4 Types of Schedules
Master Schedule, Milestone Schedule, Look Ahead Schedule, Weekly Schedule
4 Steps of Scheduling
1. Planning
2. Scheduling (Sequencing)
3. Monitoring (Updating)
4. Controlling (Revising & Rescheduling)
3 Core Components of Scheduling
Activities, Durations, & Relationships
Uses of the Master Schedule
Tracking cash flow, application & certificate for payment , project team chart, responsibility schedule
Construction Schedules are...
not only an exhibition of a time specific plan but also of project cash flow (budget) & resource commitment (materials, laborers, equipment)
Purpose of Scheduling a Project
to communicate construction plan, establish production goals, monitor & measure progress, & manage change
Project
unique undertaking aimed at achieving specific predefined goals and objectives
4 Characteristics of a Project
finite, complex undertakings, homogeneous groups of activities, & non-repetitive
Project Life Cycle
conceptual design phase, detailed design phase, construction phase, commissioning phase, closeout phase
commissioning phase
systems incorporated into the project are checked out and calibrated
conceptual design phase
preliminary evaluation of the concept the project is based on
detailed design phase
refinement and expansion of the work performed during the conceptual design phase
closeout phase
when the owner accepts the work as substantially complete and ready for its intended use
project management objectives
time management, resource management, quality management, and risk management
reasons for project planning
eliminating or reducing risk, obtaining a thorough understanding of objectives, formulating a strategy to achieve the objectives using available resources, and to develop a framework for monitoring and controlling
planning and scheduling process
1. identify project activities
2. estimate durations
3. develop project plan
4. schedule project activities
5. review & analyze schedule
6. implement schedule
work breakdown structure
A task-oriented, detailed breakdown of activities that organizes, defines, and graphically displays the total work to be completed
work package
- collection of related items
- lowest component of the WBS that are used as activities to build the project schedule (WP & activity is interchangeable)
uniformat
4 levels, lowest level (1) being the broadest and gets more specific with increasing level
MasterFormat
49 divisions
characteristics of an activity
consume time, have a definable start and finish, consumes resources, responsibilities are assignable, and an activity is measurable
activity categories
administration, mobilization/demobilization, procurement, construction, and start up & testing
4 activity relationships
finish to start (FS), start to start (SS), finish to finish (FF), & start to finish (SF)
finish to start
an activity cannot start unless the previous activity is complete (formwork can't start unless excavation is finished)
lead
negative lag
start to start
activity cannot start unless another activity has started (formwork cannot start unless excavation has started)
finish to finish
activity cannot be completed unless a related activity is finished (concrete placement can't be complete unless inspection is complete)
start to finish
new activity can't finish before an old activity (new shingle delivery can't be complete unless the old shingles have been removed)
parametric estimating methods
factor estimates (category ratio), assembly cost estimating (building component), square foot & cubic foot estimating (production ratio), unit cost method (labor, equipment, material)
determining square foot cost
utilize the gross area and perimeter of the building in the corresponding table to determine the square foot cost
square foot size adjustment price
gross sf x cost multiplier x base cost per sf
perimeter adjustment
(bldg. perimeter - table perimeter) * perimeter adjustment/100
height adjustment
(bldg. height - typ height) x height adjustment
cost per square foot
(perimeter adjustment + height adjustment + base cost per sq ft) * cost multiplier
bldg cost
adjusted cost per sq ft x bldg. sq footage
cost for basement
(adjusted cost per sq ft + basement adjustment) x basement sq ft
total cost
basement cost + bldg. cost
location factor
(location factor A/location factor B) = (cost A/cost B)
index
(index A/index B) = (cost A/cost B)
estimating methods
labor-hour (LH) productivity rate & daily output productivity method (duration = work quantity/production rate)
work quantity
amount of work that must be done as defined in the contract
production rate
daily production rate based on available resources and the environment (productive & idol time)
duration
amount of material/daily output
total labor hours
amount of material x labor hour number on table
duration using labor hours
total labor hours / (crew size x hours a day)
crowding factor
(new crew size/multiplier)/productivity rate from table
multiple starting points
duration x relative duration
or
(duration/# of starting points)/relative productivity
overtime factor
duration in hours / effective work hours
or
(duration in weeks/efficiency) x (normal work week/overtime work week)
adjustments to duration
overtime, larger crew, and multiple starting points