1/15
Looks like no tags are added yet.
What is utilization?
The fraction of time a workstation or individual is busy over the long run
how can you compute resource utilization?
a. Both B and C
What is throughput?
The number of units or tasks that are completed per unit time from a process
What is a bottleneck?
The work activity that effectively limits the throughput of the entire process
What is Little’s Law?
At any moment, people, orders, jobs, documents, money, and other entities that flow through processes are in various stages of completion and may be waiting in queues
What is the formula for Little’s Law?
Work-in-progress = throughput x flow time
What is flow time?
The average time it takes to complete one cycle of a process
What does a queueing system consist of?
Customers that arrive for service, one or more severs that provide the service, and a queue of entities that wait for service if the server is busy
What are the three common queueing configurations?
One queue feeding multiple servers, multiple queues with their own servers, and several queues in series
Why is it important to understand queues?
To analyze processes, predict performance, and better allocate resources
What do queueing models help managers understand?
Waiting times, queue lengths, and how long machines or servers are idle
What is the theory of constraints?
A set of principles that focuses on increasing total process throughput by maximizing the utilization of all bottleneck work activities and workstations
What is a constraint when it comes to the theory of constraints?
Anything in an organization that limits it from moving towards or achieving its goal
What is nonbottleneck work activity?
One in which idle capacity exists
What is a nonphysical constraint?
An environmental or organizational, such as low product demand or an inefficient management policy or procedure
True or false: Inflexible work rules, inadequate labor skills, and poor management are all forms of constraints
true