This set of vocabulary flashcards covers key project management terms from Lesson 3, including scope management, breakdown structures (WBS and DBS), scheduling methodologies like PDM, CPM, and CCM, and essential planning phase artifacts based on PMBOK and PM² standards.
Scope (PMBOK)
The sum of the products, services, and results to be provided as a project.
Product scope
The features and functions that characterize a product, service, or result.
Project scope
The work performed to deliver a product, service, or result with the specified features and functions.
Scope statement
A short description of what needs to be accomplished in a project, presenting the major objectives, deliverables, and justification in one or two phases.
Acceptance criteria
A set of conditions that is required to be met before deliverables are accepted.
Deliverable
Any unique and verifiable product, result, or capability to perform a service that is required to be produced to complete a process, phase, or project.
Project exclusion
Generally identifies what is excluded from the project to help manage stakeholder expectations by explicitly stating what is out of scope.
Constraints
A limiting factor that affects the execution of a project or process.
Assumptions
A factor in the planning process that is considered to be true, real, or certain, without proof or demonstration.
Work Breakdown Structure (WBS)
A hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the required deliverables.
Work package
The work defined at the lowest level of the WBS for which cost and duration can be estimated and managed.
Deliverables Breakdown Structure (DBS)
A hierarchical tree of deliverables and sub-deliverables used to identify and document the full set of deliverables (both project and project management) that comprise the project.
Decomposition
A technique used for dividing and subdividing the project scope and project deliverables into smaller, more manageable parts.
Expert judgement
Judgment and expertise provided by any group or individual with relevant training, knowledge, or experience used to decompose project deliverables or reconcile breakdown opinions.
Rolling wave planning
A technique where the project management team waits until a deliverable or subcomponent to be accomplished far into the future is agreed on before developing the details of the WBS.
100 percent rule
The principle that the total of the work at the lowest levels of the WBS should roll up to the higher levels so that nothing is left out and no extra work is performed.
Precedence diagramming method (PDM)
A technique used for constructing a schedule model in which activities are represented by nodes and are graphically linked by logical relationships.
Predecessor activity
An activity that logically comes before a dependent activity in a schedule.
Successor activity
A dependent activity that logically comes after another activity in a schedule.
Finish-to-start (FS)
A logical relationship in which a successor activity cannot start until a predecessor activity has finished.
Finish-to-finish (FF)
A logical relationship in which a successor activity cannot finish until a predecessor activity has finished.
Start-to-start (SS)
A logical relationship in which a successor activity cannot start until a predecessor activity has started.
Start-to-finish (SF)
A logical relationship in which a successor activity cannot finish until a predecessor activity has started.
Milestone
A zero-duration (0) checkpoint that signifies an important moment in a project, such as the completion of a major phase or approval of a deliverable.
Gantt Chart
A bar chart showing activity durations as horizontal bars placed according to start and finish dates, listing activities on the vertical axis and dates on the horizontal axis.
Critical Path Method (CPM)
A modelling technique that uses a mathematically based algorithm to calculate the longest necessary path of planned activities from beginning to end.
Critical Chain Method (CCM)
A modelling technique that takes into account resources, their levelling, and the behavior of the Project Manager (PM) when estimating activity durations.