COSC 475 Exam 1

0.0(0)
Studied by 0 people
call kaiCall Kai
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
GameKnowt Play
Card Sorting

1/48

encourage image

There's no tags or description

Looks like no tags are added yet.

Last updated 11:33 PM on 10/4/26
Name
Mastery
Learn
Test
Matching
Spaced
Call with Kai
Chat

No analytics yet

Send a link to your students to track their progress

49 Terms

1
New cards

4 Types of Schedules

Master Schedule, Milestone Schedule, Look Ahead Schedule, Weekly Schedule

2
New cards

4 Steps of Scheduling

1. Planning

2. Scheduling (Sequencing)

3. Monitoring (Updating)

4. Controlling (Revising & Rescheduling)

3
New cards

3 Core Components of Scheduling

Activities, Durations, & Relationships

4
New cards

Uses of the Master Schedule

Tracking cash flow, application & certificate for payment , project team chart, responsibility schedule

5
New cards

Construction Schedules are...

not only an exhibition of a time specific plan but also of project cash flow (budget) & resource commitment (materials, laborers, equipment)

6
New cards

Purpose of Scheduling a Project

to communicate construction plan, establish production goals, monitor & measure progress, & manage change

7
New cards

Project

unique undertaking aimed at achieving specific predefined goals and objectives

8
New cards

4 Characteristics of a Project

finite, complex undertakings, homogeneous groups of activities, & non-repetitive

9
New cards

Project Life Cycle

conceptual design phase, detailed design phase, construction phase, commissioning phase, closeout phase

10
New cards

commissioning phase

systems incorporated into the project are checked out and calibrated

11
New cards

conceptual design phase

preliminary evaluation of the concept the project is based on

12
New cards

detailed design phase

refinement and expansion of the work performed during the conceptual design phase

13
New cards

closeout phase

when the owner accepts the work as substantially complete and ready for its intended use

14
New cards

project management objectives

time management, resource management, quality management, and risk management

15
New cards

reasons for project planning

eliminating or reducing risk, obtaining a thorough understanding of objectives, formulating a strategy to achieve the objectives using available resources, and to develop a framework for monitoring and controlling

16
New cards

planning and scheduling process

1. identify project activities

2. estimate durations

3. develop project plan

4. schedule project activities

5. review & analyze schedule

6. implement schedule

17
New cards

work breakdown structure

A task-oriented, detailed breakdown of activities that organizes, defines, and graphically displays the total work to be completed

18
New cards

work package

- collection of related items

- lowest component of the WBS that are used as activities to build the project schedule (WP & activity is interchangeable)

19
New cards

uniformat

4 levels, lowest level (1) being the broadest and gets more specific with increasing level

20
New cards

MasterFormat

49 divisions

21
New cards

characteristics of an activity

consume time, have a definable start and finish, consumes resources, responsibilities are assignable, and an activity is measurable

22
New cards

activity categories

administration, mobilization/demobilization, procurement, construction, and start up & testing

23
New cards

4 activity relationships

finish to start (FS), start to start (SS), finish to finish (FF), & start to finish (SF)

24
New cards

finish to start

an activity cannot start unless the previous activity is complete (formwork can't start unless excavation is finished)

25
New cards

lead

negative lag

26
New cards

start to start

activity cannot start unless another activity has started (formwork cannot start unless excavation has started)

27
New cards

finish to finish

activity cannot be completed unless a related activity is finished (concrete placement can't be complete unless inspection is complete)

28
New cards

start to finish

new activity can't finish before an old activity (new shingle delivery can't be complete unless the old shingles have been removed)

29
New cards

parametric estimating methods

factor estimates (category ratio), assembly cost estimating (building component), square foot & cubic foot estimating (production ratio), unit cost method (labor, equipment, material)

30
New cards

determining square foot cost

utilize the gross area and perimeter of the building in the corresponding table to determine the square foot cost

31
New cards

square foot size adjustment price

gross sf x cost multiplier x base cost per sf

32
New cards

perimeter adjustment

(bldg. perimeter - table perimeter) * perimeter adjustment/100

33
New cards

height adjustment

(bldg. height - typ height) x height adjustment

34
New cards

cost per square foot

(perimeter adjustment + height adjustment + base cost per sq ft) * cost multiplier

35
New cards

bldg cost

adjusted cost per sq ft x bldg. sq footage

36
New cards

cost for basement

(adjusted cost per sq ft + basement adjustment) x basement sq ft

37
New cards

total cost

basement cost + bldg. cost

38
New cards

location factor

(location factor A/location factor B) = (cost A/cost B)

39
New cards

index

(index A/index B) = (cost A/cost B)

40
New cards

estimating methods

labor-hour (LH) productivity rate & daily output productivity method (duration = work quantity/production rate)

41
New cards

work quantity

amount of work that must be done as defined in the contract

42
New cards

production rate

daily production rate based on available resources and the environment (productive & idol time)

43
New cards

duration

amount of material/daily output

44
New cards

total labor hours

amount of material x labor hour number on table

45
New cards

duration using labor hours

total labor hours / (crew size x hours a day)

46
New cards

crowding factor

(new crew size/multiplier)/productivity rate from table

47
New cards

multiple starting points

duration x relative duration

or

(duration/# of starting points)/relative productivity

48
New cards

overtime factor

duration in hours / effective work hours

or

(duration in weeks/efficiency) x (normal work week/overtime work week)

49
New cards

adjustments to duration

overtime, larger crew, and multiple starting points