Name
Mastery
Learn
Test
Matching
Spaced
Call with Kai
Chat

No analytics yet

Send a link to your students to track their progress

41 Terms

1
New cards
What is the principle of levelling in surveying?
Levelling is the operation required to determine the heights of points on the surface of the Earth.
2
New cards
What equipment is necessary for levelling?
1. Level with tripod, 2. Levelling staff, 3. Chain/Tape, 4. Change plate, 5. Staff bubble.
3
New cards
What is the purpose of the telescope in a surveyor's level?
It forms a real image that is focused to lie in the same plane as the diaphragm.
4
New cards
How is parallax minimized in a surveyor's level?
By adjusting the eyepiece and focusing screw to eliminate parallax.
5
New cards
What does a compensating device do in an automatic level?
It corrects for residual mislevelment after the telescope is approximately levelled.
6
New cards
What is the construction material of a standard levelling staff?
Aluminium alloy.
7
New cards
What is the accuracy of a precision levelling staff?
It has an accuracy to 0.1mm when used with a precise level.
8
New cards
What is a level line relative to Mean Sea Level (MSL)?
A curved line at a constant height relative to MSL.
9
New cards
Define horizontal line in relation to a level line.
It is tangential to the level line at a point and perpendicular to the direction of gravity.
10
New cards
What is Mean Sea Level (MSL)?
The mean of tidal heights over a period of time greater than 19 years.
11
New cards
What is Principal Datum Hong Kong (PDHK)?
A reference point for most works in Hong Kong, located 1.230m below MSL.
12
New cards
What is a Benchmark (BM) in surveying?
A point of known elevation above PDHK, typically established on strong vertical surfaces.
13
New cards
What is Temporary Benchmark (TBM)?
A benchmark constructed at specific on-site locations calculated from PDHK.
14
New cards
What does Reduced Level (RL) signify?
The height of a point relative to PDHK.
15
New cards
What is Backsight (BS)?
The first sight taken after the level is set up to a known height point.
16
New cards
What is Foresight (FS)?
The last sight before moving the level, taken to a required point's height.
17
New cards
What is Intermediate Sight (IS)?
Staff readings taken between Backsight (BS) and Foresight (FS).
18
New cards
What is a Change Point (CP)?
The staff position at which a Foresight (FS) and then a Backsight (BS) readings are taken.
19
New cards
What is the first step in field procedure during levelling?
Set up the level at a point where a Bench Mark (BM) can be observed.
20
New cards
How is the first reading (BS) taken?
Using the staff on a point of known Reduced Level (RL).
21
New cards
What method is used to calculate the Height of Collimation (HC)?
HC = Known RL + Staff Reading.
22
New cards
In the Rise and Fall Method, what indicates a 'rise'?
When the second reading is less than the first reading.
23
New cards
In the Rise and Fall Method, what indicates a 'fall'?
When the second reading is greater than the first reading.
24
New cards
What is the allowable misclosure in levelling?
± 5√n mm where n is the number of instrument positions.
25
New cards
When should levelling be repeated?
If the actual misclosure exceeds the allowable misclosure.
26
New cards
What is the importance of a bracket bubble in levelling?
It helps ensure that the staff is held vertically.
27
New cards
What does the term 'collimation error' refer to in levelling?
When the line of sight or collimation is not truly horizontal, causing errors in height measurement.
28
New cards
What is the two peg test used for?
To adjust for collimation error by comparing staff readings taken from two points.
29
New cards
What significant error is corrected during the two peg test?
The inclination error of the collimation line.
30
New cards
What are common errors in levelling equipment?
Collimation error, parallax error, and defects of the staff.
31
New cards
How does staff verticality affect measurements in levelling?
If the staff is not vertical, it can lead to inaccurate readings.
32
New cards
What should be considered when leveling on unstable ground?
Use a change plate to stabilize the setup.
33
New cards
What practice helps detect misclosure in levelling?
Start and finish at points of known height.
34
New cards
What is the role of curvature in levelling observations?
Curvature affects the accuracy of line of sight over long distances.
35
New cards
How does atmospheric refraction affect leveling?
It bends the line of sight downwards, affecting height calculations.
36
New cards
What method can avoid corrections for curvature and refraction?
Reciprocal levelling.
37
New cards
In reciprocal levelling, how is the height difference calculated?
H = ((a1 – b1) + (a2 – b2)) / 2.
38
New cards
What correction is typically applied for curvature?
c ≅ L² / 2R, where L is the distance and R is Earth's radius.
39
New cards
What combined correction for curvature and refraction is considered?
Combined correction = 0.0785 L² * (6/7).
40
New cards
How is the correction for curvature and refraction computed for a 200m distance?
Using the formula combined with the given coefficients.
41
New cards
What is the final step to check accuracy in levelling work?
Ensure that the sum of Back Sight (BS) minus Foresight (FS) equals the difference in levels.