Types of Construction?
Residental homes (40-45%) Buildings (commerical) (25-30%) Infrasturcture (20-25%) Industrial Consturction (5-10%)
Owners
Starts project
Starts project, defines need, provides $$, manages process
Public
State/gov, big proj, well-defined procedures, careful finance
Private
Smaller usually, informal process, more innovation/cost efficency/flexibility
Interests: quality, value of product, schedule, and site safety
A/E
Design proj
Selected based on demonstrated ability to do in time frame and good cost
Prep construction docs
Arch design building
Interests: aesthetics, relationships, quality, recognition
General Contractor
Most contracts awarded to GC who manages and subc portions of work
Manages job, keeps on sched, control cost, ensure work is well coordinated and safely done
Coord with owner on all matters
Interests: $$, time, relationship, reputation
Subcontractor
Largest portion industry (64%)
Do the work
CM Firms
Pure Cm firm
No direct relationship to A/E, GC, subC
Prefer to be involved in design and construction process
Oversees entire construction proj on behalf owner
Owner relationship, sched, productivity, quality, safety, orders/claims, cost, coordinate contracts
As GC
Same but 100% work SubC
Trade/Labor Unions:
Formed around crafts and trades
Operated by members have constitutions
Locals serve as contract negotiating body for members in local area
Provide training, pension, hiring calls
Suppliers:
Assist in material and equip selection and asists in prep bids, prep shop drawings
Designers rely on standard specifications and standards
Insurance & Surety Companies:
Insurance provides liability and property insurance
Surety bid bonds, performance bonds, payment bonds
Bank
For C provide working capital so can pay for mats, labor, equip, etc until paid by owner
C earn their progress payments (monthly) and no up front payments are made
Monthly progress reported by C → approved by owner → paid $$
For owner provide short and long term financing
Permitting Agencies and Building authorities:
Rep interests of public safety
Administer publicly funded construction projects
Ensure private construction proj comply with zoning laws and building codes
DBB
hire design professional in charge of prep of design and contract doc
Usually competitive bid or negotiation w C
C in charge of delivery of completed proj
C is only one responsible for work execution
Sequential construction process
Lump sum bids commonly adopted whereby owner assigns risk to C
Trust-based collab between A/E
Pro- well known, cost already defines, good protection for owner, owner not very involved
Con - design not rev for constructability, sequential linear process prevents task overlap, few interactions, construction can’t start till design rdy
Pure Construction Managment (PCM)
Owner hires a design firm and CM firm based on qualification
CM is a professional service
Team concept: owner, CM, & A/E
PCM as facilitator in conflict PCM get paid fixed fee
Does: predesign est, cost and constructability input, award contract, admin contact
GC functioning as CM can easily handle post design est, coordination, and control GMP
May lack predesign est, int during design, contract admin as owner’s rep
A/E functioning as CM’s can easily handle interactions during design, contract admin
May lack accurate cost, construcability info, coord and control, GMP
Pro - one trusted common reference point, great flexibility in sched, small financial risk for PCM
Con - participants must cooperate and communicate well, committed from beginning, small incentive for CM, high risk loss of reputation
CM@R
Contractual relationships between CM and trade contractors
CM does the ones in PCM as well
Packaging construction into seperate contracts
Coordination and control of multiple contracts
Pro - reduced owner risk
Con - owner takes responsibility for design defects/omissions and may not have full contract control
DB (turnkey)
Owner hires D/B firm that does both could also be joint-venture firm
D/B hires SubC
1 contractual team responsible for design and construction function
Owners put more emphasis on schedule
Also referred to as turnkey - could also include land acquisition, financing, startup, and operation facility
Pro - fast track, good interactions between D/B, easier to make change, good for complex stuff
Con - don’t get initial price, could sacrifice quality to profit, may take diff direction than owner wanted
CM/DB
CM does D/B and is control of A/E too
CM oversight D/B
owner contract with DB and CM and then DB and CM can talk DB does subcontractors
IPD
All key stakeholders sign on multiparty contracts before design even starts
AIA defines IPD by:
