About what share of all U.S. electricity did data centers use in 2023?

About 4.4 %

2
New cards

Why do data centers worry grid engineers even though their national share of electricity is only a few percent?

The load is concentrated behind a few substations

3
New cards

In Ireland, data centers used about what share of the national electricity in 2025?

About 23 %

4
New cards

The 1999 claim that the Internet already used 8 % of U.S. electricity was later found to be about eight times too high.

True

5
New cards

As shown in the lecture, about how much power does a typical (non-AI) server rack draw today?

About 9 kW

6
New cards

An AI rack of 2024-2025 draws roughly how much power?

About 120-130 kW

7
New cards

What limits new AI data centers most, as shown in the lecture's thirty-year picture?

Megawatts and the time it takes to connect them

8
New cards

During the 2010s, U.S. data-center electricity use doubled about every two years.

False

9
New cards

Which measure do developers of AI campuses use today, instead of watts per square foot?


Megawatts per campus and the time to power

10
New cards

In the power path of a data center, what does a double-conversion UPS do?

Converts AC to DC, through a battery bus, and back to AC

11
New cards

At about what voltage does the GPU chip itself operate, after the voltage regulators on the board?

About 1 V

12
New cards

What is the main idea of the 800 V DC architecture announced for future AI racks?

Convert once to DC for the whole building, skipping steps

13
New cards

From the grid's side, the servers decide how many megawatts a data center takes, and the UPS decides what it does during a fault.

False

14
New cards

One AI rack draws about 120 kW. An average U.S. home uses about 1.2 kW on average. One rack equals about how many homes?

About 100 homes

15
New cards

In June 2026, about how much large-load demand had been requested in the ERCOT interconnection queue?

About 475 GW

16
New cards

About what share of those ERCOT large-load requests were data centers?

About 90 %

17
New cards

In October 2026, about how much large-load demand was actually running in ERCOT at its peak?

About 5 GW

18
New cards

What is the main message of the ERCOT 'funnel' from requested to running load?

Requested load differs from studied, approved or running load

19
New cards

A load of 100 MW equals the average demand of roughly 8,000 U.S. homes.

False

20
New cards

PUE (power usage effectiveness) of a data center is defined as:

Total facility power divided by IT power

21
New cards

A data center has 100 MW of IT load and a PUE of 1.3. How much power does it take from the grid?

130 MW

22
New cards

The industry-average PUE has kept falling quickly every year since 2018.

False

23
New cards

Why do racks above a few tens of kilowatts move from air cooling to liquid cooling?

A liter of water carries far more heat than a liter of air

24
New cards

Why does the cooling system matter to a power engineer?

Pumps, chillers and fans are motor loads that react to voltage dips

25
New cards

Of these four, which uses the MOST water each year in the United States?

Lawns and other outdoor use at homes

26
New cards

U.S. golf courses use roughly how many times more water than all U.S. data centers use on site?

About 30 times

27
New cards

Nationally, data centers are one of the largest water users in the United States.

False

28
New cards

Which design choice makes the biggest difference to how much water one data center uses?

Closed liquid loop versus evaporative cooling towers

29
New cards

About how much water does one evaporative 100 MW data center use per year, as shown in the lecture?

About 285 million gallons

30
New cards

Texas's last sugar mill, in the Rio Grande Valley, closed in 2024 because there was not enough irrigation water.

True

31
New cards

Which milk needs the most fresh water to produce, per liter?

Cow's milk

32
New cards

About how much fresh water does it take to make 1 liter of almond milk, from farm to carton?

About 371 liters

33
New cards

Most of the water behind almond milk is used in the factory that grinds and rinses the almonds.

False

34
New cards

Why do estimates of the water used for one chatbot answer differ by more than a thousand times?

Some count only on-site cooling, others add power-plant water

35
New cards

Even with the most pessimistic estimate shown in the lecture, one almond-milk latte takes more water than one chatbot answer.

True

36
New cards

Why can the popular figure '140 liters of water per cup of coffee' NOT be compared with a data center's cooling water?

