Aggregate operations plan
A plan for labor and production for the intermediate term with the objective to minimize the cost of resources needed to meet demand.
Sales and operations planning
The process that companies use to keep demand and supply in balance by coordinating manufacturing, distribution, marketing, and financial plans.
Long-range planning
One year or more.
Short-range planning
From a day to six months.
Production rate
Number of units completed per unit of time.
Workforce level
Number of workers needed in a period.
Yield management
Given limited capacity, the process of allocating it to customers at the right price and time to maximize profit.
back order costs
hard to measure ; include costs expediting, loss of customer goodwill, and loss of sales revenues from resulting backordering or costs incurred by a business when it is unable to immediately fill an order and promises the customer that it will be completed with a later delivery date.
chase strategy
match the production rate to the order rate by hiring and laying off employees as the order rate varies ; success depends on having a pool of easily trained applicants to draw on as order volume increases ; employees might slow down out of fear of being laid off when existing orders are completed
level strategy
maintain a stable workforce working at a constant output rate. shortages and surpluses are absorbed by fluctuating inventory levels, order backlogs, and lost sales.
employees benefit from stable work hours at the cost of potentially decreased customer service levels and increased inventory costs
possibility of inventoried products becoming obsolete
inventory
All the money that the system has invested in purchasing things it intends to sell (Goldratt's definition).
q system (fixed order)
An inventory control model where the amount requisitioned is fixed and the actual ordering is triggered by inventory dropping to a specified level of inventory.
p system (fixed time)
An inventory control model that specifies inventory is ordered at the end of a predetermined time period. The interval of time between orders is fixed and the order quantity varies.
newsvendor model
if person does not put enough papers in the stand, some customers will not be able to purchase a paper, and the newsperson will lose the profit associated with those sales
on the other hand, if too many papers are placed in the stand, the news person will have paid for papers that were not sold during the day, lowering profit for the day
decoupling point
where inventory is carried and allows the "upstream" part of the supply chain to operate relatively independent of the "downstream" part
ordering costs
managerial and clerical costs to prepare the purchase or production order ; all details such as counting items and calculating order quantities ; also costs associated with maintaining the system needed to track orders
holding or carrying costs
Costs for storage, handling, insurance, pilferage, breakage, obsolescence, depreciation, taxes, and the opportunity cost of capital ; high holding costs favor lower inventory levels and frequent replenishment
set-up or production change costs
to make each different product involves obtaining the necessary materials, arranging specific equipment set ups, filling out required papers, apportarietly charging time and materials, and moving out the previous stock of material
shortage costs
when the stock of an item is depleted, an order for that item must either wait until the stock is replenished or be canceled
stock out
when demand is not met and the order is canceled
backorder
order is held and finished on a later date when the inventory for the item is replenished
safety stock
The amount of inventory carried in addition to the expected demand.
independent demand
The demands for these items are unrelated to each other, or to activities that can be predicted with certainty.
dependant demand
The need for an item is a direct result of the need for some other item, usually an item of which it is a part. Also, when the demand for the item can be predicted with accuracy due to a schedule or specific activity.
Economic Order Quantity (EOQ)
the optimal order size to minimize the sum of ordering, carrying, and stockout costs
An inventory control model where the amount requisitioned is fixed and the actual ordering is triggered by inventory dropping to a specified level of inventory.
Reorder point (R)
An order is placed when inventory drops to this level.
inventory turn
The cost of goods sold divided by the total average value of inventory. A measure of the expected number of times that inventory is replaced each year.
cycle counting
A physical inventory taking technique in which inventory is counted on a frequent basis rather than once or twice a year.
ABC inventory classification
Divides inventory into dollar volume categories that map into strategies appropriate for the category.
A. high dollar volume ( top 15%)
B. moderate dollar volume (35%)
C. low dollar volume (50%)
Material requirements planning (MRP)
The logic for determining the number of parts, components, and materials needed to produce a product.
time fences
periods of time having some specified level of opportunity for the customer to make changes
Available to promise
A feature of MRP systems that identifies the difference between the number of units currently included in the master schedule and the actual (firm) customer orders.
Master production schedule (MPS)
A time-phased plan specifying how many of each end item the firm plans to build and when.
Bill-of-materials (BOM)
The complete product description, listing the materials, parts, and components; the quantity of each item; and the sequence in which the product is created.
lot size
production or purchasing quantities used by the MRP system
the part quantities issued in the planned order receipt and planned order release sections of MRP schedule
for in house, they are production quantities of batch sizes
for purchased parts, they are the quantities ordered from the supplier
generally meet part requirements fore one or more periods
lot for lot (L4L)
-Sets planned orders to exactly match the net requirements
-Produces exactly what is needed each week with none carried over into future periods
-Minimizes carrying cost
-Does not take into account setup costs or capacity limitations.