Multiparty contract, early involvement of all, shared risk and reward, liability waivers between key participants, fiscal transparency, joint project goals
Integrated leadership, design assistance and collaborative software, no-fault working environment
cost vs price
Cost is what it takes in dollars or resources to produce Price is what someone is willing to pay for that
Lump Sum
Firmly fixed final price
Actual cost known before it begins
Minimize risk for owner if proj is well estimated, contractual documents r accurate, and proj is clearly defined
High risk for C
Generally used with DBB & not possible w fast track
High incentive to finish early at low cost
Quantity X Unit price
Prices for defined units
Approx quantities provided by owner - high dependent on accuracy
Payment is based on what is actually installed - owner goes on sites and checks
Reason for usage - uncertainty in the field quantity
C overhead integrated in unit price
Lowest bidder selected
Risk
Price risk more under C control
Length out of C control
Cost Reimbursable Contracts
Fast track proj
Complex
Large risk assumed by owner
Cost + Percentage Fee
Owner pays actual cost + fixed percent fee
High owner risk only if pricing couldn’t be calc any other way and its urgent
No financial insurance
Permits collab at early stages
Cost + Fixed Fee
Cost vary but fee is same
Fee is independent of duration
Used only if $ cldn’t be det
No financial insurance of final cost
High incentive to finish early (same fee regardless of when C finish)
Promotes collab
GMP
Cap/GMP
Contractor assumes additional cost
GMP is defined price for an undefined product
Sim to cost-reimbursable but quality may be sacrificed to avoid going over
Var - usually GM shared savings - below GMP savings r shared between owner and C
competitive bid contracts
Lowest bidder award contract
Traditional method
Time-consuming, involving bidding, bid eval, and review period
Proj constructed w specific quality at lowest price
Formal procedure for public agencies
Two main types
Open: bid open and ready publicly
Closed: no public opening
Contractor est cost along with profit: lump sum, unit price
Loss is absorbed by C if actual cost exceeds contracted amnt
negotiated contracts
Pre selected contractor based on rep and qualifications
Common for priv owners
For fast processes
best value
Used by fed gov and states
Provide uniform set of procurement regulation
RFP (request for proposal)
Price, technical merit, timeliness, budget, eval crit and weights
public private partnership
Allows gov to build facilities that wouldn’t be able to build
Private consortium D/B facility and rents it to public agency till cost + profit r recovered
Labor Cost
Direct cost: costs that actually paid to field workers
Indirect: costs that are additional (pay roll tax, insurance, fringe benefits)
Commonly used approach: calc direct labor cost first add indirect as percent total
Material Cost
Include cost for delivery, storage, and inspection
Contractor may: produce its own materials; use own estimate, purchase the mats from manufacturer and get written quotes including tax, price, etc.
Contractor doesn’t include material cost for: owner-supplied material, owner designated material (allowance), must include the cost for storage handling and installation
Equipment Cost
Diff types of cost rates for diff equip
cost/hour for heavy stuff tractor graders
Cost/unit installed for concrete mixing plants
cost/week or months scaffolds etc
Accuracy of cost estimate depends upon the importance of equipment
Major equipment (cranes)
Very detailed analysis is required how many days and hours needed
Minor equip (power tools, concrete vibrators)
Standard cost allowanced included in est
Minor equipment (hand tools, water hose)
Lump sum allowances as the % of direct labor cost in project overhead
SubC
GC subC some portion of work to subC: includes all quotes from subC, subC and cost det before final bid, but can be det while proj proceeding (up to 3 months in)
GC needs to review the quotations and select SC in time
Owner ←> GC == GC ←>
Project Overhead
All costs that do not pertain directly to any given construction works
Generally 5-10%, GC may have no checklist (cleaning up of site, purchase set up of on site offices, salaries supervisors, consumables )
Markup
Corporate overhead, contingency, and profit
5-20% of total proj cost
Reflects the contractor appraisal between being the lowest bidder vs highest chance of having profit
Factors influencing markup size: need for work, competition, mark conditions, mag of risk and opportunities, relationship with lcient, strat values of project
Methods to assess risk
Put price on uncertainties or risk factors
Based on experience add leeway
Opportunity factors should be leverage as well to get best price possible