1/25
A comprehensive vocabulary flashcard set covering estimating fundamentals, top-down, bottom-up, and hybrid techniques, influencing factors, and cost categories in project management.
Estimating
The process of forecasting or approximating the time and cost of completing project deliverables.
Top-Down Estimates
Estimates usually performed by senior management that derive project duration and cost from analogy, group consensus, or mathematical relationships.
Bottom-Up Estimates
Estimates typically performed by the people doing the work, based on individual elements found in the work breakdown structure (WBS).
Planning Horizon
An estimating factor where time and cost estimate accuracy improves as individual work packages are defined, whereas long-duration projects increase uncertainty.
Project Complexity
An estimating factor where time to implement new technology expands nonlinearly, and poorly written scope specifications lead to estimating errors.
People
The accuracy of estimates depends on the skills of the people making the estimates. How familiar are they with the task they are estimating?
Structure and Organization
The speed gained from concentrated focus and localized project decisions. This speed comes at an additional cost of tying up personnel full time. Projects operating in a matrix environment may reduce costs by more efficiently sharing personnel across projects but may take longer to complete since attention is divided and coordination demands are higher.
Padding Estimates
The practice of adding extra time and cost to an estimate to reduce the risk of being late, which can compound across project levels and seriously overstate total project duration and cost.
Organization Culture
An organizational factor reflecting differing internal beliefs on estimates, ranging from viewing detailed estimating as not worth the effort to viewing accurate estimates as the bedrock of effective project management.
Responsibility Guideline
The estimating guideline stating that work package estimates should be made by the person(s) most familiar with the task based on experience and best judgment.
Crowdsourcing (Estimating)
The practice of using several people with relevant experience and knowledge of a task to produce more reasonable and realistic cost or time estimates.
Normal Conditions
The baseline estimating assumption that tasks are conducted under standard project conditions using efficient methods and a normal level of resources.
Time Units Guideline
The guideline requiring consistent, specific units of time (such as workdays, workweeks, or calendar days) to be selected early in the development phase of the project network.
Independence Guideline
The estimating guideline directing estimators to treat each work package task as independent of other tasks rather than aggregating tasks or forcing them to fit a predetermined total.
Contingencies Guideline
The guideline stating that individual work package estimates should not include extra allowances; instead, top management establishes a separate contingency fund to cover unforeseen events.
Consensus Methods
A top-down estimating method that uses the pooled experience of senior and middle managers through discussion and debate to reach a collective best-guess estimate for project duration and cost.
Ratio Methods
Top-down approaches (sometimes called parametric) often used in the concept or 'need' phase that employ ratios or surrogates to develop initial duration and cost estimates.
Apportion Methods
A top-down estimating method used when projects closely follow past projects in features and costs, allocating percentages of total project cost down to specific work breakdown structure tasks.
Learning Curves
A top-down estimating phenomenon recognizing that the time needed to perform a task decreases with repetition, particularly in labor-intensive tasks.
Template Methods
A bottom-up estimating method that uses the actual times and costs of past similar projects as a baseline, adjusting them to reflect differences in the new project.
Parametric Procedures (Bottom-Up)
A bottom-up estimating technique that applies specific quantitative ratios or parameters (such as cost per square foot) directly to individual tasks.
Range Estimating
A bottom-up estimating approach best applied to work packages with significant uncertainty, establishing low, average, and high estimates to evaluate range and risk.
Phase Estimating
A hybrid estimating method used under high uncertainty that begins with an overall top-down macro estimate and develops detailed bottom-up estimates phase by phase as the project progresses.
Direct Cost
A project cost that is clearly and directly chargeable to a specific work package.
Direct Overhead
Project costs that closely pinpoint which specific resources are being used in the project.
G&A Overhead
General and administrative organization costs that are not directly linked to a specific project.