This set of vocabulary flashcards covers key project management terms from Lesson 3, including scope management, breakdown structures (WBS and DBS), scheduling methodologies like PDM, CPM, and CCM, and essential planning phase artifacts based on PMBOK and PM² standards.

27 Terms

1
New cards

Scope (PMBOK)

The sum of the products, services, and results to be provided as a project.

2
New cards

Product scope

The features and functions that characterize a product, service, or result.

3
New cards

Project scope

The work performed to deliver a product, service, or result with the specified features and functions.

4
New cards

Scope statement

A short description of what needs to be accomplished in a project, presenting the major objectives, deliverables, and justification in one or two phases.

5
New cards

Acceptance criteria

A set of conditions that is required to be met before deliverables are accepted.

6
New cards

Deliverable

Any unique and verifiable product, result, or capability to perform a service that is required to be produced to complete a process, phase, or project.

7
New cards

Project exclusion

Generally identifies what is excluded from the project to help manage stakeholder expectations by explicitly stating what is out of scope.

8
New cards

Constraints

A limiting factor that affects the execution of a project or process.

9
New cards

Assumptions

A factor in the planning process that is considered to be true, real, or certain, without proof or demonstration.

10
New cards

Work Breakdown Structure (WBS)

A hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the required deliverables.

11
New cards

Work package

The work defined at the lowest level of the WBS for which cost and duration can be estimated and managed.

12
New cards

Deliverables Breakdown Structure (DBS)

A hierarchical tree of deliverables and sub-deliverables used to identify and document the full set of deliverables (both project and project management) that comprise the project.

13
New cards

Decomposition

A technique used for dividing and subdividing the project scope and project deliverables into smaller, more manageable parts.

14
New cards

Expert judgement

Judgment and expertise provided by any group or individual with relevant training, knowledge, or experience used to decompose project deliverables or reconcile breakdown opinions.

15
New cards

Rolling wave planning

A technique where the project management team waits until a deliverable or subcomponent to be accomplished far into the future is agreed on before developing the details of the WBS.

16
New cards

100100 percent rule

The principle that the total of the work at the lowest levels of the WBS should roll up to the higher levels so that nothing is left out and no extra work is performed.

17
New cards

Precedence diagramming method (PDM)

A technique used for constructing a schedule model in which activities are represented by nodes and are graphically linked by logical relationships.

18
New cards

Predecessor activity

An activity that logically comes before a dependent activity in a schedule.

19
New cards

Successor activity

A dependent activity that logically comes after another activity in a schedule.

20
New cards

Finish-to-start (FS)

A logical relationship in which a successor activity cannot start until a predecessor activity has finished.

21
New cards

Finish-to-finish (FF)

A logical relationship in which a successor activity cannot finish until a predecessor activity has finished.

22
New cards

Start-to-start (SS)

A logical relationship in which a successor activity cannot start until a predecessor activity has started.

23
New cards

Start-to-finish (SF)

A logical relationship in which a successor activity cannot finish until a predecessor activity has started.

24
New cards

Milestone

A zero-duration (00) checkpoint that signifies an important moment in a project, such as the completion of a major phase or approval of a deliverable.

25
New cards

Gantt Chart

A bar chart showing activity durations as horizontal bars placed according to start and finish dates, listing activities on the vertical axis and dates on the horizontal axis.

26
New cards

Critical Path Method (CPM)

A modelling technique that uses a mathematically based algorithm to calculate the longest necessary path of planned activities from beginning to end.

27
New cards

Critical Chain Method (CCM)

A modelling technique that takes into account resources, their levelling, and the behavior of the Project Manager (PM) when estimating activity durations.