role of the engineering manager ( + 3 main responsibilities)
a professional mentor who guides team and evaluates work - like a supervisor in industry
responsibilities:
- develop professional skills such as writing reports, maintaining an engineering notebook, communicating with clients
- guide project work: review status reports, provide feedback, monitor team progress, and approve deliverables
- manage client communication - all communication with client must be approved by EM
weekly interactions with EM
- short weekly meeting, discussion of project progress, review of documentation, feedback performance
performance review
- assessed by engineering manager
- focus on professionalism, team contribution, communication and work quality
project management + 3 main functions
defined as: the application of skills, tools, and techniques to achieve project goals that meet stakeholder needs
1. planning: what needs to be done, when tasks occur & who is responsible
2. monitoring: tracking progress, deadlines and resources
3. controlling: adjusting schedule, workload and strategy
why project management matters cicirs
Project management helps teams:
- Clarify goals
- Coordinate resources
- Identify risks
- Save time
- Reduce costs
- Improve success rates
These benefits increase the likelihood of delivering a successful project.
definition & purpose of engineering notebook
Definition:
A permanent, chronological record of your engineering work, decisions, and observations. In APS 112, It is a timestamped story documenting your design process and evidence.
Purpose:
It serves as evidence of your work, allowing another engineer to understand your process, reproduce your work and continue your project.
What must be recorded
- dates, design ideas, calculations, sketches, team decisions, research findings, observations, problems encountered, solutions tested
Required Qualities:
- neat, accurate, legible, thorough
Top Characteristics of a Good Engineering Notebook
A strong notebook should include:
Sequentially numbered pages
Clear labels on figures and calculations
Annotated sketches
Measurement and scaling information
Evidence of research
Detailed explanations
Technical drawings
Signatures or verification when required
These elements make the notebook usable and professional.
Status Reports
- a weekly summary of project progress
- ensures alignment between tasks and project schedule
- tasks MUST match the gantt chart
Status reports help teams:
Track progress
Identify problems
Communicate updates
Maintain accountability
Stay on schedule
the document cycle
Draft → Edited version → Proofread version → Feedback from TA → Revisions → Approval by Engineering Manager → Submission to client
This process continues until the document is approved.
client email, addressing client & required content
1. sets up meeting
2. sets the tone for professionalism
- is our first impression as engineers
address: professional title + last name or full name
- must identify course context. uoft, client project
- request meeting & provide at least 3 meeting times
- meeting length 1 hour
- default meeting is in person at a location convenient for the client
- team must book the meting room
client meeting plan
A structured preparation document for your first meeting.
It ensures:
You communicate effectively You understand your client You ask the right questions
audience analysis
- assessing client to communicate at correct level
- use client statement & research
Background
Education
Technical knowledge
Role in the project
Motivation
Do not assume client capabilities.
communication in engineering design
engineering design involves: choice, decisions, transformation
PLR definition & 6 required components
def: The purpose is to coordinate team knowledge and organize the project conceptually and practically
6 required components:
-Identify research focus
-State research question
-Document search strategy
-Provide working link
-Create IEEE citation
-Explain how source informs project
research : serial vs parallel work + why discussion matters
serial work - 1 person working at the time
parallel work - everyone works simultaneously
parallel work requires coordination, communication & non-overlapping times
discussion matters because: "time spent in discussion is time saved on task."
research focus (foci)
a research focus is: an unknown in the client problem that requires investigation
EX. problem: winter alleyways are dangerous
possible research foci: ice prevention methods, material friction, environmental impact
prioritization of research (4 factors)
importance, difficulty, connection to other tasks, required knowledge
CRAAP TEST
currency: is it up to date?
- check publication, updates / revisions, timeliness
relevance: does it directly help the project
- topic match (does it answer questions), level of detail,
authority
- who created? affiliations of author? can credentials be verified? can you find info about author online?
accuracy
- Can you verify any theories/statistics/data provided?
- What are the sources of any theories/statistics/data provided?
- Are artworks, charts and tables clearly labeled and easy to read?
