1
New cards

Capital and operating costs

The up-front expenditure required to build a project, plus its ongoing operations and maintenance (O&M) costs.

2
New cards

Payback period

The number of years required for cumulative savings to repay the initial investment.

3
New cards

Avoided costs

The utility expenses that a PV system allows the system owner to avoid paying.

4
New cards

Internal rate of return (IRR)

A financial metric representing a project's effective annual rate of return.

5
New cards

Levelized cost of energy (LCOE)

The lifetime cost of building and operating a system per unit of energy produced, expressed in $/kWh\$/\text{kWh}.

6
New cards

Cash flow

The movement of money into and out of a project across each year of its operational life.

7
New cards

Derate factors

Multipliers accounting for system losses (such as soiling, wiring, mismatch, and equipment aging) that reduce actual energy output below nameplate capacity.

8
New cards

RETScreen

A clean energy management software tool used for energy efficiency and renewable energy project feasibility analysis.

9
New cards

PVsyst

A comprehensive software package dedicated to solar PV design and detailed yield simulation.

10
New cards

Aurora Solar

A software platform focused on PV design and sales workflow.

11
New cards

HelioScope

A web-based software tool used primarily for commercial and utility-scale PV system design.

12
New cards

System Advisor Model (SAM)

A free performance and financial modeling software package developed by NREL for renewable energy systems.

13
New cards

Sighten

A software modeling platform built to support the solar sales workflow.

14
New cards

Energy Toolbase

A modeling platform specialized in utility rate and financial analysis for solar-plus-storage projects.

15
New cards

Direct costs (SAM)

Hardware and installation expenses that are tied directly to physical equipment, such as modules and inverters.

16
New cards

Indirect costs (SAM)

Project expenses not tied directly to physical equipment, including site assessment, permitting, engineering, and grid interconnection.

17
New cards

OpenEI U.S. Utility Rate Database

An integrated online database from which SAM users can directly download utility rate structures.

18
New cards

Nominal discount rate (SAM)

A financial rate that SAM automatically calculates from the user-entered inflation rate and real discount rate.

19
New cards

Market assessment (Stage 1)

The initial utility-scale PV project stage assessing utility cooperation, grid connectivity, available financial incentives, and state energy production mandates.

20
New cards

Feasibility study (Stage 2)

The second stage of project development evaluating environmental impacts and the quality of the available solar resource.

21
New cards

Site selection (Stage 3)

The third stage of project development analyzing transmission access points, shading, land use, zoning, topography, and soil conditions.

22
New cards

Determine system size (Stage 4)

The fourth project stage involving financial modeling, payback period estimation, financial gain forecasts, predicted energy yields, and emission offsets.

23
New cards

Technology assessment (Stage 5)

The fifth project stage determining the inverter selection, panel type, panel orientation, and racking/mounting systems.

24
New cards

Financing (Stage 6)

The utility-scale project stage securing government loan guarantees, state/federal grant programs, private investments, and Power Purchase Agreements (PPAs).

25
New cards

Commissioning (Stage 8)

The project stage involving municipal inspections, passing electrical and building codes, implementing an operations management plan, and hiring and training personnel.

26
New cards

Power purchase agreement (PPA)

A long-term contract governing the sale of electricity between a project developer and a buyer that stabilizes project revenue over its life cycle.

27
New cards

Crystalline silicon (c-Si)

The dominant photovoltaic material technology used in 80–90%80\text{--}90\% of utility-scale solar projects, available in monocrystalline and polycrystalline forms.

28
New cards

Thin film (CdTe)

Cadmium telluride PV technology that features lower upfront capital costs but significantly lower conversion efficiency and energy output than crystalline silicon.

29
New cards

Block design

A standardized plant layout strategy offering simple planning and cost-efficient construction at the expense of lower overall land area utilization.

30
New cards

Individual design

A customized plant layout strategy that provides high land area utilization and customer flexibility, but involves complex construction logistics.

31
New cards

Past layout optimization metric

Maximizing kWh/Wp\text{kWh/Wp} (yield per installed power) to achieve the goal of getting the most production out of each module.

32
New cards

Present layout optimization metric

Minimizing $/Wp\$/\text{Wp} (capital cost per installed power) to achieve the goal of installing solar generation as cheaply as possible.

33
New cards

Near-future layout optimization metric

Minimizing $/kWh\$/\text{kWh} (LCOE) to find the overall most economic and energy-efficient solution.

34
New cards

Exelon City Solar

A 10 MW10\,\text{MW} PV power plant utilizing 32,29232{,}292 tracking panels on a 41-acre41\text{-acre} brownfield in Chicago's West Pullman neighborhood; the largest urban solar facility in the U.S. at the time of construction.