1/7
Looks like no tags are added yet.
3 days
Notice to the Administrative Authority that the work is ready for inspection.
3 m
Head of water to be filled on each section of piping under water test.
15 mins.
Duration that water shall be kept before the start of inspection.
34.5 kPa
Gauge pressure for air test, equivalent to 254 mm Mercury in height.
15 mins.
Duration that air pressure shall be held during air test without introduction of additional air.
50%
Water piping shall be tested under a water pressure not less than the working pressure under which it is to be used plus ______.
344.5 kPa
Air pressure which may be substituted for the water test.