What is a milestone?
A checkpoint marking completion of activities; has zero duration
What does a Gantt chart show?
Task durations, overlaps, and sequencing over time
Critical path definition
The longest path through a project network that determines shortest completion time
What happens if a critical path task is delayed?
The entire project is delayed
What is slack?
Time a task can be delayed without affecting project completion
How to find total time for parallel tasks?
Take the longest task duration, not the sum
What does a status report include?
Completed tasks, ongoing tasks, delays, and issues
Are status reports only about completed tasks?
No, they include progress, delays, and issues
What makes a good Measure of Success (MoS)?
Quantifiable, testable, objective, and aligned with objectives
Best type of Measure of Success
Real-world testing with measurable data
Why is estimation weaker than testing?
Less accurate and requires strong justification
Is client feedback alone a strong MoS?
No, it is subjective and not quantitative
Objective vs Constraint
Objective is a desired outcome; constraint is a limitation
"Finish in 3 months" is what?
A constraint
Primary vs Secondary research
Primary is collecting your own data; secondary uses existing sources
When is primary research used?
When testing or observing real-world behavior
What is triangulation?
Using multiple sources to support a claim
When can you NOT triangulate?
When the client is a true expert with unique knowledge
CRAAP test - Relevance
If the information fits your purpose and level
Risk formula
Likelihood multiplied by Impact
What determines risk level?
Severity and probability
What is proper escalation?
Reporting to the appropriate level based on severity
Should all incidents be reported to top executives?
No, escalate based on risk level
Purpose of engineering notebook
Record work clearly for replication and legal evidence
Can engineering notebook entries be deleted?
No, they must be permanent
Can an engineering notebook support patents?
Yes, it can provide evidence of work and invention
What is a risk matrix?
A grid showing likelihood versus impact
What is a fishbone diagram?
A cause-and-effect (Ishikawa) diagram
What is a black box diagram?
A system showing inputs, processes, and outputs
What is functional decomposition?
Breaking a system into smaller functions
Observation vs Analysis
Observation is what happened; analysis is interpretation
Should observations include judgment?
No, they should remain objective
Key teamwork skill
Suspending judgment and gathering multiple observations
When multiple answers seem correct, what do you choose?
The most practical and realistic engineering solution
What is usually the best solution in APS112?
Measurable, real-world tested, scalable, and evidence-based
If stuck between answers, what should you pick?
The one that produces measurable data, not opinions
Best Measure of Success method
Test a prototype and collect measurable data
Which is a constraint example?
Completing a project in a fixed time
Which diagram shows cause and effect?
Fishbone diagram
Effect of delaying a critical path task
The entire project is delayed
Best situation to not triangulate a claim
When the client is a true authority with unique knowledge
Best way to test effectiveness of a design
Run real-world tests and collect measurable data
Best action after repeated safety incident
Report to appropriate management level
Best approach when team disagrees on idea
Change communication format (e.g., use diagrams)
Best task description in a status report
Specific and actionable (e.g., research Ontario accessibility standards)
Best way to measure physical effort
Measure force using a device in real conditions