1/16
CE 5575 - Lecture 16
define risk
uncertain event/condition that has + or - impact on project if it occurs
define risk management
attempt to recognize/manage potential trouble spots that may occur

what is on the x axis of this Risk Event Graph
defining, planning, executing, delivering
how owners control risk management
risks associated with setting performance expectations
how designers control risk management
risks associated with design
how contractors control risk management
safety, cost, quality, schedule
4 steps of risk management
identification, assessment, response development, response control
step 1 - risk identification
list possible risks, focus on certain risk events, make RBS
step 2 - risk assessment
scenario analysis, qualitative risk consequence rating, risk severity matrix
step 3 - risk response development
project risk register

what is this?
risk break down structure

what is this?
risk severity matrix (probability x impact)
qualitative vs quantitative risk
qualitative = probability x impact, quantitative includes money or time impacts
step 4 - risk response control
monitor triggering events, start contingency plans, look for new risks
what is on a risk register
details, categorizes, % probability, impact, contingency plans, current status
responses for opportunity risk
exploit, share, enhance, accept
responses for threat risks
mitigate, avoid, transfer, accept