- Is there any information about the methodology used in gathering statistics/data provided or analyzing artworks and topics?
purpose
- What type of document is it? (Different types of documents each have their own purpose)
- Why was the material produced?
- What biases are evident?
properties of good research questions
Clear Focused Answerable Relevant
good vs bad
How do we fix winter safety?
What materials increase traction on icy surfaces in urban environments?
gantt chart + 4 steps to build + def of task
def: a timeline showing tasks and their dependencies
Step 1 — Define tasksStep 2 — Sequence tasksStep 3 — Create timelineStep 4 — Analyze schedule
A task is:
a specific piece of work required to move the project forward
Includes:
owner
start date
finish date
duration
dependencies
This definition comes directly from the lecture.
key gantt chart definitions - dependency, concurrent, milestone, critical path, slack
dependency - one task must finish before another begins (e.g. PR and CDS)
concurrent tasks: can happen at the same time
milestone: a task with 0 duration (e.g. project completion)
critical path.- longest chain of dependent events - determines project finish date
slack - the amount of time a task can be delayed without affecting project completion
Bar position: Start and end time
Bar length: Duration
Arrows: Dependencies
Dotted lines: Slack
Critical tasks: Highlighted
Engineering Estimation
Engineering estimation is a calculated value using information, methods, and data that may be vague, imperfect, or incomplete.
Also called:
back-of-the-envelope
order-of-magnitude
ballpark figure
educated guess
estimation procedure (7 steps)
1 — Understand the problem
2 — Break it into smaller parts
3 — Make assumptions
4 — Estimate values
5 — Perform calculations
6 — Check and refine
7 — Explain reasoning
** State your assumptions **
Types of Estimation Methods (3)
Analogous Estimation
- using similar past data
- eg previous olympics cost 10 billion dollars, new olympics similar cost
Top Down Estimation
- start with big picture then divide into parts
- ex total project cost -> component costs
Bottom Up Estimation
- estimate small pieces first amd them add up to overall
Metric vs MoS
metric: an idea for how to measure an objective (solution independent)
- eg weight (kg), speed (m/s)
measure of success: a test procedure used to evaluate a specific design (solution specific)
key diffference: metric = what to measure , MoS= how to test
choose mOS for most important objective
Engineering design workflow (from client statement -> conclusion
Front matter
Problem definition
Design selection
Proposed design
Measure of Success
Conclusion
Client meeting 1
purpose: gather info
we: ask questions and understand problem
client meeting 2
purpose: reach agreement
client must approve: problem definition, design requirements
Engineering argument (SEE)
statement
evidence
explanation
Example
Statement:
This design improves safety.
Evidence:
Slip rate reduced by 30%.
Explanation:
Lower slip rate means safer walking.
reverse engineering
Reverse engineering is the process of analyzing an existing system by taking it apart — physically, logically, or conceptually — to understand how it works and improve or replicate it.
"Look at existing solutions so your design decisions are informed, not random."
4 practical steps of reverse engineering
1. Define the design
- What is the purpose?
- Who are the users?
- What constraints exist?
2. Make operational observations
- How does it respond to inputs?
- How well does it meet objectives?
3. Methodical disassembly & documentation
- Materials
- Components
- Measurements
- Function of each part
4. Reassemble and test
- Does it still work?
- What did you learn?
benefits of reverse engineering
helps with
- competitor analysis
- idea generation
- improving designs
- innovations after patents expire
prototyping
def of prototype:
- an early, testable version of a product, system or process
purpose:
- test function, get feedback & reduce risk in design decisions
iterative design look
test feasibility -> explore tradeoffs -> get feedback -> repeat
low vs high fidelity prototypes
low fidelity :
sketches
paper models
simple mockups
fast and cheap
focus on function and flow
high fidelity:
realistic materials
working models
closer to final product
used for performance testing
tradeoff curve - why we don't start with full prototypes
confidence increases as resources increase
- estimation
- modelling
- prototyping
project management trangle , also called triple constraint
COST, TIME / SPEED, SCOPE / QUALITY
two can be optimized, but the third usually takes a hit
PRC : critical path length / minimum project time
calculate each path (dependent tasks back to back) and the longest one is the critical path