1/49
Comprehensive vocabulary flashcards covering Module 9 (Construction Fieldwork) and Module 11 (Construction Disputes) from the Civil Engineering Management and Practice course.
Construction Fieldwork
The physical on-site activities from mobilization to turnover combining labor, materials, equipment, and engineering expertise to build, modify, rehabilitate, and maintain structures.
Field Engineers
Civil engineers who act as the link between design documents and actual construction operations, supervising activities and verifying compliance with plans and specifications.
DPWH Standard Specifications (Blue Book)
A standard technical reference and specification document governing public works and infrastructure projects in the Philippine construction context.
Site Preparation and Mobilization
The initial major fieldwork stage that involves preparing the project area before actual construction begins to establish a safe, organized, and efficient working environment.
Site Clearing
The removal of vegetation, debris, existing structures, and other obstructions to create an open and workable project area.
Surveying and Layout
The process of establishing project boundaries, reference points, and elevations through land surveys and setting out works.
Earthworks and Grading
Excavation, filling, compaction, and grading operations carried out to achieve the desired site elevations and provide foundation stability.
Installation of Temporary Facilities
The setup of site offices, storage areas, access roads, fencing, and temporary utilities required to support construction operations.
Safety and Environmental Controls
Measures implemented on-site—including erosion control, drainage systems, and safety signage—to maintain safety and satisfy environmental regulations.
Foundation Works
Substructure construction activities designed to safely transfer structural loads from the building to the ground.
Soil Treatment
Compaction, stabilization, or replacement of unsuitable soil carried out to improve ground bearing capacity for foundations.
Formworks Installation
The installation of wooden or steel molds and the placement of reinforcing bars according to structural drawings.
Reinforce Placement
The positioning, arranging, and securing of reinforcing steel bars (rebar) in preparation for concrete casting.
Concrete Pouring
The process of mixing, placing, and curing concrete to create stable footings, pads, or piles.
Backfilling
The refilling and compacting of soil around foundation elements after the placed concrete has cured and set.
Structural Works
The construction stage that defines a building's strength, stability, and overall form, encompassing columns, beams, slabs, walls, and structural steel assemblies.
Roofing and Enclosure Works
Activities that shield the structure from weather and environmental exposure, including roof framing, roofing, waterproofing, exterior walls, windows, and doors.
Utilities and Services Installation
The installation phase that provides functional operation to buildings, including plumbing, electrical, mechanical, fire protection, and communication systems.
Plumbing Works
The installation of pipes, fittings, water supply lines, and drainage networks within a facility.
Electrical Works
The installation of wiring, conduit laying, panel boards, and lighting systems throughout a structure.
Mechanical Systems
Building utility components comprising ventilation, air conditioning (HVAC), elevators, and mechanical fire systems.
Fire Protection Systems
Life safety systems including fire detection and alarms, automatic sprinklers, standpipes, fire hose cabinets, and related firefighting equipment.
Finishing Works
On-site trades including plastering, tiling, painting, drywall, and cabinetry that enhance the functionality, appearance, and durability of a structure.
Inspection
The quality process of checking materials, workmanship, dimensions, and compliance against approved project plans and specifications.
Material Testing
Testing concrete, steel, aggregates, and other construction materials to verify their quality, strength, and compliance with standards.
Soil Testing
Testing soil properties such as compaction, bearing capacity, and density to ensure foundation stability.
Workmanship Inspection
Verifying the correct installation, alignment, and finish quality of all completed construction trades.
Structural Inspection
The formal evaluation of structural elements such as footings, columns, beams, and slabs for defects and design compliance.
Site Clean-up and Demobilization
The final stage of fieldwork that clears debris, disposes of waste, dismantles temporary structures, and cleans the facility to prepare for turnover.
Demobilization of Equipment
The removal and transport of construction equipment, machinery, and tools away from the job site at project closeout.
Site Restoration
Restoring affected work areas, regrading ground, and returning the surrounding site to an acceptable physical condition after construction finishes.
Labor Shortages
A field operational challenge wherein a deficit of skilled workers reduces construction productivity and compromises installation quality.
Construction Disputes
Disagreements between project parties concerning their rights, obligations, responsibilities, or expectations under a construction contract.
Republic Act No. 9285
The Alternative Dispute Resolution Act of 2004, a Philippine law approved on April 2, 2004, institutionalizing ADR to promote speedy and efficient dispute resolution outside courts.
Executive Order No. 1008
The Construction Industry Arbitration Law, which established the Construction Industry Arbitration Commission (CIAC) in the Philippines.
Contractual Issues
Disputes originating from poorly drafted contracts, ambiguous provisions, or differing interpretations of contractual requirements and scopes of work.
Delay Claims
Common construction disputes arising from schedule slippages caused by material delivery, payments, other contractors, weather, or design revisions.
Payment Disputes
Disagreements concerning compensation for completed work, such as delayed progress billings, non-payment, retention money releases, or unapproved variation orders.
Quality and Workmanship Issues
Disputes that arise when owners assert that completed work fails to meet contract plans, specifications, or quality standards.
Change Order
A formal modification that involves additions, deletions, or revisions within the original scope of a construction contract.
Extra Work
Construction activities performed entirely outside the original contract scope that generally require additional compensation and schedule adjustments.
Proper Contract Administration
Strict compliance with contractual terms, administrative procedures, and documentation to minimize misunderstandings and prevent disputes.
Alternative Dispute Resolution (ADR)
A legally supported framework under RA 9285 enabling parties to settle disputes speedier, impartially, and more flexibly without a full court trial.
Negotiation
The simplest and most common dispute resolution method, providing a direct, fast, flexible, and cost-effective settlement between parties without a third party.
Mediation and Conciliation
A dispute resolution method where a neutral third party facilitates discussions to help parties reach a voluntary settlement without imposing a decision.
Arbitration
A dispute resolution process where a neutral arbitrator or panel hears evidence and renders a formal decision that is generally binding on the parties.
Construction Industry Arbitration Commission (CIAC)
The primary arbitration body for construction disputes in the Philippines, created under Executive Order No. 1008.
Litigation
Formal judicial court proceedings, typically treated as a last resort in construction disputes due to high costs, public nature, and prolonged duration.
Monetary Damages
Financial compensation paid to an aggrieved party for losses, delays, extra project costs, or liquidated damages caused by another party's breach of contract.
Specific Performance
A legal remedy where a court or arbitral tribunal orders a defaulting party to carry out their contractual obligations rather than merely paying compensation.