It counts the rain falling on the coffee farms

37
New cards

How long are a data center's UPS batteries typically designed to carry the load?


Seconds to minutes, until the diesels start

38
New cards

What does '2N' redundancy mean in a data center?

All equipment is doubled, each module at most half loaded

39
New cards

What is the design goal of all the equipment 'inside the fence' of a data center?

The servers should never notice a problem on the grid

40
New cards

Which device automatically switches the load between the utility supply and the diesel generators?

The automatic transfer switch (ATS)

41
New cards

A Tier I data center is commonly quoted at only about 26 minutes of downtime per year.

False

42
New cards

What happened in Northern Virginia on 10 July 2024?

After a normal line fault, about 1,500 MW of data centers went to backup

43
New cards

When a large data-center load suddenly disconnects, what does the grid see first?

Frequency and voltage rise, so generators must back off

44
New cards

Why does a data center disconnect from the grid during a voltage dip?

Its UPS moves the servers to batteries and diesels

45
New cards

About how large was the data-center load loss in PJM on 22 July 2026, the largest so far?

About 3,800 MW

46
New cards

Ireland's new grid-code rule asks demand facilities such as data centers to:

Recover at least 90 % of their load within 500 ms after a fault

47
New cards

For a shallow voltage dip (above about 0.8-0.9 pu) a data center can stay connected; only deeper dips make it switch to its internal supply.

True

48
New cards

Why does the power of an AI training cluster swing up and down about once a second?

GPUs compute together, then pause together to exchange results

49
New cards

Which kind of AI workload is much smoother for the grid?

Inference: answering many users' questions

50
New cards

The rate of change of frequency after a power imbalance is RoCoF = f0 x dP / (2H). It becomes larger when:

The system inertia H is larger

51
New cards

In the lecture's simplified model of a low-inertia grid, what almost removed the frequency problem caused by AI power swings?

A large grid-forming battery

52
New cards

ERCOT's new rule PGRR 144 exempts large loads from ride-through tests because they are not generators.

False

53
New cards

What problem appears when many transformers are connected in parallel at a big data-center campus?

The fault current becomes very high

54
New cards

Which measure reduces a too-high fault current at a large campus?

Series reactors or high-impedance transformers

55
New cards

Texas asks for financial security of $50,000 per MW before an interconnection study. How much is that for a 1 GW request?

$50,000

56
New cards

In Texas, new large loads of 75 MW or more pay no fee for their interconnection study.

False

57
New cards

Texas's 2025 law SB 6 sets special rules for loads of at least:

75 MW

58
New cards

In ERCOT's 2026 survey of large loads, which topic was most often left unanswered?

How the site will be cooled

59
New cards

Most of the capacity in ERCOT's 2026 large-load survey was crypto mining.

False

60
New cards

About how many full-time people typically run a large (250,000 square feet) data-center building?

About 50

61
New cards

Where does most of a data center's CO2 come from?

The power plants that supply its electricity

62
New cards

Data-center jobs are mostly during construction; far fewer people are needed to run the finished building.

True

63
New cards

A data center buys enough solar energy over a year to match its use. Why can it still depend on gas?

At night solar produces nothing and the grid supplies the load

64
New cards

What does '24/7 carbon-free energy' mean?

Clean energy in every hour, not only on yearly average

65
New cards

The undamaged unit at Three Mile Island is being restarted to supply a technology company under a long-term contract.

True

66
New cards

Which of these large loads is the MOST flexible for the grid?

Bitcoin mining

67
New cards

Why is AI inference less flexible than AI training?

Users are waiting for the answers

68
New cards

About how much new load could fit into today's U.S. grids if it accepted curtailment about 0.25 % of the time?

About 76 GW

69
New cards

In field tests, AI computing clusters have cut their power by about 25-40 % for the grid without stopping their important jobs.

True

70
New cards

Inverter-based generators have a ride-through standard (IEEE 2800), but large loads have no equivalent standard yet.

True