Goldratt
Israeli business management consultant
developed software that scheduled jobs through through manufacturing processes, called OPT or optimized product technology ; scheduling logic was based off of the separation of bottleneck and nonbottleneck operations
Goldratt's Rules of Production Scheduling
1. Do not balance capacity, balance production flow
2. The level utilization of a non-bottleneck resource is not determined by
its own potential but by some other constraint in the system
3. An hour lost at a bottleneck is an hour lost for the entire system
4. An hour saved at a non-bottleneck doesn't improve the system
5. Bottlenecks govern both throughput and inventory in the system
6. Transfer Batch is not necessarily equal to the Process Batch
7. Process Batches should be variable both along their route and in time
8. Priorities can be set only by examining the system's constraints
dollar days
a measurement of the value of inventory and the time it stays within an area
multiply the total value of inventory by the number of days that inventory spends within a department
synchronous manufacturing
A production process coordinated to work in harmony to achieve the goals of the firm.
Goldratt's Theory of Constraints
1) Identify the system constraints (no improvement is possible unless the constraint or weakest link is found)
2) Decide how to exploit the system constraints (make the constraint as effective as possible)
3) Subordinate everything else to that decision (align every other part of the system to support the constraint even if this reduces the efficiency on non constraint resources)
4) Elevate the system constraints ( if output is still inadequate, acquire more of this resource so it no longer ids a constraint)
5) If in the previous steps, the constraints have been broken, go back to step 1, but do not let inertia become the system constraint
( after this constraint problem is solved, bo back to the beginning and start over. This is a continuous process of improvement: identifying constraints, breaking them, and then identifying the new ones that result
bullwhip effect
the phenomenon in supply chains whereby ordering patterns experience increasing variance as you proceed upstream in the chain
distortion of demand and increased volatility that occurs as forecasts and orders move from the retailer up to the manufacturer. When a spike in demand occurs, each party in the supply chain adds additional products to their orders to act as a buffer
drum, buffer, rope
every production system needs some control point or points to control the flow of product through the system
drum
if a system contains a bottleneck, then this is the best place for control, ; called the drum because it strikes the beat that the rest of the system (or those parts that it influences) uses to function
buffer
always keep buffer inventory in front of bottleneck to ensure it always has something to work on
rope
communication back upstream to A what D has produced so that A only provides this amount. Keeps inv from building up, this communication is called a rope
can be formal ( schedule) or informal ( daily discussion)
Capacity-constrained resource (CCR)
A resource whose utilization is close to capacity and could be a bottleneck if not scheduled carefully (Goldratt's definition).
What is OSCM?
The design, operation, and improvement of the systems that create and deliver the firm's primary products and services.
Service vs Product
Product: tangible
Service Intangible
- direct customer involvement in service products process introduces significant variability in both the time it takes and the level of knowledge required by the firms employee
Make to order vs make to stock
Make to order: production environment where the product is built directly from raw materials and components in response to a specific customer order
- keep inventory levels at a minimum
Make to stock: production environment where the customer is served "on-demand" from finished goods inventory
- can be controlled based on the actual or anticipated amount of finished goods inventory
Exhibit 20.2
Independent demand: The demands for these items are unrelated to each other, or to activities that can be predicted with certainty.
dependent demand: The need for an item is a direct result of the need for some other item, usually an item of which it is a part. Also, the demand for the item can be predicted with accuracy due to a schedule or specific activity.

Theory of Contraints
Identify the system constraints (no improvement is possible unless the constraint or weakest link is found)
2) Decide how to exploit the system constraints (make the constraint as effective as possible)
3) Subordinate everything else to that decision (align every other part of the system to support the constraint even if this reduces the efficiency on non constraint resources)
4) Elevate the system constraints ( if output is still inadequate, acquire more of this resource so it no longer ids a constraint)
5) If in the previous steps, the constraints have been broken, go back to step 1, but do not let inertia become the system constraint
( after this constraint problem is solved, go back to the beginning and start over. This is a continuous process of improvement: identifying constraints, breaking them, and then identifying the new ones that result (amethodologyy for identifying the most important limiting factor (constraint)
MRP vs JIT
MRP uses backward scheduling, schedule production through bill of materials
JIT does not allow for flexibility
requires a stable production level
used in repetitive manufacturing environments (CAT)environments
vendors need to be located nearby in order to make smaller more frequent deliveries
What is a bottleneck?
a resource whose capacity is less than the demand placed on it; a point in the production process that slows it down by impeding or interrupting the flow of production
purposes of inventory
1. To maintain the independence of operations
2. To meet variations in product demand
3. To allow flexibility in production scheduling
4. To provide a safeguard for variation in raw material delivery time
5. To take advantage of economic purchase-order size
6. many other domain-specific reasons
relevant costs of aggregate plan
basic production costs - fixed and variable costs, direct and indirect labor costs, overtime compensation
costs associated with changes in the production rate- hiring, training, laying off personnel
inventory holding costs - cost of capital tied up in inventory
Backordering costs - hard to measure, expediting, loss of customer goodwill, loss of sales revenues resulting from back ordering
advantages and disadvantages of Q system (fixed order quantity)
favors more expensive items because the average inventory is lower
requires more time to maintain because every addition or withdrawal is logged
no review period
advantages
more appropriate for important items such as critical repair parts because of the closer monitoring and therefore quicker response to potential stockouts
advantages and disadvantages of P system (fixed time period model)
disadvantages
only the passage of time triggers the model
advantages
has a larger average inventory
expected benefits of MRP by industry type
assemble to stock - high
Make-to-stock - medium
assemble to order - high
make to order - low
engineer to order - high
process - medium