Chapter 3 Prgram Management tools

0.0(0)
Studied by 0 people
call kaiCall Kai
learnLearn
examPractice Test
spaced repetitionSpaced Repetition
heart puzzleMatch
flashcardsFlashcards
GameKnowt Play
Card Sorting

1/83

encourage image

There's no tags or description

Looks like no tags are added yet.

Last updated 6:00 PM on 10/14/26
Name
Mastery
Learn
Test
Matching
Spaced
Call with Kai
Chat

No analytics yet

Send a link to your students to track their progress

84 Terms

1
New cards

Technology Readiness Assessment (TRA)

A systematic, metrics-based process assessing the maturity of, and technical risk associated with, critical technologies in acquisition programs.

2
New cards

Critical Technology

Technology posing major technical risk during development, especially during the Engineering and Manufacturing Development (EMD) phase

3
New cards

Breadboard

Integrated components configured for laboratory use to demonstrate concept feasibility and technical principles. Resembles final system in function only.

4
New cards

Model

A functional form of a system, generally reduced in scale, near or at operational specifications, sufficiently hardened to demonstrate technical and operational capabilities

5
New cards

Prototype

A physical or virtual model used to evaluate technical/manufacturing feasibility or military utility

6
New cards

Relevant Environment

A testing environment simulating the most important and most stressing aspects of the operational environment

7
New cards

Operational Environment

An environment addressing all operational requirements and specifications (including packaging, platform, and environmental stress)

8
New cards

Low Fidelity

Representative model providing only first-order information (used for trend analysis)

9
New cards

High Fidelity

Addresses form, fit, and function; validates system specifications in an integrated laboratory setting

10
New cards

TRL 1 (basic principles observed and reported)

Scientific research begins transitioning into applied R&D (paper studies)

11
New cards

TRL 2 (technology concept/application formulated)

Invention begins; practical applications conceived. Speculative; supported by analytic studies

12
New cards

TRL 3 (analytical & experimental proof of concept)

Active R&D initiated. Analytical studies and laboratory experiments validate separate unintegrated elements

13
New cards

TRL 4 (component/breadboard validation in LABORATORY)

Basic components integrated to confirm they work together (LOW FIDELITY), ad hoc hardware)

14
New cards

TRL 5 (component/breadboard validation in RELEVANT ENVIRONMENT)

Significant fidelity increase; tested with realistic supporting elements in simulated environment

15
New cards

TRL 6 (system/subsystem model or prototype in RELEVANT ENVIRONMENT)

Major milestone step: Representative model/prototype testing in relevant/simulated operational environment (REQUIRED for MILESTONE B)

16
New cards

TRL 7 (system prototype demonstration in OPERATIONAL ENVIRONMENT)

Prototype near or at planned operational system demonstrated in operational environment (testbed aircraft, vehicle, space)

17
New cards

TRL 8 (actual system completed and qualified through test & demonstration)

True development complete; developmental test and evaluation (DT&E) confirms system meets design specifications

18
New cards

TRL 9 (actual system proven through successful mission operations)

Operational use under ,is soon conditions (OT&E reports, actual combat/field deployments)

19
New cards

Integrated Master Plan (IMP)

Event-based - Not calendar-based

Structured around major program events, accomplishments, and narrative completion criteria

20
New cards

Integrated Master Schedule (IMS)

Time-based - Calendar-driven - Networked schedule

Expands directly from IMP events and criteria down to discrete wire packages, planning packages, task durations, and dependencies

A “living document” continuously updated throughout project execution

21
New cards
  1. Identify Tasks


Decompose WBS into discrete tasks with defined starts, finishes, costs, and deliverables

22
New cards
  1. Sequence Tasks


Establish logical relationships using network diagrams

23
New cards

Mandatory Dependencies (Hard Logic)

Inherent physical/technical requirements (foundation before framing)

24
New cards

Discretionary Dependencies (Soft Logic)

Preferred order based on best practices or organizational policies

25
New cards

External Dependencies

Restrictions outside program control (environmental approval, test range availability)

26
New cards
  1. Determine Resource Requirements


Calculate necessary labor categories, equipment, and facilities

27
New cards
  1. Estimate Task Durations


Establish work days required based in effort and available personnel

28
New cards
  1. Construct Schedules


Perform forward and backward passes to establish critical path, float, and baseline dates

29
New cards

Finish-to-Start (FS)

Successor cannot start until predecessor finishes (STANDARD accounts for 90% of links)

30
New cards

Start-to-Start (SS)

Successor cannot start until predecessor starts

31
New cards

Finish-to-Finish (FF)

Successor cannot finish until predecessor finishes

32
New cards

Start-to-Finish (SF)

Successor cannot finish until predecessor starts (extremely rare; avoid)

33
New cards

Lag

A planned delay inserted between tasks

34
New cards

Lead (Negative Lag)

Accelerating a successor before predecessor completion. AVOID entirely (target=0) because it distorts float and masks critical path risks

35
New cards

Horizontal Traceability

Demonstrates that detailed tasks follow a logical sequence across time and account for predecessor/successor handoffs

36
New cards

Vertical Traceability

Demonstrates data consistency across all hierarchy levels

37
New cards

Integrated Baseline Review (IBR)

A joint government-contractor review assessing baseline realism, scope coverage, logic, and risk. Ni later than 180 days after contract award or major contract modifications.

38
New cards
  1. Parkinson’s Law


Work expands to fill the time allotted. Workers consume entire durations regardless of capability.

