Vocabulary flashcards covering project monitoring, performance dashboards, variance analysis formulas, change control, issue management, collaboration tools, and stakeholder management via PMIS.

29 Terms

1
New cards

Project Monitoring

The ongoing process of collecting data, comparing actual performance against plans, identifying variances, and driving corrective action.

2
New cards

Project Management Information System (PMIS)

A centralized platform where project teams and stakeholders exchange information, coordinate activities, share documents, track progress, and receive real-time alerts to keep projects on course.

3
New cards

Progress Tracking

The continuous measurement of project execution in real time by monitoring completed, ongoing, and delayed tasks, milestone achievement, percentage completed, resource utilization, hours worked, actual expenses, and dependencies.

4
New cards

Performance Dashboard

A visual summary providing real-time visibility of project status in one view, tracking progress, budget, schedule, resources, risks, and issues to facilitate informed decision-making.

5
New cards

Dashboard Status Legend

A standard three-color visual indicator system where Green designates 'on target', Yellow indicates 'needs attention', and Red signifies 'critical / immediate action required'.

6
New cards

Schedule Variance (SV)

A performance metric calculated as Schedule Variance=Actual Progress−Planned Progress\text{Schedule Variance} = \text{Actual Progress} - \text{Planned Progress}, where a negative outcome (such as 60%−80%=−20%60\% - 80\% = -20\%) signifies the project is behind schedule.

7
New cards

Cost Variance (CV)

A financial metric calculated as Cost Variance=Budgeted Cost−Actual Cost\text{Cost Variance} = \text{Budgeted Cost} - \text{Actual Cost}, where a negative outcome (such as ₱200,000−₱230,000=−₱30,000\text{₱}200{,}000 - \text{₱}230{,}000 = -\text{₱}30{,}000) indicates an over-budget condition.

8
New cards

Change Control Process

A systematic five-step workflow in PMIS consisting of: submit request, record in PMIS, perform impact analysis across scope, schedule, and cost, conduct stakeholder review and decision, and update plans if approved.

9
New cards

Issue Management Process

A structured PMIS procedure to resolve project problems comprising: identify and log issue, assess urgency and impact, assign an owner, develop and implement a solution, and monitor progress.

10
New cards

Status Reporting

The formal communication practice designed to report progress with clarity and consistency, track performance, issues, and changes, drive corrective actions, and deliver accurate, timely information to stakeholders.

11
New cards

Core Principle of Project Communication

Delivering the right information to the right person at the right time through centralized PMIS coordination.

12
New cards

Four Functional Pillars of Project Communication

The foundational communication activities in PMIS: Create & collect (announcements and messages), Share & distribute (reports, schedules, and budgets), Store & retrieve (minutes and documents), and Manage & govern (discussions and decisions).

13
New cards

Announcements & Messages

A project information type utilized primarily to align project teams quickly.

14
New cards

Updates & Performance Reports

Project information assets created to show project status, baseline comparisons, and performance variances.

15
New cards

Dashboards & Notifications

Real-time visual feeds and automated alerts intended to prompt timely corrective actions.

16
New cards

Minutes & Documents

Official records stored and retrieved within PMIS to preserve the project historical record.

17
New cards

Discussions & Decisions

Recorded communications within the PMIS governance structure that create ownership and team accountability.

18
New cards

Version Control

A PMIS collaboration capability that manages revisions and protects the single source of truth across project documents.

19
New cards

Stakeholder Management Five-Step Process

The progressive framework for engaging project participants: 1. Identify (who influences or is affected), 2. Analyze (interests, influence, expectations), 3. Plan (choose engagement strategies), 4. Manage (feedback, support, conflict resolution), and 5. Monitor (adjust communication and approach).

20
New cards

Role of PMIS in Stakeholder Management

The seven key administrative and communicative functions performed by PMIS: maintain stakeholder register, classify interest & influence, implement communication plans, distribute targeted reports, collect approvals & feedback, track issues & decisions, and control confidential access.

21
New cards

Elements of a Project Communication Plan

The seven structural components answering essential delivery questions: Stakeholder (who), Information (what), Purpose (why), Method (how), Frequency (when/how often), Owner (preparer/deliverer), and Feedback (response handling).

22
New cards

Six Core Benefits of Effective PMIS Communication

The collaborative drivers of project success: Coordinate (stronger teamwork), Inform (timely, consistent updates), Engage (participation and trust), Clarify (less duplication), Decide (faster problem-solving), and Account (transparency and ownership).

23
New cards

Schedules, Budgets & Tasks

A project information category managed within PMIS specifically intended to coordinate delivery.

24
New cards

Six Team Collaboration Features in PMIS

The suite of collaborative tools consisting of:

  1. Shared workspace
  2. Task assignments
  3. Co-editing
  4. Discussion & messaging
  5. Virtual meetings
  6. Version control
25
New cards

PMIS Impact on Remote Teams

Treats geographic distance as a design constraint rather than a delivery delay by keeping locations synchronized in real time, maintaining a single source of truth, and shortening response cycles.

26
New cards

Key Project Stakeholder Groups

The six main entities identified and managed in PMIS: sponsors, clients, teams, suppliers, agencies, and users.

27
New cards

Root Causes Detected by Variance Analysis

Underlying operational drivers identified through PMIS tracking, primarily project delays, resource shortages, and unexpected issues.

28
New cards

PMIS Change Control Practical Example

A client requests a facial recognition attendance feature, prompting the team to evaluate the impact on scope, schedule, and cost in PMIS before seeking approval.

29
New cards

PMIS Issue Management Practical Example

A developer suddenly resigns, requiring the problem to be logged into PMIS, assessed for urgency, and resolved via immediate task reassignment.