Which characteristic highlights a difference between projects and operations?
Projects are temporary endeavors whereas an organization’s operations are ongoing in nature.
Which objective is true of projects?
They have a unique purpose.
The role of a _____ is to provide direction and funding for a project.
project sponsor
Galaxy, a construction company, buys a particular brand of tiles manufactured by Tiles and Floors, an eco-friendly tile manufacturing company. However, Tiles and Floors has declared bankruptcy and closed down. At present, Galaxy is facing a crisis because there are no other manufacturers in the market that supplies eco-friendly tiles. Which constraint is Galaxy currently facing?
Resources
Steve, an engineer in a construction company, is at present working on a home construction project. The home is being built for the Robinson family, the owners of the home. Steve is working with his project team and support staff to ensure the project is completed on time. In such a scenario, the project sponsor is _____.
the Robinson family
Which knowledge area involves defining and managing all the work required to complete the project successfully?
Project scope management
An important tool for project scope management is _____.
a work breakdown structure
Which tool is most likely to be used in project schedule management?
Gantt charts
Fast tracking is an example of a tool used in _____ management.
schedule
In which of the following areas of management is payback analysis most likely to be used?
Cost
Which tool can best help in efficient communication management?
Kick-off meetings
A _____ is a tool used in risk management.
probability matrix
Which of the following refers to a set of principles that guides decision making based on personal values of what is considered right and wrong?
Ethics
Enterprise project management software is also known as a _____ tool of project management software.
high-end
What is a difference between low-end and midrange tools of the project management software?
Midrange tools are designed to handle larger projects than low-end tools.
Which statement best describes outsourcing?
An organization’s acquisition of goods and services from an outside source
An organization setting up manufacturing and retailing facilities in a new country
An organization selling its products in a market outside its domestic market
An organization’s use of virtual teams with employees located in different countries
An organization’s acquisition of goods and services from an outside source
Which characteristic of organizational culture refers to the degree to which departments within an organization are encouraged to coordinate with each other?
Unit integration
Which of the following best describes a kill point in the project life cycle?
A review of the status of a project at each phase of development to determine if it should be continued, redirected, or terminated
In what type of organizational structure do project managers have the most authority?
Project
In which systems development life cycle do model developers use a model to generate functional requirements and physical design specifications simultaneously?
Prototyping life cycle
Which observation is true of the agile approach to software development?
In the agile approach, requirements must be clearly expressed early in the life cycle.
An agile approach sets scope goals, but leaves time and cost goals flexible.
In the agile method, requirements and solutions evolve through collaboration.
Agile is a predictive model of software development.
In the agile method, requirements and solutions evolve through collaboration.
Which systems development life cycle model assumes that requirements will remain stable after they are defined?
Waterfall life cycle
Projects must operate in a broad organizational environment, and project managers need to consider projects within the greater organizational context. Which approach describes the holistic view of carrying out projects within the context of the organization?
Systems thinkingWhich of the following is true of the project life cycle?
Which of the following is true of the project life cycle?
In the later phases of the project life cycle, the level of uncertainty is usually the highest.
More resources are usually needed during the initial phases of a project than during the middle or final phases.
In the early phases of a project life cycle, resource needs are usually lowest.
It is much more expensive to make major changes to a project during the earlier phases than the latter phases.
In the early phases of a project life cycle, resource needs are usually lowest.
_____ refers to a set of shared assumptions, values, and behaviors that characterize the functioning of an organization.
Organizational culture
Which planning process is associated with project scope management?
Collecting requirements
Which is true about the agile method?
It uses several iterations or deliveries of software instead of waiting until the end of the project to provide a product.
What is often the most difficult and unappreciated process in project management?
planning
The project stakeholder management knowledge area maps to which process group by identifying stakeholders?
initiating
The project management plan is the output of which project planning process?
integration management
What is the main purpose of project plans?
guide project execution
Which is an example of a pre-initiation task?
Identifying stakeholders
Developing a business case for a project
Drafting the project charter
Drawing up a work breakdown structure
Developing a business case for a project
The organization recognizes that a new project exists and completes a project charter during which processes for a new project?
initiating
Which planning process is within the Project Scope Management knowledge area?
Creation of a WBS
Which project would be compatible with the use of the agile approach?
Projects that have more flexible scheduling
The primary purpose of the Initiation Phase is to:
Authorize the project and define its purpose
Which of the following is an output of the Initiation Phase?
Project Charter
The business need in a project describes:
The problem, opportunity, or demand that justifies the project
Which document formally gives the Project Manager authority to use organizational resources?
Project Charter
Which of the following is NOT a common reason for a business need?
Solving a recurring problem
Responding to new regulations
Reducing wait times for a service
Assigning daily work to team members
Assigning daily work to team members
The person who typically provides funding and overall approval for a project is the:
Project Sponsor
Which of the following is NOT typically included in a Project Charter?
Purpose/Business Need
Objectives
High-level Milestones
Detailed task assignments
Detailed task assignments
Stakeholders are any individuals or groups who can affect or are affected by the project.
True
Once stakeholders are identified in the Initiation Phase, the list cannot change later in the project.
False
The Project Charter is sometimes called the “birth certificate” of the project because it authorizes the project to exist.
True