What is quality control

Comparing output to standards and correcting unacceptable resuts

2
New cards

What are the 3 phases of QA

Acceptance Sampling → Process Control → Continuous Improvement

3
New cards

What is the optimal amount of inspection

The inspection level that minimizes total inspection and defect costs

4
New cards

Attributes vs Variables

Attributes are counted/classified; Variables are measured

5
New cards

When is centralized inspection preferred

Wehn specialzed equipment or labratory conditions are needed

6
New cards

When should inspection happen before a covering process

Before work hides defects, such as checking plumbing before dry wall

7
New cards

Why is inspection alone insifficent for QC

It detects but doesn’t neccessarily prevent them. Process control help prevent defects

8
New cards

What is acceptace Sampling

Inspecting a sample from a batch to decide whether the batch is acceptable

9
New cards

Process control

Monitoring and correcting a process during production to maintaon quality

10
New cards

Continuous improvement

Continously improving processed to build quality into prodction and prevent defects

11
New cards

Which QA assurance phase is most progressivr

Continuous Improvement bc quality is built into the process

12
New cards

Does increasing inspection always reduce total cost?

No. Inspection costs rise while the cost of passing defects falls. Total cost is minimized at the optimal inpection level

13
New cards

What are the 4 main inspection decisions

  • How much/how often

  • Where in process

  • centralized vs onsite

  • attributes vs variables


14
New cards

Why inspect before a costly or irreverable operation

To catch defected before they cause expenive waste or become impossible to correct

15
New cards

What is the main advantage of on-site inspection

Faster decisions, less disruption, and QA at the source

16
New cards

What is the main trade-off between centralized and on-site inspection

Centralized offers specialized testing ; onsite offers faster feedback and less dsruption

17
New cards

Statistical Process Control ( SPC)

Statistical evalualtion of process output to determine whether a process is in control

18
New cards

Quality of confomance

The extent to which a product or service meets it’s specification

19
New cards

Main question of process control

Is the process stable, with only random variation?

20
New cards

Main question of process capability

Can a stable process consistently meet specifications

21
New cards

Can a process be stable but not capable

Yes. It may operate conistently while producting output outside it’s specifications

22
New cards

Why should process control be assesed before capability

Capability assumes the process is stable; unstable process is not predictable

23
New cards

What is random ( common cause) variation?

Natural Variation caused by numerous minor factors

24
New cards

What is assignable ( special cause variation)

Nonrandom variation with an identfifiable cause

25
New cards

Does every variation require corrective action

No. Normal random variation is expected; Special causes require investigation

26
New cards

Purpose of Sampling in SPC

To periodically collect data and evaluate whether process variation is random

27
New cards

What are the 6 steps of the control processes

  1. Define

  2. Measure

  3. Compare

  4. Evaluate

  5. Correct

  6. Monitor


28
New cards

Ask chat the change the cheatsheet and then make the cheatsheet + finish this chapter today

29
New cards

Control chart

A time-ordered plot of sample statistics used to distinguish random from nonrandom variation

30
New cards

What fo UCL and LCL represent

Upper and loqer control limits defining the expected range of process variation

31
New cards

What does the centre line ( CL) represent

The process average or epected value of the plotted statistic

32
New cards

What does a point outside the control limits indicate

An out-of-control signal suggesting assignable variation that needs investigation

33
New cards

Does a point inside control limits guarentee the process is in control

No. Random patterns may exist even when all points are inside the limits

34
New cards

Can a process be in control but produce defective products?

Yes. It may be stable but unable to meet specifications

35
New cards

Type I error

False Alarm: Concluding a process is out of control when it is actually in control

36
New cards

Type II error

Missed Alarm: Concluding a process is in control when it is actually out of control

37
New cards

Which error is manufacturer’s risk?

Type I bc it can cause unncecessary investigatio or correction

38
New cards

Which error is consumer’s risk

Type II bc a real process problem goes undected

39
New cards

What is a (alpha) for three-sigma control limits under normality

Approx. 0.27%, with 0.135% in each tail

40
New cards

What are control Charts for variables used for?

Monitoring measurable characteristics, such as length, weight, or temperature

41
New cards

What does an X-bar chart monitor?

The central tendency (mean) of a process

42
New cards

What does an R-chart monitor?

Process dispersion ( variability or spread)

43
New cards

If the process average shifts, which chart is most useful

X-bar chart

44
New cards

If the process mean stays constant but variability increases, which chart is most useful?

R Chart

45
New cards

How to calculate a sample range

Maximum observation - Minimum observation

46
New cards

Grand Mean

The average of all sample means

47
New cards

Average range

The average of all sample ranges

48
New cards

A factory takes 25 samples of 4 items each. Which n is used for the constants?

n = 4, not 25

49
New cards

Why shoulf X-bar and R charts be used together?

They monitor different things: the process mean and it’s variabilty

50
New cards

Can X-bar chart appear in control while the R-chart is out of control

Yes. The mean can be stable while variability is excessive

51
New cards

How many samples does the prof reccomend for intial controls

20-25 samples

52
New cards

What should you do if preliminary control limits reveal an out-of-control signal?

Investigate and correct assignable causes, then collect new observations and reassess

53
New cards

What is the difference between p-charts and c-charts?

P-chatr monitors proportion of defective items; c-chart monitors the number of defects per unit

54
New cards

A product has five scratches. How would p-chart and c-chart treat it?

P-chart: 1 defective item

C-chart: 5 defects

55
New cards

What happens when a calculated control-chart LCL is negative?

Set it to zero because negative defect counts or proportions are impossible

56
New cards

What is an important requirement for using a c-chart?

The inspection unit or opportunity for defects must retain constant

57
New cards

What is a run test

A test for nonrandom patterns like a sequence of observations

58
New cards

What is the difference between a trend and cycle

Trend = sustained movement in one direction. Cycle = repreating wave-like movement

59
New cards

What does bias mean on a control chart?

Too many observations occur on one side of the centre line

60
New cards

Can a process be out of control even if all observations fall within control limits?

Yes. Nonrandom patterns can indicate an unstable process

61
New cards

What is process capability

How well a stable process’s natural variation fits within the specification limits

62
New cards

What is the difference between Cp and Cpk

Cp measured potential cabailty based on spead; Cpk also accounts for centering

63
New cards

How do you interpret Cp <1 , =1, >1

<1 : Process wider than specs

=1 : Equal widths

>1 : Process narrower than specs

64
New cards

Can Cp be high while Cpk is low

Yes. The process may have lower variabilty but be off-centre

65
New cards

Can Cpk ever be greater than Cp

No. Cpk ≤ Cp. They are equal when is the process is centered.

66
New cards

5 ways to improve process capability

Simplify, Standardize, Mistake-proof, Upgrade equipment, automate

67
New cards

What do the X and Y axes of an OC curve represent

X= Actual proportion defective; Y = probability of accepting the lot

68
New cards

What happens to acceptance probability as the defect rate increases

It decreases

69
New cards

What happens if the acceptance number c increases while n stays fixed

The sampling plan becomes more lenient, so acceptance probability increases