecast start and finish dates for activities or events within project, programme or portfolio
Schedule management definition
process of developing and maintaining schedules. It identifies when activities are planned to be performed, considers dependencies and can be used for internal or external resources and activities
What are the benefits of scheduling
Used throughout project to monitor progress, forecast future performance and communicate info to stakeholders, shows team members when tasks are due to be completed, shows key milestones, visual representation of dependencies between tasks
Critical path definition
The sequence of activities through a precedence network from start to finish, the sum of whose durations determines the overall duration.
the longest route through network, determines the earliest possible completion date
Critical path analysis definition
an activity based scheduling technique that determines the overall duration of the identified work based on estimates and logical dependencies
the method of calculating the critical path
What is the process of creating a time schedule (7)
identify all activities for each work package
create a logical sequence of activities
estimate duration of each activity
calculate overall schedule duration
identify and mark milestone
present schedule for review
approve and baseline the schedule
Network diagram definition
a graphical representation of activities and their logical dependencies, used to support the development and analysis of schedules
Float definition
the flexibility with which an activity may be rescheduled
Time boxing definition
used in iterative lifecycle approaches for an iteration with a fixed end date that is not allowed to change, thereby adjusting the scope and quality to deliver on time and to cost