Actual quantity of output
Production Department Transfer Price
Internal seller and producer - being paid to transfer it’s product to the sales department, wants higher TP
Recording revenue for production
Arm’s-length standard
Related companies should use prices consistent with what unrelated companies would agree to under similar circumstances
OCED Taxing Pillars
Ensuring large multinational groups pay a minimum level of tax on income in each jurisdiction where they operate
1: Shifts some taxable profit to countries where companies earn revenue, profit margins above 10%
2: Sets a 15% global minimum corporate tax for multinational companies with revenue above €750 million
Selling Department Transfer Price
Internal buyer - paying for product and selling it to outside customers, wants lower TP cost
Cost of the product received
QS
Budgeted quantity of output
NA
Actual number of input required to go into each full output unit
NS
Standard/budgeted input that should be required to go into each full output unit
PA
Actual price paid for input (material unit/labor hour)
Ps
Expected/Standard price to pay per input (material unit/labor hour)
RA
Actual overhead rate
Ex: actual overhead cost per direct labor hour
Rs
Standard overhead rate
Ex: budgeted overhead cost per direct labor hour
MA
Actual sales mix, each channels share of units sold
Ms
Budgeted sales mix, expected channel shares of units sold
Actual Cost
PANAQA What we actually spent to make our actual output.
Total Cost PNQ Example
$5 per pound (P) × 2 pounds per shirt (N) ×100 shirts (Q) = $1,000 Total Cost
Flexible Budget
PSNSQA What we should have spent for the units we actually produced, using standard prices and standard input usage.
Changes with actual output
Static Budget
PSNSQS Everything standard/budget, original budget for the originally planned number of units, will not change
Static Budget Variance
Total difference between the original Static budget and Actual cost
= PSNSQS - PANAQA
Flexible Budget Variance
Difference between the Flexible budget and Actual cost.
At actual output, did we spend more or less than we should have?
= PSNSQA - PANAQA
Sales-Volume Variance
Difference between the Static budget and Flexible budget.
How much did costs change because output differed from the original plan, looking at quantity change?
= PSNSQS - PSNSQA
Price/Rate Variance
Cost difference caused by paying a different P price per input than expected, “Did we pay more or less than expected?”
[PS-PA] * NAQA //
Efficiency/Quantity Variance
Cost difference caused by using more or fewer inputs than allowed for actual output, “Did we use too many/few pounds or labor hour than expected?”
= PSNSQA- PSNAQA // = PS[NS-NA]QA
PNQ Level 1
The overall difference (Static Budget Variance), “How far was actual cost from the original plan?” A-S
PNQ Level 2
Whether the overall difference came from output volume or spending performance, “Was it because we made a different number of units, or because costs at actual output differed from standards?”
Static budget variance= Sales-volume variance + Flexible budget variance
PNQ Level 3
Whether the flexible-budget difference came from input prices or input usage, “Did we pay a different price, use a different amount, or both?”
Flexible budget variance = Price variance + Efficiency variance