39
New cards
  1. Student Syndrome


Procrastination; delaying full effort until the deadline looms.

40
New cards
  1. Multitasking


Fragmented attention causes inefficiencies across multiple active tasks.

41
New cards
  1. Padded Estimates


Safely buffers get wasted because workers slacken pace knowing a cushion exists.

42
New cards
  1. Successor Task Bottlenecks


Downstream teams are unready or unable to accept early deliverables.

43
New cards

Float Formula

Late Finish (LF) - Early Finish (EF)

44
New cards

Total Float

Time an activity can slip without delaying the overall project completion date.

45
New cards

Free Float

Time an activity can slip without delaying any successor task.

46
New cards

Critical Path

The sequence of tasks with the longest total duration and least float (determining minimum project time)

47
New cards

Analogy

Compares new system directly to a single historical system using subjective adjustments (Very early, Fast, Inexpensive, High cost risk)

48
New cards

Parametric

Uses regression analysis on historical database to create Cost Estimating Relationships (CERs) (Early stages, fast, dependent on database accuracy)

49
New cards

Engineering (Bottom-Up)

Detailed cost buildup at lowest WBS level using drawings, bills of materials, and labor standards (Late development EMD, Highly Detailed, Very Costly and Time-Consuming)

50
New cards

Actual Costs (Extrapolation)

Extrapolates historical costs from prototype, test articles, or early production lots using learning curves. (Late Phases, Highest accuracy)

51
New cards

Direct Costs

Labor & Materials - Traced directly to the product

52
New cards

Indirect Costs

Overhead, G&A

53
New cards

Raw Materials

Sheet metal, plastics, & bar stock

54
New cards

Purchased Parts

Standard vendor parts (switches, fasteners, batteries)

55
New cards

Commercial Items

Off-the-shelf items sold commercially (Chips, Boards)

56
New cards

Interdivisional Transfers

Items transferred across company divisions; priced at cost without profit

57
New cards

Subcontracted Items

Major subassemblies built to prime specifications (engines, landing gear)

58
New cards

Loading Factors

Adders for consumables, excess usage (scrap/spoilage), obsolescence, and inventory discrepancies

59
New cards

Decrement Factor

Downward adjustment applied to subcontractor quotes to reflect historical savings won during negotiations

60
New cards

Recurring Costs

Repetitive costs that vary with quantity produced (fabrication, assembly, operational configuration testing, sustaining engineering)

61
New cards

No recurring Costs

One-time or non repetitive development cost that generally do not vary with quantity (R&D, tooling design, test fixtures, initial qualification, software architecture)

62
New cards

Divergent Phase (Open)

Brainstorm broadly; withhold evaluation; encourage wild ideas; emphasize quantity over quality; allow ideas to grow

63
New cards

Convergent Phase (Focus)

Use logic & methodical screening; define explicit evaluation criteria; avoid rushing to premature closure; select & strengthen ideas

64
New cards

Structured

Round-robin turn-taking. Guarantees equal participation, but lacks spontaneity

65
New cards

Unstructured

free-flow discussion. High synergy, but risks dominance by aggressive personalities

66
New cards

Silent (Brainwritting)

Ideas written on cars/sticky notes without speaking. Eliminates interpersonal pressure & debating generation

67
New cards

Cause & Effect Diagram (Ishikawa/Fishbone)

Identifies root causes of a specific failure or defect (People, Product, Process, Equipment)

68
New cards

Force field Analysis

Weighs forces pushing toward a goal (Driving Forces +) against forces blocking it (Restraining Forces - )

69
New cards

Histogram

Displays frequency distribution of continuous variables

70
New cards

Scatter Diagram

Identifies mathematical/statistical correlation between two variables(Positive slope/direct, Negative slope/inverse, or circular dispersion/no correlation

71
New cards

The Prioritization Matrix

Compares alternatives using weighted scores across criteria (Cost, Schedule, Performance)

72
New cards

Affordability Constraints

The highest scoring option may not be selected if it breaches a hard constraint (budget ceiling/weight limit)

73
New cards

Trade-off Space

If an alternative delivers superior operational value but exceeds an individual component budget, PMs must explore trade-offs across other system areas before finalizing

74
New cards

Affinity Diagram

Organizes high volume of brainstormed items into natural thematic clusters (group ideas silently without discussion

75
New cards

Pairwise Ranking

Prioritizes a small list of items through direct head-to-head comparisons

76
New cards

Pareto Chart

Isolates the “vital few” root causes from the “trivial many” (80/20 Rule) , vertical bars ordered in descending order

77
New cards

Oval Symbol

Terminator (start/end trigger)

78
New cards

Rectangle

Process activity/step

79
New cards

Diamond

Decision Point (branching Yes/No)

80
New cards

Circle

Connector/Jump to another page

81
New cards

Deployment Flowchart (swimlane)

Distributes steps into horizontal or vertical lanes representing departments or roles. Pinpoints handoffs, gaps, and redundant work

82
New cards

Nominal Group Technique (NGT)

Eliminates peer pressure by having individuals rank ideas independently before tallying

83
New cards

Weighted Multi-Voting

Participants allocate a fixed budget of points across ideas. A voting ceiling prevents individual participants from distorting results

84
New cards

Responsibility Assignment Matrix (RAM/RACI)

Maps specific tasks to individuals or roles using responsibility designations (Primary, Second, Review, Input)